TABLE OF CONTENTS
Page
1.1 Project
Organization and Contacts of Key Management
1.3 Summary
of Construction Works
2 Environmental Monitoring and Audit Requirements
2.3 Environmental
Quality Performance Limits (Action/Limit Levels)
2.4 Environmental
Mitigation Measures
5 Advice on the Solid and Liquid Waste Management Status
6 Summary of Exceedances of the Environmental Quality Performance Limit
7 Summary of Complaints, Notifications of Summons and Successful
Prosecutions
8 Comments, recommendations and Conclusions
List of
Tables
Table 1.1 Contact Information of Key Personnel
Table 3.1 Summary of 1-hour TSP
Monitoring Results in the Reporting Period
Table 3.2 Summary of 24-hour
TSP Monitoring Results in the Reporting Period
Table 3.3 Summary of the Number of Exceedances for 1-hr &
24-hr TSP Monitoring
Table 4.1 Summary of Construction Noise Monitoring Results in
the Reporting Period
Table 4.2 Summary of the Number of Monitoring Exceedances for
Construction Noise
Table 5.1 Summary of
Waste Flow Table
Figure 1.1 General
Project Layout Plan
Figure 1.2a-b Locations
of Monitoring Station
List of Appendices
Appendix A Project
Organization Structure
Appendix B Construction
Programme
Appendix C Implementation
Schedule of Environmental Mitigation Measures (EMIS)
Appendix D Summary of Action
and Limit Levels
Appendix E Impact
Air Quality Monitoring Results and their Graphical Presentation
Appendix F Meteorological
Data
Appendix G Impact
Daytime Construction Noise Monitoring Results and their Graphical Presentation
Appendix H Statistics
on Complaints, Notifications of Summons and Successful Prosecutions
The proposed widening of Tolo Highway and Fanling Highway
between Island House Interchange and Fanling (the
Project) is a Designated Project under the Environmental Impact Assessment
Ordinance (Cap. 499) (EIAO). An Environmental Impact Assessment (EIA) Report
(the approved EIA Report) together with an Environmental Monitoring and Audit
(EM&A) Manual (the approved EM&A Manual) were completed and approved
under the EIAO on 14 July 2000 (Register Number: EIA-043/2000).
The objective of the Project ¡°Widening of Tolo
Highway / Fanling Highway between Island House
Interchange and Fanling¡± is to widen Tolo Highway and Fanling Highway
to dual 4-lane carriageway in order to alleviate the current traffic congestion
problems and to cope with the increasing transport demands to and from the
urban areas and also cross boundary traffic.
The construction works for this Project will be delivered in 2 stages
i.e. Stage 1 (between Island House Interchange and Tai Hang) and Stage 2
(between Tai Hang and Wo Hop Shek Interchange). Stage 2 would be implemented under two
works contracts. Contract No. HY2012/06 ¡°Widening of Fanling Highway ¨C
Tai Hang to Wo Hop Shek Interchange¡± and the
entrusted portion to CEDD under Contract No. CV/2012/09
¡±Liantang/Heung Yuen Wai Boundary Control
Point Site Formation and Infrastructure Works ¨C Contract 3¡±. This
report focuses on
Contract No. HY2012/06 ¡°Widening of Fanling Highway ¨C Tai Hang to Wo Hop Shek Interchange¡± in Stage 2 of
the Project only.
Pursuant
to the EP (EP-324/2008/A) Condition 2.7, the Capture Survey Trip Report for Ma Wat River Northern Meander (Version 2) for the Project was
submitted on 24 December 2013 by the Environmental Team (ET) and verified by
the Independent Environmental Checker (IEC) on 6 January 2014.
The
construction phase of the Contract under the EP and the Environmental
Monitoring and Audit (EM&A) programme of the contract commenced on 21 November 2013. The impact
environmental monitoring and audit includes air quality and noise monitoring.
This report documents the
findings of EM&A works conducted in the period between 1 November 2014 and
31 January 2015. As informed by the Contractor, construction activities in the
reporting period were:
- Ground investigation;
- Tree felling and transplantation;
- Piling works;
- Pipe laying;
- Retaining wall construction;
- Excavation;
- Backfilling;
- Drainage;
- Temporary bridge construction;
- Box culvert construction;
- Noise barrier construction;
- Houses demolition; and
- Soil nail.
