TABLE OF CONTENTS

Page

EXECUTIVE SUMMARY  2

1       Introduction  4

1.1     Project Organization and Contacts of Key Management 4

1.2     Programme  4

1.3     Summary of Construction Works  4

2       Environmental Monitoring and Audit Requirements  6

2.1     Monitoring Parameters  6

2.2     Monitoring Locations  6

2.3     Environmental Quality Performance Limits (Action/Limit Levels) 6

2.4     Environmental Mitigation Measures  6

3       air quality monitoring   6

4       Noise MONITORING   7

5       Advice on the Solid and Liquid Waste Management Status  7

6       Summary of Exceedances of the Environmental Quality Performance Limit  8

7       Summary of Complaints, Notifications of Summons and Successful Prosecutions  8

8       Comments, recommendations and Conclusions  9

8.1     Comments  9

8.2     Recommendations  10

8.3     Conclusions  10

 

List of Tables

                                                                                                                                              

Table 1.1         Contact Information of Key Personnel

Table 3.1         Summary of 1-hour TSP Monitoring Results in the Reporting Period

Table 3.2         Summary of 24-hour TSP Monitoring Results in the Reporting Period

Table 3.3        Summary of the Number of Exceedances for 1-hr & 24-hr TSP Monitoring

Table 4.1         Summary of Construction Noise Monitoring Results in the Reporting Period

Table 4.2        Summary of the Number of Monitoring Exceedances for Construction Noise

Table 5.1         Summary of Waste Flow Table

 

Figures

 

Figure 1.1         General Project Layout Plan

Figure 1.2a-b     Locations of Monitoring Station

 

List of Appendices

 

Appendix A       Project Organization Structure

Appendix B       Construction Programme

Appendix C       Implementation Schedule of Environmental Mitigation Measures (EMIS)

Appendix D      Summary of Action and Limit Levels

Appendix E       Impact Air Quality Monitoring Results and their Graphical Presentation

Appendix F       Meteorological Data

Appendix G      Impact Daytime Construction Noise Monitoring Results and their Graphical Presentation

Appendix H       Statistics on Complaints, Notifications of Summons and Successful Prosecutions


 

EXECUTIVE SUMMARY

The proposed widening of Tolo Highway and Fanling Highway between Island House Interchange and Fanling (the Project) is a Designated Project under the Environmental Impact Assessment Ordinance (Cap. 499) (EIAO). An Environmental Impact Assessment (EIA) Report (the approved EIA Report) together with an Environmental Monitoring and Audit (EM&A) Manual (the approved EM&A Manual) were completed and approved under the EIAO on 14 July 2000 (Register Number: EIA-043/2000).

The objective of the Project ¡°Widening of Tolo Highway / Fanling Highway between Island House Interchange and Fanling¡± is to widen Tolo Highway and Fanling Highway to dual 4-lane carriageway in order to alleviate the current traffic congestion problems and to cope with the increasing transport demands to and from the urban areas and also cross boundary traffic.

The construction works for this Project will be delivered in 2 stages i.e. Stage 1 (between Island House Interchange and Tai Hang) and Stage 2 (between Tai Hang and Wo Hop Shek Interchange).  Stage 2 would be implemented under two works contracts.  Contract No. HY2012/06 ¡°Widening of Fanling Highway ¨C Tai Hang to Wo Hop Shek Interchange¡± and the entrusted portion to CEDD under Contract No. CV/2012/09 ¡±Liantang/Heung Yuen Wai Boundary Control Point Site Formation and Infrastructure Works ¨C Contract 3¡±. This report focuses on Contract No. HY2012/06 ¡°Widening of Fanling Highway ¨C Tai Hang to Wo Hop Shek Interchange¡± in Stage 2 of the Project only.

Pursuant to the EP (EP-324/2008/C) Condition 2.7, the Capture Survey Trip Report for Ma Wat River Northern Meander (Version 2) for the Project was submitted on 24 December 2013 by the Environmental Team (ET) and verified by the Independent Environmental Checker (IEC) on 6 January 2014.

The construction phase of the Contract under the EP and the Environmental Monitoring and Audit (EM&A) programme of the contract commenced on 21 November 2013. The impact environmental monitoring and audit includes air quality and noise monitoring.

