TABLE OF CONTENTS
Page
1.4 Summary
of Construction Works
1.5 Summary
of EM&A Programme Requirements
2.4 Monitoring
Parameters, Frequency and Duration
2.6 Monitoring
Schedule for the Reporting Month
3.4 Monitoring
Parameters, Frequency and Duration
3.6 Monitoring
Schedule for the Reporting Month
4 ENVIRONMENTAL SITE INSPECTION AND AUDIT
4.2 Advice
on the Solid and Liquid Waste Management Status
4.3 Environmental
Licenses and Permits
4.4 Implementation
Status of Environmental Mitigation Measures
4.5 Summary
of Exceedances of the Environmental Quality Performance Limit
4.6 Summary
of Complaints, Notification of Summons and Successful Prosecutions
5.1 Construction
Programme for the Coming Months
5.2 Key
Issues for the Coming Month
5.3 Monitoring
Schedule for the Coming Month
6 ConclusionS AND RECOMMENDATIONS
List of
Tables
Table 1.1 Contact Information of Key Personnel
Table 2.1 Air
Quality Monitoring Equipment
Table 2.2 Locations
of Impact Air Quality Monitoring Stations
Table 2.3 Air
Quality Monitoring Parameters, Frequency and Duration
Table 2.4 Summary
of 1-hour TSP Monitoring Results in the Reporting Period
Table 2.5 Summary
of 24-hour TSP Monitoring Results in the Reporting Period
Table 3.1 Noise
Monitoring Equipment
Table 3.2 Locations
of Impact Noise Monitoring Stations
Table 3.3 Noise
Monitoring Parameters, Frequency and Duration
Table 3.4 Summary of Construction Noise Monitoring Results
in the Reporting Period
Table 4.1 Summary of Environmental Licensing and
Permit Status
Figures
Figure
1.1 General
Project Layout Plan
Figure 2.1 EM&A
Monitoring Locations
Figure 4.1 Environmental
Complaint Handling Procedures
List of Appendices
Appendix
A Project
Organization Structure
Appendix
B Construction
Programmes
Appendix C Implementation
Schedule of Environmental Mitigation Measures (EMIS)
Appendix D Summary of Action
and Limit Levels
Appendix E Calibration
Certificates of Monitoring Equipments
Appendix F EM&A
Monitoring Schedules
Appendix G Impact Air
Quality Monitoring Results and their Graphical Presentation
Appendix H Meteorological
Data for the Reporting Month
Appendix
I Impact
Daytime Construction Noise Monitoring Results and their Graphical Presentation
Appendix
K Site
Inspection Summaries
Appendix L Statistics
on Complaints, Notifications of Summons and Successful Prosecutions
The
proposed widening of Tolo Highway and Fanling Highway between Island House
Interchange and Fanling (the Project) is a Designated Project under the
Environmental Impact Assessment Ordinance (Cap. 499) (EIAO) and is governed by an Environmental Permit (EP-324/2008)(EP) issued by EPD
on 23 December 2008.
Subsequently, EPD issued a Variation of Environmental Permit (EP-324/2008/A)
(VEP) on 31 January 2012.
The
Project aims to widen Tolo Highway and Fanling Highway
to dual 4-lane carriageway in order to alleviate the current traffic congestion
problems and to cope with the increasing transport demands to and from the
urban areas and also cross boundary traffic.
The
construction works for this Project will be delivered in 2 stages i.e. Stage 1
(between Island House Interchange and Tai Hang) and Stage 2 (between Tai Hang
and Wo Hop Shek Interchange). The construction works of Stage 1 were commenced
on 23 November 2009 and will tentatively be completed in February 2014; while
construction programme of Stage 2 is currently under review. This report
focuses on Stage 1 of the Project only.
The
construction phase of Stage 1 under the EP and the Environmental Monitoring and
Audit (EM&A)
programme for Stage 1 of the Project commenced on 23 November 2009. The impact
environmental monitoring and audit includes air quality and noise monitoring.
This report documents the
findings of EM&A works conducted in the period between 1 and 31 December
2013.
