Appendix
C - Implementation Schedule of Environmental Mitigation Measures (EMIS)
Air Quality - Schedule of Recommended Mitigation Measures
Impact |
Mitigation Measures |
Timing |
Implementation Status |
Air
Quality during Construction |
· Restricting heights
from which materials are dropped, as far as practicable to minimize the
fugitive dust arising from unloading/loading. |
During
construction |
V |
· All stockpiles of
excavated materials or spoil of more than 50m3 shall be enclosed,
covered or dampened during dry or windy conditions. |
@ |
||
· Effective water
sprays shall be used to control potential dust emission sources such as
unpaved haul roads and active construction areas. |
@ |
||
· All spraying of
materials and surfaces shall avoid excessive water usage. |
V |
||
· Vehicles that have
the potential to create dust while transporting materials shall be covered,
with the cover properly secured and extended over the edges of the side and
tail boards. |
V |
||
· Materials shall be
dampened, if necessary, before transportation. |
V |
||
· Travelling speeds
shall be controlled to reduce traffic induced dust dispersion and
resuspension within the site from the operating haul trucks. |
V |
||
· Vehicle washing
facilities shall be provided to minimize the quantity of material deposited
on public roads. |
V |
Noise - Schedule of Recommended Mitigation Measures
Impact |
Mitigation Measures |
Timing |
Implementation Status |
Noise
during Construction |
· Use of silenced
plant or plant equipped with mufflers or dampers in substitute of ordinary
plant. |
During
construction |
V |
· Reduce the number of
equipment and their percentage on-time. |
V |
||
· 3.5 m and 5.5 m high
temporary noise barrier at culvert construction work area (Figure 2a of the
Environmental Permit). |
V |
||
· 3 m high temporary
noise barrier along the northern edge of Bridge 12 at ground level (Figure 2b
of the Environmental Permit). |
V |
||
· 2 m high temporary
noise barrier along the northern edge of Bridge 12 at bridge level (Figure 2b
of the Environmental Permit). |
In progress |
||
· 2.5 m high temporary
noise barrier along TaiWo Service Road West (Figure 2c of the Environmental
Permit). |
V |
||
· 3.5m high temporary
noise barrier along Tai Wo Services Road West near Tai Hang (Figure2c of the
Environmental Permit). |
In progress |
Water Quality - Schedule of Recommended Mitigation Measures
Impact |
Mitigation Measures |
Timing |
Implementation Status |
Water
quality during Construction |
Demolition and
reconstruction of bridges |
During
construction |
|
· Prevent off-site
migration through use of sheet piles. |
V |
||
· Minimize duration of
works as far as practical. |
V |
||
· All sewer and
drainage connections should be sealed to prevent debris, soil, sand, etc,
from entering public sewers/drains. |
V |
||
· Site surface runoff
should be settled to remove sand/silt before it is discharged into the
existing storm drains. |
V |
||
River training works |
|
||
· lnspection and
testing of water quality in the nullah on the Tai Po River. |
N/A |
||
Road Widening Works
and Earthworks |
|
||
· Wastewater generated
from any concrete batching washdown of equipment or similar activities should
be discharged into foul sewers, after the removal of settable solids, and pH
adjustment as necessary. All sewage discharges from the study area should
meet the TM standards and approval from EPD through the licensing process is
required. |
V |
||
· Sand traps, oil interceptors
and other pollution prevention installations should be provided, properly
cleaned and maintained. |
@ |
||
· Runoff from exposed
working areas, unfinished slopes and from unlined temporary channels should
be directed to stilling basins and/or silt traps before discharging to the
drainage outfalls. |
@ |
||
· Regular inspections
of stilling basins and/or silt traps are required to ensure that sediment is
not conveyed into the existing drainage system. |
V |
||
· Open stockpiles
should be covered with a tarpaulin cover. |
@ |
||
· During the wet season,
any exposed top soils should be covered with a tarpaulin, shotcreted or
hydroseeded. |
V |
||
· Sand and silt from
wash-water from vehicle washing should be settled out before discharging into
storm drains. |
V |
||
· Fuels should be
stored in bunded areas such that spillage can be easily collected. |
V |
Waste - Schedule of Recommended Mitigation Measures
Impact |
Mitigation Measures |
Timing |
Implementation Status |
Waste
Management during Construction |
General Waste |
During
construction |
|
· Transport of wastes
off site as soon as possible. |
V |
||
· Maintenance of
accurate waste records |
V |
||
· Minimization of
waste generation for disposal (via reduction/recycling/re-use). |
V |
||
· No on-site burning
will be permitted. |
V |
||
· Use of re-useable
metal hoardings/signboards. |
V |
||
Vegetation from site
clearance |
|
||
· Segregation of
materials to facilitate disposal. |
V |
||
· Mulching to reduce
bulk and where possible review opportunities for the possible beneficial use
within landscaping areas. |
V |
||
Demolition Wastes |
|
||
· Segregation of
materials to facilitate disposal. |
V |
||
· Appropriate
stockpile management. |
V |
||
Excavated Materials |
|
||
· Segregation of
