Contents
Page
EXECUTIVE SUMMARY i
1 INTRODUCTION AND PROJECT INFORMATION 1
1.1 Background.............................................................................................................. 1
1.2 Construction
Programme and Activities.................................................................. 1
1.3 Project
Organisation................................................................................................ 2
1.4 Purpose of the
Report.............................................................................................. 2
2 SUMMARY OF EM&A REQUIREMENTS 3
2.1 Monitoring
Requirements......................................................................................... 3
2.2 Environmental
Mitigation Measures........................................................................ 3
3 SUMMARY OF EM&A Monitoring Data 3
3.1 Monitoring Data........................................................................................................ 3
3.2 Summary of
Monitoring Exceedances.................................................................... 4
4 WASTE MANAGEMENT 5
5 ENVIRONMENTAL NON-CONFORMANCE 5
6 CONCLUSION, COMMENTS AND
RECOMMENDATIONS 5
Table 1.1 Contact Information of Key Personnel
Table 2.1 Monitoring Parameter
Table 3.1 Summary of Monitoring Data in the Reporting Quarter
Table 3.2 Summary of Exceedance Events in the Reporting Quarter
List of Figures
Figure 2 Environmental
Monitoring Locations
List of Appendices
Appendix A Construction Programme
Appendix B Project Organization Structure
Appendix C Implementation Schedule of Environmental
Mitigation Measures (EMIS)
Appendix D Meteorological Data Extracted from Hong
Kong Observatory
Appendix E Environmental Monitoring Data for Air
Quality and Noise
Appendix G Statistics on Complaints, Notifications
of Summons and Successful Prosecutions
This report documents the findings of EM&A works conducted in the
quarter between 1 August November 2016
and 31 October January 20176.
The impact stage EM&A programme for the Project includes air quality
and noise monitoring.
The EM&A programme was carried out by the ET in accordance with the
EM&A Manual requirements. It is
concluded from the environmental monitoring and audit works that adequate
environmental mitigation measures have been implemented by the civil works
contractors where appropriate in the reporting quarter.
In the reporting quarter, no exceedance
events were recordedone (1)
exceedance of Action Level of Dissolved Oxygen was recorded for water quality
monitoring at the monitoring location I5 on 12 December 2016. No
necessary remedial actions have been taken.
No environmental
non-compliance was recorded in the reporting
quarter. No environmental complaints were received
in the reporting quarter. No
environmental related prosecution or notification of summons was received in
the reporting quarter.
The box culvert works have been partially
completed by the end of March 2014 except the last construction activity,
installation of a base slab at Box Culvert ID4. Due to the loading requirement
of a fresh water main under the box culvert, installation of the base slab at Box
Culvert ID4 has been scheduled to be commenced in December
2016.
The construction works at the box culvert ID4
are temporarily suspended until the utilities diversion works complete. The 4-week post construction water
quality monitoring will be commenced after the installation of the base slab
finishes, hence the completion of the box culvert works.
1.1.1
The
Project is a Designated Project under the Environmental Impact Assessment
Ordinance (EIAO) (Cap. 499). An
Environmental Impact Assessment (EIA) Report together with an Environmental
Monitoring and Audit (EM&A) Manual were approved on 14 July 2000 (Register
Number: EIA-043/2000). The Project
is governed by an Environmental Permit (EP) (EP-324/2008) which was granted on
23 December 2008. A variation of EP
(VEP) was applied and the VEP (EP-324/2008/A) was subsequently granted on 31
January 2012. An
additional VEP has been applied on 24 February 2014 and the VEP (EP-324/2008/B)
was subsequently granted on 17 March 2014.
Furthermore, an additional VEP has been applied
on 9 March 2015 and the VEP (EP-324/2008/C) was subsequently granted on 27
March 2015. The
current VEP (EP-324/2008/D) was
granted on 27 August 2015.
1.1.2
Chun
Wo Construction & Engineering Co Ltd (Chun Wo) was commissioned by the
Civil Engineering and Development Department (CEDD) as the Civil Contractor for
the Entrusted Portion of Widening of Tolo Highway/Fanling Highway between
Island House Interchange and Fanling Stage 2. Meinhardt Infrastructure &
Environment Ltd (MIEL) has been appointed by Chun Wo as the Environmental Team
(ET) to fulfill the corresponding EM&A requirements pursuant to
Environmental Permit No. EP-324/2008/D in accordance with the Updated EM&A
Manual (dated March 2015) for Widening
of Tolo Highway/Fanling Highway between Island House Interchange and Fanling
Stage 2. The EM&A programme
commenced in 5 November 2013.