As informed by the Contract 1 Contractor (China State Construction Engineering (Hong Kong) Ltd.), construction activities in the reporting period were:-
- Temporary shoring, sheetpiling and excavation
- At-grade road construction
- Widening and demolition of central dividers
- Retaining wall construction
- Noise barrier footing construction
- Noise barrier panels installation
- Asphalt laying
- Installation of Drainage Pipes
- Modification of Edge coping
The
construction works carried out by the Contract 2
Contractor (Gammon Construction Ltd.) in the reporting period were:-
- Condition survey of existing structures
- Setting up the temporary traffic arrangement
- Excavation of trial trenches to locate existing utilities
- Construction of haul road
- Construction of concrete profile barrier and beam barrier
- Construction of Pilecap / Spread footing of Noise Barrier / Semi Noise Enclosure
- Slope works, including installation of soil nails
- NTHA mitigation works
- Construction of retaining walls
- Noise barrier construction
- Modification of existing bridge structures
- Entrusted watermains works
- Sewer Installation
- Road and drainage works; and Landscaping works
There was no reporting change
required in the reporting month.
Breaches of Action and Limit Levels for Air
Quality
No
exceedance of Action and Limit Level was recorded for 1-hour and 24-hour TSP
monitoring in the reporting month.
Breaches of Action and Limit Levels for Noise
No Action Level exceedance of construction noise was recorded in the reporting month since no noise complaints related to 0700 ¨C 1900 hours on normal weekdays was received and followed by the Environmental Team in the reporting month.
No Limit Level exceedance of construction noise was
recorded in the reporting month.
Complaint, Notification of Summons and
Successful Prosecution
One (1) noise-related complaint was received on 4 November 2013 and followed up by the Environmental Team in November and December 2013. The summary of investigation is described in Sections 4.6.3 to 4.6.5.
One (1) air-related complaint was received on 13 December 2013 and followed up by the Environmental Team in December 2013. The summary of investigation is described in Sections 4.6.6 to 4.6.8.
No notification of summons and successful prosecution was received in the reporting month.
Future Key Issues
Key
issues to be considered in the coming month included:-
- Properly store and label oils and
chemicals on site;
- Chemical, chemical waste and waste
management;
- Collection of construction waste should
be carried out regularly;
- Site runoff should be properly
collected and treated prior to discharge;
- Properly maintain all drainage
facilities and wheel washing facilities on site;
- Exposed slopes should be covered up
properly if no temporary work will be conducted;
- Suppress dust generated from
excavation, breaking and drilling activities, haul road traffic and grout
mixing;
- Quieter powered mechanical equipment
should be used;
- Closely check and replace the sound
insulation materials wrapped at the concrete breaker tip regularly;
- Better scheduling of construction
works to minimize noise nuisance; and
- Tree protective measures for all
retained trees should be well maintained.
1.1.1.
Tolo Highway and Fanling Highway are expressways
in the North East New Territories connecting Sha Tin, Tai Po and Fanling. These
highways form a vital part of the strategic Route 9, which links other major
strategic routes to Shenzhen. At present, this section of Route 9 is dual
3-lane carriageway. However, at several major interchanges along this section
of Route 9, the highway is only dual-2 lane. Severe congestion is a frequent
occurrence during peak periods, particularly in the Kowloon bound direction.
1.1.2.
The objective of the Project ¡°Widening
of Tolo Highway / Fanling Highway between Island House Interchange and Fanling¡±
is to widen Tolo Highway and Fanling Highway to dual 4-lane carriageway in
order to alleviate the current traffic congestion problems and to cope with the
increasing transport demands to and from the urban areas and also cross
boundary traffic.
1.1.3.
The Project is a designated project and
is governed by an Environmental Permit (EP-324/2008)(EP) issued by EPD on
23 December 2008. Subsequently, EPD issued a Variation of Environmental Permit
(EP-324/2008/A) (VEP) on 31 January 2012.
1.1.4.
The scope of the Project comprises
mainly:-
(i) |
Widening
of a 5.7 km section of Tolo Highway and 3.0 km section of Fanling Highway
between Island House Interchange and Wo Hop Shek Interchange from the
existing dual 3-lane to dual 4-lane, including construction of new vehicular
bridges; |
(ii) |
Widening
of interchange sections at Island House Interchange, Tai Po North Interchange,
and Lam Kam Road Interchange from dual 2-lane to dual 3-lane, except Sha Tin
bound carriageway at Tai Po North Interchange, which is widened from 3-lane
to 4-lane, including realignment of various slip roads; |
(iii) |
Modification
and reconstruction of highways, vehicular bridges, underpasses and
footbridges. |
1.1.5.
The construction works for this Project
will be delivered in 2 stages i.e. Stage 1 (between Island House Interchange
and Tai Hang) and Stage 2 (between Tai Hang and Wo Hop Shek Interchange). The
construction works of Stage 1 commenced on 23 November 2009 and will
tentatively be completed in January 2014;
while the construction programme of Stage 2 is currently under review.
This report focuses on Stage 1 of the Project only.
1.1.6.