This report documents the findings of EM&A works conducted in the period between 1 November 2015 and 31 January 2016. As informed by the Contractor, construction activities in the reporting period were as follows:

 

-          Site clearance

-          Ground investigation

-          Piling works

-          Pipe laying

-          Retaining wall construction

-          Noise barrier

-          Excavation

-          Backfilling

-          Drainage

-          Temporary bridge construction

-          House construction

-          Footbridge demolition

-          Bridge construction

Reporting Change

There was no reporting change required in the reporting period.

Breaches of Action and Limit Levels for Air Quality

No exceedance of Action and Limit Level was recorded for 1-hour and 24-hour TSP monitoring in the reporting period.


Breaches of Action and Limit Levels for Noise

No Action or Limit Level exceedance of construction noise was recorded in the reporting period. No noise complaints related to 0700 ¨C 1900 hours on normal weekdays was received and followed by the Environmental Team in the reporting period.

Complaint, Notification of Summons and Successful Prosecution

No complaint, notification of summons or successful prosecution was received in the reporting period.

 

Future Key Issues

 

Key issues to be considered in the coming month include:

 

-       Properly store and label oils and chemicals on site;

-       Chemical, chemical waste and waste management;

-       Collection of construction waste should be carried out regularly;

-       Properly maintain all drainage facilities and wheel washing facilities on site;

-       Exposed slopes should be covered up properly if no temporary work will be conducted;

-       Quieter powered mechanical equipment should be used;

-       Suppress dust generated from excavation activities and haul road traffic; and

-       Tree protective measures for all retained trees should be well maintained.

 


1             Introduction

1.1          Project Organization and Contacts of Key Management

1.1.1       The project organization structure is shown in Appendix A. The key personnel contact names and numbers are summarized in Table 1.1.

  Table 1.1          Contact Information of Key Personnel

Party

Position

Name

Telephone

Fax

 

ER

(Hyder-Arup-Black & Veatch Joint Venture)

 

Chief Resident Engineer

Edwin Chung

6115 0818

2638 0950

 

IEC

 (Mott MacDonald Hong Kong Limited)

 

Independent Environmental Checker

Steven Tang

2828 5920

2827 1823

 

Contractor

 

(China State Construction Engineering (Hong Kong) Limited)

 

Environmental Officer

Michael Tsang

9277 4956

2672 2501

C C Chow

9679 6315

2672 2501

ET

 (AECOM Asia Company Limited)

ET Leader

Y W Fung

3922 9393

   3922 9797

 

1.2          Programme

1.2.1       The Construction Programme is shown in Appendix B.

1.3          Summary of Construction Works

1.3.1       Details of the construction works carried out by the Contractor in this reporting period are listed below:

-          Site clearance

-          Ground investigation

-          Piling works

-          Pipe laying

-          Retaining wall construction

-          Noise barrier

-          Excavation

-          Backfilling

-          Drainage

-          Temporary bridge construction

-          House construction

-          Footbridge demolition

-          Bridge construction

 

1.3.2       The general layout plan of the Project site showing the contract areas is shown in Figure 1.1.

1.3.3       The environmental mitigation measures implementation schedule are presented in Appendix C.


 

2             Environmental Monitoring and Audit Requirements

2.1          Monitoring Parameters

2.1.1       The updated EM&A Manual has designated 1 air quality monitoring station and 2 noise monitoring stations to monitor environmental impacts on air quality and noise due to Stage 2 of the Project.

2.1.2       The updated EM&A Manual also requires environmental site inspections for air quality, noise, water quality, chemical, waste management, ecology and landscape and visual impacts.

2.2          Monitoring Locations

2.2.1       For air quality monitoring, the monitoring station was set up at Fanling Government Secondary School, in accordance with updated EM&A Manual. The location is shown in Figure 1.2a.

2.2.2       For noise monitoring, the monitoring stations M2 and M3 were set up at West Tai Wo and Fanling Government Secondary School respectively in accordance with updated EM&A Manual. Figure 1.2a-b shows the locations of the monitoring stations.

2.3          Environmental Quality Performance Limits (Action/Limit Levels)

2.3.1       The environmental quality performance limits (i.e. Action/Limit Levels) of air quality monitoring were derived from the baseline air quality monitoring results at the monitoring station (AM2); while the environmental quality performance limits of noise monitoring were defined in the EM&A Manual.