materials to facilitate disposal / reuse. |
V |
||
· Appropriate
stockpile management. |
V |
||
· Re-use of excavated
material on or off site (where possible). |
V |
||
· Special handling and
disposal procedures in the event that contaminated materials are excavated. |
N/A |
||
Construction Wastes |
|
||
· Segregation of
materials to facilitate recycling/reuse (within designated area in
appropriate containers/stockpiles). |
V |
||
· Appropriate
stockpile management. |
V |
||
· Planning to reduce
over ordering and waste generation. |
V |
||
· Recycling and re-use
of materials where possible (e.g. metal, wood from formwork) |
V |
||
· For material which
cannot be re-used/recycled, collection should be carried out by an approved
waste contractor for landfill disposal. |
V |
||
Bentonite Slurries |
|
||
· Bentonite slurries
should be reused as far as possible. |
N/A |
||
· Disposal in
accordance with Practice Note For
Professional Persons ProPECC PN 1/94. |
N/A |
||
Chemical Wastes |
|
||
· Storage within
locked, covered and bunded area. |
V |
||
· The storage area
shall not be located adjacent to sensitive receivers e.g. drains. |
V |
||
· Minimize waste
production and recycle oils/solvents where possible. |
V |
||
· A spill response
procedure shall be in place and absorption material available for minor
spillages. |
@ |
||
· Use appropriate and
labelled containers. |
V |
||
· Educate site workers
on site cleanliness/waste management procedures. |
V |
||
· lf chemical wastes
are to be generated, the contractor must register with EPD as a Chemical Waste
Producer. |
V |
||
· The chemical wastes
shall be collected by a licensed chemical waste collector. |
V |
||
Municipal Wastes |
|
||
· Waste shall be
stored within a temporary refuse collection facility, in appropriate
containers prior to collection and disposal. |
V |
||
· Regular, daily
collections are required by an approved waste collector. |
V |
Ecology - Schedule of Recommended Mitigation Measures
Impact |
Mitigation Measures |
Timing |
Implementation Status |
Ecology
during Construction |
Accurate Delineation
of Works Area |
During
construction |
|
· Boundaries of
proposed works areas shall be clearly identified and separated from external
areas by a physical barrier to prevent encroachment of adjacent habitats. |
V |
||
· lndividual trees
which fall within the works areas but which work plans show do not require
removal are to be retained and fenced off to maximize protection. |
V |
||
Vegetation Clearance |
|
||
· No fires shall be
lit within the works area for the purpose of burning cleared vegetation. |
V |
||
· The Contractor shall
give consideration to mulching the cleared vegetation for recycling within
the works area / adjacent land. |
V |
||
Dust generation |
|
||
· Vehicle washing
facilities to be provided at every discernible or designated vehicle exit
point; |
V |
||
· All temporary site
access roads shall be sprayed with water to suppress dust as necessary; |
V |
||
· All dusty materials
should be sprayed with water immediately prior to any handling; and |
V |
||
· All debris should be
covered entirely by impervious sheeting or stored in a sheltered debris
collection area. |
V |
||
Surface Run-off |
|
||
· Bund and cover stockpiles
to avoid run-off; |
V |
||
· Channel any run-off
through a system of oil, grease and sediment / silt traps and reuse water on
site where ever practical; |
V |
||
· All vehicle
maintenance to be undertaken within a bunded area; and |
N/A |
||
· Maximize vegetation
retention on-site to maximize absorption (minimize transport). |
V |
Landscape and Visual Impact - Schedule of Recommended
Mitigation Measures
Impact |
Mitigation Measures |
Timing |
Implementation Status |
Landscape
and Visual Impact during Construction |
Preservation of
Existing Vegetation |
During
construction |
|
· Trees identified for
retention within the project limit would be protected during the works |
V |
||
· The tree
transplanting and planting works shall be implemented by approved Landscape
Contractors |
V |
||
Temporary Works
Areas |
|
||
· Where feasible the
works areas would be screened using hoarding and existing vegetation would be
retained where possible to reduce the landscape and visual impacts arising
from the construction activity. The landscape of these works areas would be
restored following the completion of the construction phase. |
V |
||
Hoarding |
|
||
· A hoarding would be
erected where practicable in the most visually sensitive locations to screen
the temporary construction works from the local VSR's. |
V |
||
Top Soils |
|
||
· The works will
result in disturbance to extensive areas of topsoil. Topsoil worthy of
retention should be stockpiled for use following completion of the civil
engineering works. lt should either be temporarily vegetated with hydroseeded
grass or turned over on a regular basis. |
N/A |
||
Protection of Important
Landscape Features |
|
||
· lmportant features
such as temples, lsland House and kilns within the study area, although
remote from the proposed works retained and adequately protected. |
V |
Legend: V = implemented;
x = not implemented;
@
= partially implemented;
N/A = not applicable - No
such work was undertaken or no such material was used on site.