The construction works for Stage 1 of
the Project will be implemented under 2 works contracts (Contract 1 and
Contract 2). Contract 1 covers the
section of Tolo Highway between Island House Interchange and Ma Wo, Contract 2
covers the section of Tolo Highway between Ma Wo and Tai Hang.
1.1.7.
Hyder-Arup-Black and Veatch Joint
Venture (HABVJV) are appointed by Highways Department (HyD) as the consultants
for the design and construction assignment for the Tolo project under Agreement
No. CE 58/2000 Supplementary Agreement No. 3 (SA3) (i.e. the Engineer for the
Contracts).
1.1.8.
China State Construction Engineering
(Hong Kong) Ltd. (CSHK) was commissioned as the Contractor of Contract 1 of
Stage 1 of the Project, while Gammon Construction Limited (GCL) was
commissioned as the Contractor of Contract 2 of Stage 1 of the Project.
1.1.9.
AECOM Asia Co. Ltd. was employed by HyD
as the Environmental Team (ET) to undertake the Environmental
Monitoring and Audit (EM&A) works
for Stage 1 of the Project and Mott MacDonald Hong Kong Ltd. acts as the
Independent Environmental Checker (IEC) for the Contracts.
1.1.10.
The construction phase of Stage 1 under
the EP commenced on 23 November 2009.
1.1.11.
According to the updated EM&A
Manual of Stage 1 of the Project, there is a need of an EM&A programme
including air quality and noise monitoring. The EM&A programme for Stage 1
of the Project commenced on 23 November 2009.
Table 1.1 Contact Information of Key Personnel
Party |
Position |
Name |
Telephone |
Fax |
ER of Stage 1, Contract 1 (Hyder-Arup-Black
& Veatch Joint Venture) |
Chief Resident Engineer /TOLO1 |
James Tsang |
9038 8797 |
26674000 |
ER of Stage 1, Contract 2 (Hyder-Arup-Black
& Veatch Joint Venture) |
Chief Resident Engineer /TOLO2 |
Paul Appleton |
9097 5833 |
2653 2348 |
IEC of Stage 1 (Mott MacDonald Hong Kong Limited) |
Independent Environmental
Checker |
Terence Kong |
2828 5919 |
2827 1823 |
Contractor of Stage 1, Contract 1 (China State Construction Engineering
(Hong Kong) Limited) |
Site Agent |
Eddie Tang |
9863 7686 |
2667 5666 |
Environmental Officer |
Michael Tsang |
9277 4956 |
2667 5666 |
|
M L Lam |
9489 4641 |
2667 5666 |
||
Contractor of Stage 1, Contract 2 (Gammon Construction Limited) |
Site Agent |
John Chan |
3126 1202 |
2559 3410 |
Environmental Officer |
Thomson Chang |
9213
6569 |
2559 3410 |
|
Crispin Ao |
9223
8773 |
2559 3410 |
||
Jason Cheng |
9837
9323 |
2559 3410 |
||
ET of Stage 1 (AECOM Asia Company Limited) |
ET Leader |
Y T Tang |
3922 9393 |
3922 9797 |
- Temporary shoring, sheetpiling and excavation
- At-grade road construction
- Widening and demolition of central dividers
- Retaining wall construction
- Noise barrier footing construction
- Noise barrier panels installation
- Asphalt laying
- Installation of Drainage Pipes
- Modification of Edge coping
- Condition survey of existing structures
- Setting up the temporary traffic arrangement
- Excavation of trial trenches to locate existing utilities
- Construction of haul road
- Construction of concrete profile barrier and beam barrier
- Construction of Pilecap / Spread footing of Noise Barrier / Semi Noise Enclosure
- Slope works, including installation of soil nails
- NTHA mitigation works
- Construction of retaining walls
- Noise barrier construction
- Modification of existing bridge structures
- Entrusted watermains works
- Sewer Installation
- Road and drainage works; and Landscaping works
- All monitoring
parameters;
- Monitoring
schedules for the reporting month and forthcoming months;
- Action and
Limit levels for all environmental parameters;
- Event / Action
Plan;
- Environmental
mitigation measures, as recommended in the Project EIA study final report; and
- Environmental
requirement in contract documents.