2.3.2       The environmental quality performance limits are given in Appendix D.

2.4          Environmental Mitigation Measures

2.4.1       Relevant environmental mitigation measures were stipulated in the Particular Specification and EP for the Contractor to adopt. A list of environmental mitigation measures and their implementation statuses are given in Appendix C.

 

3             air quality monitoring

3.1.1       In accordance with the updated EM&A Manual, baseline 1-hour and 24-hour TSP levels at one air quality monitoring station was established. Impact 1-hour TSP monitoring was conducted for at least three times every 6 days, while impact 24-hour TSP monitoring was carried out for at least once every 6 days.

3.1.2       The weather was mostly sunny, with several fine, cloudy and rainy days in the reporting quarter. Weather information including the wind speed and wind direction is annexed in Appendix F. The information was obtained from the Hong Kong Observatory Tai Po and Tai Mei Tuk Automatic Weather Stations.

3.1.3       The monitoring results for 1-hour TSP and 24-hour TSP monitoring are summarized in Tables 3.1 and 3.2 respectively. Detailed impact air quality monitoring results are presented in Appendix E.

Table 3.1          Summary of 1-hour TSP Monitoring Results in the Reporting Period

Location

Average (mg/m3)

Range (mg/m3)

Action Level  (mg/m3)

Limit Level (mg/m3)

AM2

(Fanling Government Secondary School)

75.3

65.4 ¨C 82.1

317.8

500

 

Table 3.2          Summary of 24-hour TSP Monitoring Results in the Reporting Period

Location

Average (mg/m3)

Range (mg/m3)

Action Level  (mg/m3)

Limit Level (mg/m3)

AM2

(Fanling Government Secondary School)

36.0

7.4 ¨C 58.1

200.7

260

 

3.1.4       The major dust sources in the reporting period included construction activities from Stage 2 of the Project, as well as nearby traffic emissions.

3.1.5       All 1-hour and 24-hour TSP results were below the Action and Limit Level in the reporting quarter.

3.1.6       Detailed impact air quality monitoring results are presented in Appendix E.

 

4             Noise MONITORING

4.1.1       In accordance with the EM&A Manual, impact noise monitoring was conducted for at least once per week during the construction phase of the Contract.

4.1.2       The monitoring results for construction noise are summarized in Table 4.1 and the monitoring data are provided in Appendix G.

  Table 4.1          Summary of Construction Noise Monitoring Results in the Reporting Period

 

Average (dB(A))

Leq (30 mins)

Range (dB(A))

Leq (30 mins)

Limit Level (dB(A)) 

Leq (30 mins)

M2*

69.3

68.6 ¨C 71.0

75

M3#

63.6

60.6 ¨C 69.8

65/70

              *+3dB(A) Façade correction included

# Limit Level of 70dB(A) applies to education institutes while 65dB(A) applies during school examination period.

 

4.1.3       The major noise sources during the noise monitoring included nearby road traffic noise.

4.1.4       No Action or Limit Level exceedance of construction noise was recorded in the reporting period. No noise complaints related to 0700 ¨C 1900 hours on normal weekdays was received and followed by the Environmental Team in the reporting period.

 

4.1.5       The graphical plots of the trends of the monitoring results are provided in Appendix G.

 

5             Advice on the Solid and Liquid Waste Management Status

5.1.1       As advised by the Contractor, 8,573 m3 of inert C&D material was disposed of as public fill to Tuen Mun 38 (of which 0m3 was broken concrete), while 280 m3 of general refuse was disposed of at NENT landfill. 213 kg of paper/cardboard packaging, 0 kg of plastics and 0 kg of metals were collected by recycling contractors in the reporting period. 2,905 m3, 3692 m3, and 1976 m3 of inert C&D materials were reused on site, in other projects and in NENT for backfilling purpose respectively. 0kg of chemical wastes was collected by licensed contractors in the reporting period.

5.1.2       The actual amounts of different types of waste generated by the activities of the Project in the reporting quarter are summarized in Table 5.1.


