Contents
Page
EXECUTIVE SUMMARY i
1 INTRODUCTION AND PROJECT INFORMATION 1
1.1 Background.............................................................................................................. 1
1.2 Construction
Programme and Activities.................................................................. 1
1.3 Project
Organisation................................................................................................ 1
1.4 Purpose of the
Report.............................................................................................. 2
2 SUMMARY OF EM&A REQUIREMENTS 2
2.1 Monitoring
Requirements........................................................................................ 2
2.2 Environmental
Mitigation Measures........................................................................ 2
3 SUMMARY OF EM&A Monitoring Data 2
3.1 Monitoring Data........................................................................................................ 2
3.2 Summary of
Monitoring Exceedances..................................................................... 3
4 WASTE MANAGEMENT 3
5 ENVIRONMENTAL NON-CONFORMANCE 3
6 CONCLUSION, COMMENTS AND
RECOMMENDATIONS 4
Table 1.1 Contact Information of Key Personnel
Table 2.1 Monitoring Parameter
Table 3.1 Summary of Monitoring Data in the Reporting Quarter
Table 3.2 Summary of Exceedance Events in the Reporting Quarter
List of Figures
Figure 2 Environmental
Monitoring Locations
List of Appendices
Appendix A Construction Programme
Appendix B Project Organization Structure
Appendix C Implementation Schedule of Environmental Mitigation Measures
(EMIS)
Appendix D Meteorological Data Extracted from Hong Kong Observatory(NIL)
Appendix E Environmental Monitoring Data for Air Quality and Noise(NIL)
Appendix G Statistics on Complaints, Notifications of Summons and
Successful Prosecutions
This report documents the findings of EM&A works conducted in the
quarter between 1 May 2021 and 31 July 2021.
The impact stage EM&A programme for the Project includes air quality
and noise monitoring.
The EM&A programme was carried out by the ET in accordance with the
EM&A Manual requirement. It is
concluded from the environmental monitoring and audit works that adequate
environmental mitigation measures have been implemented by the civil works
contractors where appropriate in the reporting quarter.
In the reporting quarter, no exceedance event was recorded. No necessary
remedial actions have been taken.
No environmental
non-compliance was recorded in the reporting
quarter. No environmental complaint was received in
the reporting quarter. No environmental
related prosecution or notification of summons was received in the reporting
quarter.
The box culvert works have been partially
completed by the end of March 2014 except the last construction activity,
installation of a base slab at Box Culvert ID4. The installation of the base
slab at Box Culvert ID4 was commenced in December 2016 and has been completed
in March 2017.
The 4-week post construction water quality
monitoring has been commenced and completed in April 2017.
As informed by the contractor, all major construction activities of the
Entrusted Portion Project of Section 1A and 1B were substantially completed on
28 September 2018 and 3 October 2018 respectively. In such regard, the EM&A
Programme of the captioned project, including monthly EM&A reporting and
the corresponding environmental monitoring and audit works, is no longer
required and we have submitted the termination proposal to EPD on 4 April 2018.
And EPD replied the Final EM&A Report need to be provided to facilitate the
consideration of cessation of construction phase EM&A Programme and the
EM&A monitoring and audit works will not be terminated without prior
approval of EPD.
1.1.1
The Project is a Designated
Project under the Environmental Impact Assessment Ordinance (EIAO) (Cap.
499). An Environmental Impact
Assessment (EIA) Report together with an Environmental Monitoring and Audit
(EM&A) Manual were approved on 14 July 2000 (Register Number:
EIA-043/2000). The Project is
governed by an Environmental Permit (EP) (EP-324/2008) which was granted on 23
December 2008. A variation of EP
(VEP) was applied and the VEP (EP-324/2008/A) was subsequently granted on 31
January 2012. An
additional VEP has been applied on 24 February 2014 and the VEP (EP-324/2008/B)
was subsequently granted on 17 March 2014.
Furthermore, an additional VEP has been applied
on 9 March 2015 and the VEP (EP-324/2008/C) was subsequently granted on 27
March 2015. The previous
VEP (EP-324/2008/D) was
granted on 27 August 2015. The current VEP (EP-324/2008/E)
was granted on 26 January 2017.
1.1.2
Chun
Wo Construction & Engineering Co Ltd (Chun Wo) was commissioned by the
Civil Engineering and Development Department (CEDD) as the Civil Contractor for
the Entrusted Portion of Widening of Tolo Highway/Fanling Highway between
Island House Interchange and Fanling Stage 2. Meinhardt Infrastructure &
Environment Ltd (MIEL) has been appointed by Chun Wo as the Environmental Team
(ET) to fulfill the corresponding EM&A requirements pursuant to
Environmental Permit No. EP-324/2008/D in accordance with the Updated EM&A
Manual (dated March 2015) for Widening
of Tolo Highway/Fanling Highway between Island House Interchange and Fanling
Stage 2. The EM&A programme
commenced in 5 November 2013.
1.1.3
Figure 1 shows the works areas for the
Entrusted Portion of Widening of Tolo Highway/Fanling Highway between Island
House Interchange and Fanling Stage 2.
1.2.1
No
construction activities undertaken in the reporting month. No construction
programme will be presented in Appendix A
2.1.1
The
project organization structure is shown in Appendix B. The key personnel contact names and
numbers for the Project, together with the general enquiry hotline, are
summarised in Table 2.1.