Table 2.1 Air Quality Monitoring Equipment
Equipment |
Brand
and Model |
Portable direct reading dust meter
(1-hour TSP) |
Sibata Digital Dust Monitor (Model
No. LD-3 and LD-3B) |
High Volume Sampler |
Tisch Total Suspended Particulate
Mass Flow Controlled High Volume Air Sampler (Model No. TE-5170
& GMW-2310) |
Table 2.2 Locations
of Impact Air Quality Monitoring Stations
Monitoring Station |
Location |
Description |
AM1A |
3 Sheung
Wun Yiu |
Ground
floor at the boundary outside Fan Sin Temple |
AM2 |
12 Shan
Tong New Village |
Ground
floor outside the premises |
AM3 |
Riverain
Bayside |
Roof of
the switch room |
AM4A |
168 Shek Kwu Lung Village |
Roof of
the switch room |
Table 2.3 Air
Quality Monitoring Parameters, Frequency and Duration
Parameter |
Frequency
and Duration |
1-hour TSP |
Three times every 6 days while the highest dust impact was
expected |
24-hour TSP |
Once every 6 days |
(a)
The HVS was installed in the vicinity of
the air sensitive receivers. The
following criteria were considered in the installation of the HVS.
(i)
A horizontal platform with appropriate
support to secure the sampler against gusty wind was provided.
(ii)
The distance between the HVS and any
obstacles, such as buildings, was at least twice the height that the obstacle
protrudes above the HVS.
(iii)
A minimum of 2 meters separation from
walls, parapets and penthouse for rooftop sampler.
(iv)
A minimum of 2 meters separation from any supporting
structure, measured horizontally.
(v)
No furnace or incinerator flues nearby.
(vi)
Airflow around the sampler was
unrestricted.
(vii)
Permission was obtained to set up the
samplers and access to the monitoring stations.
(viii)
A secured supply of electricity was
obtained to operate the samplers.
(ix)
The sampler was located more than 20
meters from any dripline.
(x)
Any wire fence and gate, required to
protect the sampler, did not obstruct the monitoring process.
(xi)
Flow control accuracy was kept within
¡À2.5% deviation over 24-hour sampling period.
(b)
Preparation of Filter Papers
(i)
Glass fibre filters, G810 were labelled
and sufficient filters that were clean and without pinholes were selected.
(ii)
All filters were equilibrated in the
conditioning environment for 24 hours before weighing. The conditioning
environment temperature was around
(iii)
All filter papers were prepared and
analysed by ALS Technichem (HK) Pty Ltd., which is a HOKLAS accredited
laboratory and has comprehensive quality assurance and quality control
programmes.
(c)
Field Monitoring
(i)
The power supply was checked to ensure
the HVS works properly.
(ii)
The filter holder and the area
surrounding the filter were cleaned.
(iii)
The filter holder was removed by
loosening the four bolts and a new filter, with stamped number upward, on a
supporting screen was aligned carefully.
(iv)
The filter was properly aligned on the
screen so that the gasket formed an airtight seal on the outer edges of the
filter.
(v)
The swing bolts were fastened to hold
the filter holder down to the frame.
The pressure applied was sufficient to avoid air leakage at the edges.
(vi)
Then the shelter lid was closed and was
secured with the aluminum strip.
(vii)
The HVS was warmed-up for about 5
minutes to establish run-temperature conditions.
(viii)
A new flow rate record sheet was set
into the flow recorder.
(ix)
On site temperature and atmospheric
pressure readings were taken and the flow rate of the HVS was checked and
adjusted at around 1.1 m3/min, and complied with the range specified
in the updated EM&A Manual (i.e. 0.6-1.7 m3/min).
(x)
The programmable digital timer was set
for a sampling period of 24 hrs, and the starting time, weather condition and
the filter number were recorded.
(xi)
The initial elapsed time was recorded.
(xii)
At the end of sampling, on site
temperature and atmospheric pressure readings were taken and the final flow
rate of the HVS was checked and recorded.
(xiii)
The final elapsed time was recorded.
(xiv)
The sampled filter was removed carefully
and folded in half length so that only surfaces with collected particulate
matter were in contact.
(xv)
It was then placed in a clean plastic
envelope and sealed.
(xvi)
All monitoring information was recorded
on a standard data sheet.
(xvii)
Filters were then sent to ALS
Technichem (HK) Pty Ltd. for analysis.
(d)
Maintenance and Calibration
(i)
The HVS and its accessories were
maintained in good working condition, such as replacing motor brushes routinely
and checking electrical wiring to ensure a continuous power supply.
(ii)
5-point calibration of the HVS was
conducted using TE
(iii)
Calibration certificate of the HVSs are
provided in Appendix E.
(a)
Measuring Procedures
The measuring procedures of the
1-hour dust meter were in accordance with the Manufacturer¡¯s Instruction Manual
as follows:-
(i)
Turn the power on.
(ii)
Close the air collecting opening cover.
(iii)
Push the ¡°TIME SETTING¡± switch to [BG].