There was no reporting change
required in the reporting period.
Breaches of Action and Limit Levels for Air
Quality
No
exceedance of Action and Limit Level was recorded for 1-hour and 24-hour TSP monitoring
in the reporting period.
Breaches of Action and Limit Levels for Noise
No Action Level exceedance of construction noise was recorded in the reporting period, since no noise complaints related to 0700 ¨C 1900 hours on normal weekdays was received and followed by Environmental Team in the reporting period.
One (1) Limit Level exceedance was recorded on 15 January 2015 for noise monitoring at M3 in the reporting period. The exceedance was considered non-project-related.
Table 1.1 Contact Information of Key Personnel
Position |
Name |
Telephone |
Fax |
|
ER (Hyder-Arup-Black
& Veatch Joint Venture) |
Chief Resident Engineer |
Edwin
Chung |
6115 0818 |
2638 0950 |
IEC (Mott MacDonald Hong Kong Limited) |
Independent Environmental
Checker |
Terence Kong |
2828 5919 |
2827 1823 |
Contractor (China State Construction
Engineering (Hong Kong) Limited) |
Environmental Officer |
Michael Tsang |
9277 4956 |
2672 2501 |
C C
Chow |
9679 6315 |
2672 2501 |
||
ET (AECOM Asia Company Limited) |
ET Leader |
Y W Fung |
3922 9393 |
3922 9797 |
- Site clearance;
- Ground investigation;
- Tree felling and transplantation;
- Piling works;
- Pipe laying;
- Retaining wall construction;
- Excavation;
- Backfilling;
- Drainage;
- Temporary bridge construction;
- Box culvert construction;
- Noise barrier construction;
- Houses demolition; and
- Soil nail.
Table 3.1 Summary
of 1-hour TSP Monitoring Results in the Reporting Period
Location |
Average (mg/m3) |
Range (mg/m3) |
Action Level (mg/m3) |
Limit Level (mg/m3) |
AM2 (Fanling Government Secondary School) |
77.5 |
66.6 ¨C 83.2 |
317.8 |
500 |
Table 3.2 Summary
of 24-hour TSP Monitoring Results in the Reporting Period
Location |
Average (mg/m3) |
Range (mg/m3) |
Action Level (mg/m3) |
Limit Level (mg/m3) |
AM2 (Fanling Government Secondary School) |
61.1 |
17.7 ¨C 157.8 |
200.7 |
260 |
Table
4.1 Summary of Construction Noise Monitoring Results in the Reporting
Period
|
Average (dB(A)) Leq (30 mins) |
Range (dB(A)) Leq (30 mins) |
Limit Level (dB(A)) Leq (30 mins) |
M2* |
68.9 |
64.7 ¨C 70.3 |
75 |
M3# |
63.5 |
60.0 ¨C 66.7 |
65/70 |
*+3dB(A) Façade correction included
# Limit Level of 70dB(A) applies to
education institutes while 65dB(A) applies during school examination period.
Table 5.1 Summary of Waste Flow Table
Waste
Type |
Actual
Amount |
Disposal/Reuse
Locations |
Inert
C&D materials |
4,643 m3 (of which 0m3 was broken concrete) |
Tuen Mun
38 |
General refuse |
490 m3 |
NENT Landfill |
Paper/cardboard
packaging |
171 kg |
Recycling Contractors |
Plastics |
0kg |
Recycling Contractors |
Metals |
0kg |
Recycling Contractors |
C&D
materials reused on site |
2,002 m3 |
Site Area |
C&D
materials reused in other projects |
1,761 m3 |
Other projects |
C&D
materials reused in NENT for backfilling |
880 m3 |
NENT Landfill |
Chemical wastes |
0kg |
Licensed Contractors |
Air Quality Impact
Construction Noise Impact
Water Quality Impact
Chemical and Waste
Management
Landscape and
Visual Impact
Miscellaneous