Site Inspection Summary

 

Inspection Information

Contract No.

HY/2008/09 (Between Island House Interchange and Ma Wo)

Date:

4 December 2013

Time:

09:45

Inspection No.:

395

 

Non-compliance

 

 

Nil

 

 

Observations

 

Follow Up Observation

 

 

 

 

Nil.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

New Observation

 

1.

The Contractor was reminded to provide a drip tray to hold the oil can.

 

 

 

 

 

Remarks

 

 

Nil

 

 

 

 


 

Site Inspection Summary

 

Inspection Information

Contract No.

HY/2009/08 (Between Ma Wo and Tai Hang)

Date:

5 December 2013

Time:

14:15

Inspection No.:

396

 

Non-compliance

 

 

Nil

 

 

Observations

 

Follow Up Observations

1.

The excess general refuse in the waste skip at Bridge 13 was removed (Closed).

 

 

 

New Observations

 

 

2.

The Contractor was reminded to provide a drip tray to oil cans at Gate 2 or remove the oil cans.

 

 

 

 

 

 

 

 

 

 

 

 

 

Remarks

 

 

Nil

 

 


 

Site Inspection Summary

 

Inspection Information

Contract No.

HY/2008/09 (Between Island House Interchange and Ma Wo)

Date:

11 December 2013

Time:

14:00

Inspection No.:

397

 

Non-compliance

 

 

Nil

 

 

Observations

 

Follow Up Observation

 

 

 

 

1.

The oil can was removed (Closed).

 

 

 

 

 

 

 

 

 

 

 

 

 

 

New Observation

 

 

Nil.

 

 

 

 

 

 

 

Remarks

 

 

Nil

 

 


 

Site Inspection Summary

 

Inspection Information

Contract No.

HY/2009/08 (Between Ma Wo and Tai Hang)

Date:

12 December 2013

Time:

14:15

Inspection No.:

398

 

Non-compliance

 

 

Nil

 

 

Observations

 

Follow Up Observations

1.

Oil cans at Gate 2 are removed (Closed).

 

 

 

New Observations

 

 

 

Nil.

 

 

 

 

 

 

 

 

 

 

 

 

 

Remarks

 

 

Nil

 

 


 

Site Inspection Summary

 

Inspection Information

Contract No.

HY/2008/09 (Between Island House Interchange and Ma Wo)

Date:

18 December 2013

Time:

09:15

Inspection No.:

399

 

Non-compliance

 

 

Nil

 

 

Observations

 

Follow Up Observation

 

 

 

Nil.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

New Observation

 

 

Nil.

 

 

 

 

 

 

 

Remarks

 

 

Nil

 

 


 

Site Inspection Summary

 

Inspection Information

Contract No.

HY/2009/08 (Between Ma Wo and Tai Hang)

Date:

19 December 2013

Time:

14:15

Inspection No.:

400

 

Non-compliance

 

 

Nil

 

 

Observations

 

Follow Up Observations

 

Nil.

 

 

New Observations

 

 

1.

The Contractor was reminded to cover the exposed slope at Gate 48 with tarpaulin sheets.

 

 

 

 

 

 

 

 

 

 

 

 

 

Remarks

 

 

Nil

 

 


 

Site Inspection Summary

 

Inspection Information

Contract No.

HY/2008/09 (Between Island House Interchange and Ma Wo)

Date:

24 December 2013

Time:

09:15

Inspection No.:

401

 

Non-compliance

 

 

Nil

 

 

Observations

 

Follow Up Observation

 

 

 

Nil.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

New Observation

 

1

Dry soil surface was observed on access roads and the Contractor was reminded to spray the access road with water or dust suppression chemicals to maintain the entire surface wet. (Follow up)

 

 

2

Oil drums were observed without drip tray and the Contractor was reminded to provide trays to oil drums as a mitigation measure. (Follow up)

 

 

 

 

 

Remarks

 

 

Nil

 

 


 

Site Inspection Summary

 

Inspection Information

Contract No.

HY/2009/08 (Between Ma Wo and Tai Hang)

Date:

24 December 2013

Time:

09:30

Inspection No.:

402

 

Non-compliance

 

 

Nil

 

 

Observations

 

Follow Up Observations

1.

The slope at Gate 48 is covered by tarpaulin sheets.

 

 

New Observations

 

 

 

Nil.

 

 

 

 

 

 

 

 

 

 

 

 

 

Remarks

 

 

Nil

 

 


 

Site Inspection Summary

 

Inspection Information

Contract No.

HY/2009/08 (Between Ma Wo and Tai Hang)

Date:

31 December 2013

Time:

09:15

Inspection No.:

403

 

Non-compliance

 

 

Nil

 

 

Observations

 

Follow Up Observations

 

Nil.

 

 

New Observations

 

 

1.

Mud was observed at the edge of the footpath at NLKP3. The Contractor was reminded to clear the mud and increase the height of sand bags to prevent the overflow of sand from the construction site.

 

2.

Muddy water was observed at the edge of the road at W74. The contractor was reminded to direct the water to an appropriate discharge point so that it will not mix with sand to produce muddy water.

 

 

 

 

 

 

 

 

 

 

 

Remarks

 

 

Nil