(iv)
Push ¡°START/STOP¡± switch to perform
background measurement for 6 seconds.
(v)
Turn the knob at SENSI ADJ position to
insert the light scattering plate.
(vi)
Leave the equipment for 1 minute upon
¡°SPAN CHECK¡± is indicated in the display.
(vii)
Push ¡°START/STOP¡± switch to perform
automatic sensitivity adjustment. This measurement takes 1 minute.
(viii)
Pull out the knob and return it to
MEASURE position.
(ix)
Push the ¡°TIME SETTING¡± switch the time
set in the display to 3 hours.
(x)
Lower down the air collection opening
cover.
(xi)
Push ¡°START/STOP¡± switch to start
measurement.
(b)
Maintenance and Calibration
(i)
The 1-hour TSP meter was calibrated at
1-year intervals against a continuous particulate TEOM Monitor, Series 1400ab.
Calibration certificates of the Laser Dust Monitors are provided in Appendix E.
(ii)
1-hour validation checking of the TSP
meter against HVS is carried out yearly at the air quality monitoring
locations.
Table 2.4 Summary
of 1-hour TSP Monitoring Results in the Reporting Period
|
Average (mg/m3) |
Range (mg/m3) |
Action Level (mg/m3) |
Limit Level (mg/m3) |
AM1A |
79.6 |
72.6 ¨C 86.2 |
302.1 |
500 |
AM2 |
79.8 |
73.2 ¨C 84.4 |
301.9 |
500 |
AM3 |
79.3 |
73.5 ¨C 84.3 |
301.9 |
500 |
AM4A |
80.5 |
75.9 ¨C 85.0 |
302.3 |
500 |
Table 2.5 Summary of
24-hour TSP Monitoring Results in the Reporting Period
|
Average (mg/m3) |
Range (mg/m3) |
Action Level (mg/m3) |
Limit Level (mg/m3) |
AM1A |
92.6 |
65.7 ¨C 133.8 |
176.6 |
260 |
AM2 |
45.8 |
24.1 ¨C 68.1 |
178.6 |
260 |
AM3 |
56.6 |
34.1 ¨C 82.0 |
193.1 |
260 |
AM4A |
62.2 |
26.4 ¨C 102.9 |
198.5 |
260 |
Table 3.1 Noise
Monitoring Equipment
Equipment |
Brand and Model |
Integrated
Sound Level Meter |
Rion NL-31
/ B&K 2238 / B&K 2250-L |
Acoustic
Calibrator |
Rion NC-73 |
Table 3.2 Locations
of Impact Noise Monitoring Stations
Monitoring Station |
Location |
Description |
NM1A |
168 Shek Kwu Lung Village |
|
NM2 |
38 Ha Wun Yiu |
1.2m from the ground floor free-field
of the village house |
NM3 |
Wong Shiu Chi Middle School |
|
NM4 |
Uptown Plaza |
1m from the exterior of the roof top
façade of Block 4 |
NM5 |
The Paragon |
|
NM6 |
PLK Tin Ka Ping Primary School |
1.2m ground floor free-field near the
entrance |
NM7 |
Riverain Bayside |
1m from the exterior of the roof
façade of the switch room |
Table
3.3 Noise
Monitoring Parameters, Frequency and Duration
Parameter |
Frequency
and Duration |
30-mins measurement at each monitoring station between 0700 and
1900 on normal weekdays. Leq, L10 and L90
would be recorded. |
At least once per week |
(a)
Façade measurements were made at all
monitoring locations, except monitoring stations NM2 and NM6.
(b)
The sound level meter was set on a
tripod at a height of
(c)
The battery condition was checked to
ensure the correct functioning of the meter.
(d)
Parameters such as frequency weighting,
the time weighting and the measurement time were set as follows:-
(i)
frequency weighting: A
(ii)
time weighting: Fast
(iii)
time measurement: Leq(30-minutes)
during non-restricted hours i.e. 07:00 ¨C 1900 on normal weekdays; Leq(5-minutes)
during restricted hours i.e. 19:00 ¨C 23:00 and 23:00 ¨C 07:00 of normal weekdays, whole day of
Sundays and Public Holidays
(e)
Prior to and after each noise
measurement, the meter was calibrated using the acoustic calibrator for 94dB(A)
at 1000 Hz. If the difference in
the calibration level before and after measurement was more than 1 dB(A), the
measurement would be considered invalid and repeat of noise measurement would
be required after re-calibration or repair of the equipment.
(f)
During the monitoring period, the Leq,
L10 and L90 were recorded. In addition, site conditions and noise
sources were recorded on a standard record sheet.