 

Table 5.1            Summary of Waste Flow Table

 

Waste Type

Actual Amount

Disposal/Reuse Locations

Inert C&D materials

8,573 m3 (of which 0 m3 was broken concrete)

Tuen Mun 38

General refuse

280 m3

NENT Landfill

Paper/cardboard packaging

213 kg

Recycling Contractors

Plastics

0 kg

Recycling Contractors

Metals

0 kg

Recycling Contractors

C&D materials reused on site

2,905 m3

Site Area

C&D materials reused in other projects

3692 m3

Other projects

C&D materials reused in NENT for backfilling

1976 m3

NENT Landfill

Chemical wastes

0 kg

Licensed Contractors

 

6             Summary of Exceedances of the Environmental Quality Performance Limit

6.1.1       All 1-hour and 24-hour TSP monitoring results complied with the Action / Limit Levels in the reporting quarter.

6.1.2       No Action or Limit Level exceedance of construction noise was recorded in the reporting period. No noise complaints related to 0700 ¨C 1900 hours on normal weekdays was received and followed by the Environmental Team in the reporting period.

 

7             Summary of Complaints, Notifications of Summons and Successful Prosecutions

7.1.1       No complaint, notification of summons or successful prosecution was received in the reporting period.

7.1.2       The statistics on complaints, notifications of summons and successful prosecutions are summarized in Appendix H.

7.1.3       A 24-hour complaint hotline at 6628 8366 has been established for the Project. The hotline number is displayed at the site entrances, fencings and project signboards, as well as printed on publications such as newsletters for the public.

 


8             Comments, recommendations and Conclusions

8.1          Comments

8.1.1       According to the environmental site inspections performed in the reporting period, the following comments are made to the Contractor for precautionary and rectification purposes:

Air Quality Impact

¡¤         The Contractor should dampen the road to reduce dust generation.

¡¤         The Contractor should cover the stockpile with impervious sheeting to prevent dust generation.

¡¤         The Contractor should provide proper labels to the non-road mobile machineries.

 

Construction Noise Impact

¡¤         The Contractor should provide the valid NEL on the air compressor.

¡¤         The Contractor should provide proper wrapping to the breaker¡¯s head as mitigating measure.

 

Water Quality Impact

¡¤         The Contractor should remove the stagnant water.

¡¤         The Contractor should provide sufficient mitigation measures to prevent deposited silt and grit from entering public drainage.

¡¤         The Contractor should provide bunding to avoid waste water to be carried to the public road.

¡¤         The Contractor should provide waste water treatment and mechanism to avoid waste water from entering the public pedestrian pathway.

¡¤         The Contractor should clear the accumulated mud in wheel washing basins regularly.

¡¤         The Contractor should clean the sedimentation tank regularly.

¡¤         The Contractor should clear the blocked drainage and provide proper mechanism to avoid waste water from entering the public road.

¡¤         The Contractor should clean the mud trail and adopt effective wheel washing mechanism to prevent any muddy trail from entering the public haul road.

 

 

Chemical and Waste Management

¡¤         The Contractor should remove the mud stain and oil stain properly.

¡¤         The Contractor should remove the waste frequently.

¡¤         The Contractor should provide drip tray to the chemicals to prevent leakage to ground.

¡¤         The Contractor should review the house-keeping practices and clear the trash in a timely manner.

¡¤         Oil stain was found on ground leaked from a breaker¡¯s head. The Contractor should clear the oil stain and disposed of as chemical waste.

 

Landscape and Visual Impact

¡¤         Nil.

 

Miscellaneous

¡¤         The Contractor should clean the public road in a timely manner.

¡¤         The Contractor should clean the pedestrian pathway regularly.

 


8.2          Recommendations

8.2.1       The impact air quality and noise monitoring programme ensures that any deterioration in environmental condition is readily detected and timely actions are taken to rectify any non-compliances. Assessment and analysis of monitoring results collected demonstrated the environmental acceptability of the Project. The weekly environmental site inspections ensure that all the environmental mitigation measures recommended in the ERR are effectively implemented.

8.2.2       The EM&A programme effectively monitored the environmental impacts from the construction activities and no particular recommendations were advised for the improvement of the programme.

8.3          Conclusions

8.3.1       All 1-hour and 24-hour TSP monitoring results complied with the Action / Limit Levels in the reporting quarter.

8.3.2       No Action or Limit Level exceedance of construction noise was recorded in the reporting period. No noise complaints related to 0700 ¨C 1900 hours on normal weekdays was received and followed by the Environmental Team in the reporting period.

8.3.3       No complaint, notification of summons or successful prosecution was received in the reporting period.