1.1.3
Figure 1 shows the works areas for the
Entrusted Portion of Widening of Tolo Highway/Fanling Highway between Island
House Interchange and Fanling Stage 2.
1.2.1
The
construction programme is presented in Appendix A. The major construction activities
undertaken in the reporting quarter are summarized below:
¡P
Cable
Detection and Trial Trenches; |
¡P
Demolition
of Existing Vehicular Bridge; |
¡P
Footbridge
Construction; |
¡P
Storm
Drains Laying; |
¡P
Noise
Barrier Construction; |
¡P
Pier / Pier
Table Construction; |
¡P
Pile Cap
Works; |
¡P
Portal Beam
Construction; |
¡P
Retaining
Wall Construction; |
¡P
Road Works; |
¡P
Sewer Works; |
¡P
Utilities
Duct Laying; |
¡P
Viaduct
Segment Erection; |
¡P
Water Main
Laying; |
¡P
Extended
Podium Construction; |
¡P
Construction
of Remaining Base Slab of Box Culvert ID4; |
¡P
Abutment
Construction; |
¡P
Construction
of Boundary Wall for DSD Pumping Station; |
¡P
Extended
Podium Construction; and |
¡P
Roundabout
Modification Works. |
1.3.1
The
project organization structure is shown in Appendix B. The key personnel contact names and
numbers for the Project, together with the general enquiry hotline, are
summarised in Table 1.1Table 1.1.
Table 1.1 Contact Information of Key Personnel
Party |
Role |
Position |
Name |
Telephone |
Fax |
AECOM |
Engineer¡¦s
Representative |
Senior
Resident Engineer |
Mr. Alan Lee |
2171 3303 |
2171 3498 |
Resident Engineer (Environmental) |
Mr. |
2171 3350 |
|||
Mott MacDonald |
Independent Environmental Checker (IEC) |
IEC |
Mr. Steven Tang |
2828 5920 |
2827 1823 |
Chun Wo |
Contractor |
Site Agent |
Mr. Daniel Ho |
2638 6144 |
2638 7077 |
Environmental Officer |
Mr. |
2638 6181 |
|||
Meinhardt |
Environmental Team (ET) |
ET Leader |
Mr. Fredrick Leong |
2859 1739 |
2540 1580 |
Enquiry Hotline |
General Enquiry |
-- |
Ms Helena Mak |
6355 1731 |
-- |
1.4.1
This
is the Quarterly EM&A Report which summaries the impact monitoring results
and audit findings for the Project during the reporting period between 1 August November 2016
and 31 October January 20167.
2.1.1
In
accordance with the Updated EM&A Manual, environmental parameters including
Air Quality and Noise have been monitored.
The specific parameters, monitoring frequency and the respective Action
and Limit Levels are given in Table
2.1Table 2.1 and the location of the monitoring
station is shown in the Figure 2.
Table 2.1 Monitoring Parameter
Parameter |
Unit |
Action
Level |
Limit Level |
Frequency |
Air Quality |
||||
1-hour
TSP |
mg/m3 |
292.7 |
500 |
Three times every 6 days |
24-hour
TSP |
mg/m3 |
170.3 |
260 |
Once every 6 days |
Construction Noise |
||||
Leq 30min |
dB(A) |
When
one documented valid complaint is received |
75 |
Once every Week |
2.1.2
The box culvert works have
been partially completed by the end of March 2014 except the last construction
activity, installation of a base slab at Box Culvert ID4. Due to the loading requirement of a
fresh water main under the box culvert, installation of the base slab at Box
Culvert ID4 has been scheduled to be commenced in December
2016.
2.1.3 The construction works at the box culvert ID4 are temporarily suspended until the utilities diversion works complete. The 4-week post construction water quality monitoring will be commenced after the installation of the base slab finishes, hence the completion of the box culvert works.
2.2.1
Environmental
mitigation measures have been recommended in the EM&A Manual and are given
in Appendix C. The implementation
status for the reporting quarter is also given in the Appendix.
3.1.1
Monitoring has been conducted in accordance with the
specification in the EM&A Manual in the reporting quarter. Meteorological data for the reporting
quarter have been extracted from Hong Kong Observatory and are given in Appendix D. Monitoring data with graphical
presentation for the reporting quarter have been given in Appendix E. A summary on the monitoring results has
also been given in Table
3.1Table 3.1.