(g)
Noise measurement was paused during
periods of high intrusive noise (e.g. dog barking, helicopter noise) if
possible. Observations were recorded when intrusive noise was unavoidable.
(h)
Noise monitoring was cancelled in the
presence of fog, rain, wind with a steady speed exceeding
(a)
The microphone head of the sound level meter
was cleaned with soft cloth at regular intervals.
(b)
The meter and calibrator were sent to
the supplier or HOKLAS laboratory to check and calibrate at yearly intervals.
(c)
Calibration certificates of the sound
level meters and acoustic calibrators are provided in Appendix E.
Table 3.4 Summary of Construction Noise Monitoring Results in the Reporting
Period
|
Average, dB(A), Leq (30 mins) |
Range, dB(A), Leq (30 mins) |
Limit Level, dB(A), Leq (30 mins) |
NM1A |
63.2 |
61.9 ¨C 64.2 |
75 |
NM2 |
65.9* |
62.9 ¨C 67.5* |
75 |
NM3 |
61.3 |
58.4 ¨C 63.5 |
70# |
NM4 |
64.1 |
57.2 ¨C 65.5 |
75 |
NM5 |
61.9 |
56.9 ¨C 64.1 |
75 |
NM6 |
61.8* |
59.6 ¨C 64.4* |
70# |
NM7 |
59.5 |
54.6 ¨C 62.8 |
75 |
*+3dB(A) Façade correction
included
Air Quality
Noise
Water Quality
Chemical and Waste Management
Landscape and Visual Impact
Miscellaneous
Air Quality
Noise
Water Quality
Chemical and Waste Management
Landscape and Visual Impact
Miscellaneous
Table 4.1 Summary of Environmental Licensing and Permit Status
Statutory Reference |
License/ Permit |
License or Permit No. |
Valid Period |
License/ Permit Holder |
Remarks |
|
From |
To |
|||||
EIAO |
Environmental
Permit |
EP-324/2008/A |
31/01/2012 |
N/A |
HyD |
Tolo
Highway/Fanling Highway between Island House
Interchange and Ma Wo |
WPCO |
Discharge License
(Office) |
WT00005096-2009 |
03/12/2009 |
31/12/2014 |
CSHK |
Discharge at Site
Office |
Discharge License
(Site) |
WT00005445-2009 |
15/12/2009 |
31/12/2014 |
CSHK |
Discharge of
Construction Runoff |
|
Discharge License
(Office) |
WT00006782-2010 |
25/06/2010 |
30/06/2015 |
GCL |
Discharge at Site
Office |
|
Discharge License
(Site) |
WT00007162-2010 |
09/08/2010 |
31/07/2015 |
GCL |
Discharge of
Construction Runoff |
|
WDO |
Chemical Waste
Producer Registration |
5213-727-C3249-46 |
25/09/2009 |
N/A |
CSHK |
Chemical waste
produced in Contract HY/2008/09 |
5213-722-G2347-18 |
18/05/2010 |
N/A |
GCL |
Chemical waste
produced in Contract HY/2009/08 |
||
WDO |
Billing
Account for Disposal of Construction Waste |
7009328 |
08/09/2009 |
N/A |
CSHK |
Waste disposal in
Contract HY/2008/09 |
7010320 |
02/03/2010 |
N/A |
GCL |
Waste disposal in
Contract HY/2009/08 |
||
NCO |
Construction Noise
Permit |
GW-RN0417-13 |
21/07/2013 |
17/01/2014 |
CSHK |
Construction works at Island
House Interchange |
GW-RN0468-13 |
19/08/2013 |
23/01/2014 |
CSHK |
Routine Road Maintenance |
||
GW-RN0561-13 |
02/10/2013 |
01/04/2014 |
CSHK |
Modification of Sign Gantry_G11, G13,
G70, G73, G74, G75 & G76 |
||
GW-RN0572-13 |
07/09/2013 |
03/12/2013 |
CSHK |
Modification of Sign Gantry_G14, G15,
G16, G17, G65, G66, G67 & G68 |
||
GW-RN0607-13 |
19/10/2013 |
22/12/2013 |
CSHK |
Road Paving on Tolo Highway between
Ma Wo and NLKRB (Shatin Bound) |
||
GW-RN0614-13 |
19/10/2013 |
22/12/2013 |
CSHK |
Road Paving on North Bound of Tolo
Highway at Island House Interchange |
||
GW-RN0620-13 |
19/10/2013 |
22/12/2013 |
CSHK |
Road Paving Reconstruction on Tolo
Highway (Fanling Bound) Between
NB12 and Tat Wan Road |
||
GW-RN0647-13 |
01/11/2013 |