Table 2.1 Contact Information of Key Personnel
Party |
Role |
Position |
Name |
Telephone |
Fax |
AECOM |
Engineer¡¦s
Representative |
Senior
Resident Engineer |
Mr. Julian
Ling/ Mr. Eddie Luk |
2171 3303 |
2171 3498 |
Mott MacDonald |
Independent Environmental Checker (IEC) |
IEC |
Mr. Steven Tang |
2828 5920 |
2827 1823 |
Chun Wo |
Contractor |
Site Agent |
Mr. Chan |
2638 6144 |
2638 7077 |
Environmental Officer |
Mr. Yip Yun Lam |
3166 5111 |
|||
Meinhardt |
Environmental Team (ET) |
ET Leader |
Mr. WK. Chiu |
2859 5881 |
2540 1580 |
Enquiry Hotline |
General Enquiry |
-- |
Ms Helena Mak |
6355 1731 |
-- |
2.2.1
This
is the Quarterly EM&A Report which summaries the impact monitoring results
and audit findings for the Project during the reporting period between 1 May 2021
to 31 July 2021.
3.1.1
In
accordance with the Updated EM&A Manual, environmental parameters including
Air Quality and Noise have been monitored.
The specific parameters, monitoring frequency and the respective Action
and Limit Levels are given in Table 3.1 and the location of the monitoring
station is shown in the Figure 2.
Table 3.1 Monitoring Parameter
Parameter |
Unit |
Action
Level |
Limit Level |
Frequency |
Air Quality |
||||
1-hour
TSP |
mg/m3 |
292.7 |
500 |
Three times every 6 days |
24-hour
TSP |
mg/m3 |
170.3 |
260 |
Once every 6 days |
Construction Noise |
||||
Leq 30min |
dB(A) |
When
one documented valid complaint is received |
75 |
Once every Week |
3.1.2
The box
culvert works have been completed in the end of March 2017. The 4-week post
construction water quality monitoring has been completed in the end of April
2017 in the same manner as the impact monitoring.
3.2.1
Environmental
mitigation measures have been recommended in the EM&A Manual and are given
in Appendix C. The implementation
status for the reporting quarter is also given in the Appendix.
4.1.1
As
no remaining construction activities will be undertaken, the air quality and
noise monitoring has been suspended since 31 October 2020. Thus, no air
quality, noise monitoring results and the graphical presentation of air quality,
noise monitoring data will be presented.
Table 4.1 Summary of Monitoring Data in the Reporting
Quarter
Monitoring Location |
Minimum |
Maximum |
Average |
Air Quality |
|||
1 hour Total
Suspended Particulate |
|||
SR77 |
- |
- |
- |
24 hour Total
Suspended Particulate |
|||
SR77 |
- |
- |
- |
Construction Noise |
|||
SR77 |
- |
- |
- |
4.2.1
The
number of exceedances event recorded in the reporting quarter is summarized in Table 4.2.
Table 4.2 Summary of Exceedance Events in the
Reporting Quarter
Parameter |
Criteria |
Number of Exceedances Events |
Number of Project Related Exceedance Events |
Air Quality |
|||
1-hour Total
Suspended Particulates |
Action Level |
0 |
0 |
Limit
Level |
0 |
0 |
|
24-hour Total
Suspended Particulates |
Action Level |
0 |
0 |
Limit
Level |
0 |
0 |
|
Construction Noise |
|||
Leq 30min |
Action Level |
0 |
0 |
Limit
Level |
0 |
0 |
|
Limit
Level |
0 |
0 |
4.2.2
No exceedance of Action
Level and Limit level for 1-hour TSP and 24-hour TSP monitoring were recorded at SR77 in the reporting quarter.
4.2.3
No exceedance of noise monitoring was recorded at SR77 in the
reporting quarter.
5.1.1
The
Contractor has registered as a chemical waste producer of the Project. The C&D materials and waste sorting
were carried out on-site.
Receptacles were provided for general refuse collection.
5.1.2
During
the reporting quarter, a total of 0m3 of excavated material has been
generated. 0m3 of inert C&D materials was disposed of at public
fill to Tuen Mun Area 38, while 0m3 of inert C&D materials was reused
on site. 0m3 of general refuse was disposed of at North East New
Territories (NENT) Landfill. No plastics
and no paper/cardboard packaging were collected by recycling contractor in the
reporting quarter. No metals were
collected by recycling contractor in the reporting quarter. No chemical waste was
collected by licensed contractor in the reporting quarter. Details of the waste management data are
presented in Appendix F.
6.1.1
No
environmental non-compliance was recorded in the reporting quarter. No environmental complaint was received. No environmental related prosecution or
notification of summons was received in the reporting quarter. The summary for the non-compliance,
complaints and prosecutions is provided in Appendix G.
7.1.1
The
EM&A programme was carried out by the ET in accordance with the EM&A
Manual requirement. It is concluded
from the environmental monitoring and audit works that adequate environmental
mitigation measures have been implemented by the civil works contractors where
appropriate in the reporting quarter.
7.1.2
In
the reporting quarter, no exceedance event was recorded.
7.1.3
No environmental non-compliance was recorded in the reporting
quarter. No environmental complaints were received in the reporting quarter. No environmental related prosecution or
notification of summons was received in the reporting
quarter.
7.1.4
The box
culvert works have been completed in the end of March 2017. The 4-week post
construction water quality monitoring has been completed in the end of April
2017 in the same manner as the impact monitoring.