Table 3.1 Summary of Monitoring Data in the Reporting Quarter
Monitoring Location |
Minimum |
Maximum |
Average |
Air Quality |
|||
1 hour Total
Suspended Particulate |
|||
SR77 |
|
|
|
24 hour Total
Suspended Particulate |
|||
SR77 |
|
|
|
Construction Noise |
|||
SR77 |
59.0 |
|
65. |
Water Quality |
|||
Dissolved
Oxygen |
|||
I5 |
6mg/L |
11.5mg/L |
8.7mg/L |
Suspended
Solid |
|||
I5 |
<2.5mg/L |
16mg/L |
5.7mg/L |
Turbidity |
|||
I5 |
3.9NTU |
29.7NTU |
7.8NTU |
3.2.1
The
number of exceedances event recorded in the reporting quarter is summarized in Table
3.2Table 3.2.
Table 3.2 Summary of Exceedance Events in the Reporting Quarter
Parameter |
Criteria |
Number of Exceedances Events |
Number of Project Related Exceedance Events |
Air Quality |
|||
1-hour Total
Suspended Particulates |
Action Level |
0 |
0 |
Limit
Level |
0 |
0 |
|
24-hour Total
Suspended Particulates |
Action Level |
0 |
0 |
Limit
Level |
0 |
0 |
|
Construction Noise |
|||
Leq 30min |
Action Level |
0 |
0 |
Limit
Level |
0 |
0 |
|
Water
Quality |
|||
Dissolved
Oxygen |
Action Level |
1 |
0 |
Limit Level |
0 |
0 |
|
Suspended
Solid |
Action Level |
0 |
0 |
Limit Level |
0 |
0 |
|
Turbidity |
Action Level |
0 |
0 |
Limit Level |
0 |
0 |
3.2.2 No exceedance of air monitoring was recorded at SR77 in the reporting quarter.
3.2.3
No exceedance of noise monitoring was recorded at SR77 in the reporting
quarter.
3.2.4 One (1) exceedance of water quality monitoring was recorded at I5 in the reporting quarter.
3.2.5
The
Contractor has been reminded to strengthen the mitigation measures including:
¡P
All
vehicles should be washed to remove any dusty materials before leaving the
construction site.
¡P
Ensure
all vehicles are properly washed to remove mud and debris before leaving the
site.
¡P
Good
housekeeping should be maintained and stagnant water should be removed from
secondary containment regularly.
¡P
Provide
proper chemical and chemical waste management.
¡P
A
spill response procedure shall be in place and absorption material available
for minor spillages.
Water
Quality
¡P
Surface run-off, rainwater and waste water from
construction site discharged into appropriate drains via adequately designed
sand/ silk removal facilities (e.g. sand traps,
sile traps and sedimentation basins) and pH adjusted before discharge.
4.1.1
The
Contractor has registered as a chemical waste producer of the Project. The C&D materials and waste sorting
were carried out on-site.
Receptacles were provided for general refuse collection.
4.1.2
During
the reporting quarter, a total of 3,4942,573m3 of excavated material
has been generated. 1,8821,628m3
of inert C&D materials was disposed of at public fill to Tuen Mun Area 38,
while 435m3 471m3 of
inert C&D materials was reused on site. 315m3
415m3 of general refuse was
disposed of at North East New Territories (NENT) Landfill. 25m3 of plastics and no
paper/cardboard packaging were collected by recycling contractor in the
reporting quarter. 12m3
of metals were collected by recycling contractor in the reporting quarter. No0.8m3 of chemical waste wasere
collected by licensed contractor in the reporting quarter. Details of the waste management data are
presented in Appendix F.
5.1.1
No
environmental non-compliance was recorded in the reporting quarter. No environmental complaint was received. No environmental related prosecution or
notification of summons was received in the reporting quarter. The summary for the non-compliance, complaints
and prosecutions is provided in Appendix G.
6.1.1
The
EM&A programme was carried out by the ET in accordance with the EM&A
Manual requirements. It is
concluded from the environmental monitoring and audit works that adequate
environmental mitigation measures have been implemented by the civil works
contractors where appropriate in the reporting quarter.
6.1.2
In
the reporting quarter, one (1)no
exceedance events wereas recorded.
6.1.3
No environmental non-compliance was recorded in the reporting
quarter. No environmental complaints were received in the reporting quarter. No environmental related prosecution or
notification of summons was received in the reporting
quarter.
6.1.4
The box culvert works have
been partially completed by the end of March 2014 except the last construction
activity, installation of a base slab at Box Culvert ID4. Due to the loading requirement of a
fresh water main under the box culvert, installation of the base slab at Box
Culvert ID4 has been scheduled to
be commenced in December 2016.
6.1.5 The construction works at the box culvert ID4 are temporarily suspended until the utilities diversion works complete. The 4-week post construction water quality monitoring will be commenced after the installation of the base slab finishes, hence the completion of the box culvert works.