31/12/2013 |
CSHK |
Carrying out construction works
within MTRC's tracks protection zone |
||
GW-RN0693-13 |
16/11/2013 |
22/12/2013 |
CSHK |
Road Paving on Tolo Highway at Island
House Interchange (Shatin Bound) |
||
GW-RN0703-13 |
19/11/2013 |
28/12/2013 |
CSHK |
Installation of Noise Barrier on
Kwong Fuk West Viaduct |
||
GW-RN0707-13 |
19/11/2013 |
28/12/2013 |
CSHK |
Road Paving Reconstruction on Tolo Highway (Fanling & Shatin
Bound) near Shan Tong Road |
||
GW-RN0710-13 |
21/11/2013 |
24/12/2013 |
CSHK |
Sign Gantry at Tolo Highway between Yuen Chau Tsai and Ma Wo |
||
GW-RN0726-13 |
27/11/2013 |
31/12/2013 |
CSHK |
Concreting Works on Tolo Highway
(Fanling Bound) near Tat Wan Road |
||
GW-RN0741-13 |
03/12/2013 |
28/12/2013 |
CSHK |
Installation of Sign Gantries G18
& G19 |
||
GW-RN0742-13 |
02/12/2013 |
28/12/2013 |
CSHK |
Road Pavement at Shatin Bound of
Tolo Highway between Wan Tau Tong Estate and Tai Po Road |
||
GW-RN0763-13 |
10/12/2013 |
28/12/2013 |
CSHK |
Modification of Sign Gantries G13
G14 G16 G17& G66 |
||
GW-RN0766-13 |
14/12/2013 |
23/02/2014 |
CSHK |
Road Paving on Tolo Highway between
Ma Wo and NLKRB |
||
GW-RN0788-13 |
22/12/2013 |
23/02/2014 |
CSHK |
Road pavement for Slip Road from
Tolo Highway to Tai Po Road near
Yuen Chau Tsai |
||
GW-RN0789-13 |
02/01/2014 |
31/03/2014 |
CSHK |
Construction works next to MTRC's
tracks protection zone |
||
GW-RN0801-13 |
28/12/2013 |
23/02/2014 |
CSHK |
Road Marking Alternation at Tolo
Highway at |
||
GW-RN0807-13 |
29/12/2013 |
23/02/2014 |
CSHK |
Road pavement for Slip Road from
Tolo Highway to Tai Po Road near
Yuen Chau Tsai |
||
GW-RN0810-13 |
31/12/2013 |
23/02/2014 |
CSHK |
Road Paving Reconstruction on |
||
GW-RN0530-13 |
03/10/2013 |
02/02/2014 |
GCL |
Renewal of GW-RN0194-13 |
||
GW-RN0695-13 |
17/11/2013 |
12/05/2014 |
GCL |
General work and asphalt paving at Tolo Highway near Shek Kwu Lung and
Ma Wo (CH18.1 - 19.2) |
||
GW-RN0785-13 |
28/12/2013 |
27/02/2014 |
GCL |
Stitching Construction at Section of Tolo Highway (Shatin Bound) CH19 to CH18.8A |
||
GW-RN0786-13 |
19/12/2013 |
11/06/2014 |
GCL |
Renewal of
GW-RN0484-13 |
||
GW-RN0795-13 |
24/12/2013 |
27/02/2014 |
GCL |
Erection of Sign Gantry at Tolo Highway (Fanling Bound) CH19.9 to CH20.1 near Lam Kam Interchange |
Mitigation measures, including water spraying by sprinklers
on haul roads and exposed slopes, covering non-working slopes by tarpaulin
sheets at a sight distance from the complainant before the complete
construction of permanent footpath, full-time manual water spraying, and the
tarpaulin dust screen of appropriately 1.8 m in height set on the top of W45-47
which is along W44 and NB31, and a section of footpath on W38, were taken by
the Contractor. As shown in Figure 4B, water is sprayed manually to the leaves
of the trees to minimize the emitted dust from dropping to the complainant¡¯s
house and Ma Wo Tsuen through the trees. As shown in Figure 5, the loading and
unloading height of general fill materials at W38 was kept to a minimum.
Besides, in case any dump truck passes through W45-47, the mechanical covering
will not open until they reach the unloading point.
Wheel washing has been carried out at the site entrance. The
dump truck responsible for the delivery of fill materials for W38 only moved
within W48 and W38, which was not exiting from the site entrance on 12 and 13
December 2013.
With reference to the monitoring results recorded on the day closest to
the day of complaint at the nearest EM&A monitoring station (AM1A- Sheung Wun Yiu), the 24-hour TSP level on 10
December 2013 was 133.8 ug/m3, which was below the action level of
176.6 ug/m3. Besides, the average 1-hour TSP 10 December 2013
at the nearest EM&A monitoring station (AM1A-
Sheung Wun Yiu) was 83.5 ug/m3, which was
also below the action level of 302.3ug/m3.
Nevertheless, the complaint was considered project-related.
Therefore, the Contractor is reminded to enhance the dust mitigation
measures as stated in the ¡°Recommended Mitigation Measures¡±
below:
-
Confirm
the implementation of dust mitigation measures (erection of
tarpaulin dust screens along the work areas W38-48, spraying water manually by
workers and sprinkler systems for the haul roads and exposed slopes at work
areas W38-48, covering non-working slopes by tarpaulin sheets within work
areas, covering dusty materials carried in dump trucks within work areas
W38-48) during all construction and dusty
activities to minimize fugitive dust generation;
-
Increase
the frequency of watering in the work areas (specially at the entrance of the construction site, and on site
haul roads and exposed slopes / areas in the work areas W38-48), so that site haul roads and exposed surfaces are in
a wet condition;
-
Cover the backfilling surface after
work;
-
Keep soil surfaces wet before loading
and unloading activities;
-
Maintain the frequency of the
environmental supervision (by the Contractor) to regularly review the adequacy
and effectiveness of dust suppression measures to suit the construction
progress;
-
Inform the complainant before dusty
activities (e.g. rock breaking, excavation, grouting and backfilling) are
carried out; and
-
Foster better public relations with
the sensitive receivers and complainants nearby.
- Temporary shoring, sheetpiling and excavation
- At-grade road construction
- Retaining wall construction
- Noise barrier footing construction
- Noise barrier panels installation
- Asphalt laying
- Installation of drainage pipes
- Condition survey of existing structures
- Setting up the temporary traffic arrangement
- Excavation of trial trenches to locate existing utilities
- Construction of haul road
- Construction of concrete profile barrier and beam barrier
- Construction of Pilecap / Spread footing of Noise Barrier / Semi Noise Enclosure
- Slope works, including installation of soil nails
- NTHA mitigation works
- Construction of retaining walls
- Noise barrier construction
- Modification of existing bridge structures
- Entrusted watermains works
- Sewer Installation
- Road and drainage works; and Landscaping works
- Properly store and label oils and chemicals on site;
- Chemical, chemical waste and waste management;
- Collection of construction waste should be carried out regularly;
- Site runoff should be properly collected and treated prior to discharge;
- Properly maintain all drainage facilities and wheel washing facilities on site;
- Exposed slopes should be covered up properly if no temporary work will be conducted;
- Suppress dust generated from excavation, breaking and drilling activities, haul road traffic and grout mixing process;
- Quieter powered mechanical equipment should be used;
- Closely check and replace the sound insulation materials wrapped at the concrete breaker tip regularly;
- Better scheduling of construction works to minimize noise nuisance; and
- Tree protective measures for all retained trees should be well maintained.
Air Quality
Impact
l The soil stockpiles should be
properly covered.
l The grouting
station should be properly sheltered as one of the dust control measures
Construction
Noise Impact
l Properly erect the temporary
noise barriers in accordance with the Environmental Permit requirement.
l Noisy operations should be
oriented to a direction away from sensitive receivers as far as possible.
l Sound insulation materials shall
be wrapped at the
breaker tip for concrete breaking works.
Water Quality
Impact
l Preventive measures should be
implemented to avoid the spread of mud trails on the public road.
l Silty effluent should be
treated/desilted before discharged. Untreated effluent should be prevented from
entering public drain channel.
l Proper drainage channels/bunds
should be provided at the site boundaries to collect/intercept the surface
run-off from works areas.
l Stagnant water accumulated
within works area should be removed.
Chemical and
Waste Management
l C&D materials and wastes,
general refuse should be sorted properly and removed timely.
l All chemical containers and oil
drums should be properly stored.
l All plants and vehicles on site
should be properly maintained to prevent oil leakage.
l All drain holes of the drip
trays utilized within works areas should be properly plugged to avoid any oil
leakage.
l Oil stains on soil surface and
empty chemical containers should be cleared and disposed of as chemical waste.
l Drip tray should be provided to prevent oil
leakage.
l Only the recycling materials
should be dumped into the appropriate recycling bins.
Landscape and
Visual Impact
l All retained trees should be
properly fenced off at the works area.