Contents
Page
EXECUTIVE SUMMARY i
1 INTRODUCTION AND PROJECT INFORMATION 1
1.1 Background.............................................................................................................. 1
1.2 Construction Programme
and Activities.................................................................. 1
1.3 Project
Organisation................................................................................................ 2
1.4 Purpose of the
Report.............................................................................................. 2
2 SUMMARY OF EM&A REQUIREMENTS 2
2.1 Monitoring
Requirements......................................................................................... 2
2.2 Environmental
Mitigation Measures........................................................................ 3
3 SUMMARY OF EM&A Monitoring Data 3
3.1 Monitoring Data........................................................................................................ 3
3.2 Summary of
Monitoring Exceedances.................................................................... 3
4 WASTE MANAGEMENT 4
5 ENVIRONMENTAL NON-CONFORMANCE 54
6 CONCLUSION, COMMENTS AND
RECOMMENDATIONS 5
Table 1.1 Contact Information of Key Personnel
Table 2.1 Monitoring Parameter
Table 3.1 Summary of Monitoring Data in the Reporting Quarter
Table 3.2 Summary of Exceedance Events in the Reporting Quarter
List of Figures
Figure 2 Environmental
Monitoring Locations
List of Appendices
Appendix A Construction
Programme
Appendix B Project Organization Structure
Appendix C Implementation Schedule of Environmental
Mitigation Measures (EMIS)
Appendix D Meteorological Data Extracted from Hong
Kong Observatory
Appendix E Environmental Monitoring Data for Air
Quality and Noise
Appendix G Statistics on Complaints, Notifications
of Summons and Successful Prosecutions
This report documents the findings of EM&A works conducted in the
quarter between 1 August February November 2017
and 301
October AprilJanuary
20178.
The impact stage EM&A programme for the Project includes air quality
and noise monitoring.
The EM&A programme was carried out by the
ET in accordance with the EM&A Manual requirements. It is concluded from the environmental
monitoring and audit works that adequate environmental mitigation measures have
been implemented by the civil works contractors where appropriate in the
reporting quarter.
In the reporting quarter, nooneno
exceedance events
wereas
recorded. No necessary remedial actions have been taken.
No environmental
non-compliance was recorded in the reporting
quarter. NoOneNo environmental complaints wasere received on 28 December 2017 in the reporting quarter. No environmental related prosecution or
notification of summons was received in the reporting quarter.
The box culvert works have been partially
completed by the end of March 2014 except the last construction activity,
installation of a base slab at Box Culvert ID4. The installation of the base
slab at Box Culvert ID4 was commenced in December 2016 and has been completed
in March 2017.
The 4-week post construction water quality
monitoring has been commenced and completed in April 2017.
1.1.1 The Project is a Designated Project under the Environmental Impact Assessment Ordinance (EIAO) (Cap. 499). An Environmental Impact Assessment (EIA) Report together with an Environmental Monitoring and Audit (EM&A) Manual were approved on 14 July 2000 (Register Number: EIA-043/2000). The Project is governed by an Environmental Permit (EP) (EP-324/2008) which was granted on 23 December 2008. A variation of EP (VEP) was applied and the VEP (EP-324/2008/A) was subsequently granted on 31 January 2012. An additional VEP has been applied on 24 February 2014 and the VEP (EP-324/2008/B) was subsequently granted on 17 March 2014. Furthermore, an additional VEP has been applied on 9 March 2015 and the VEP (EP-324/2008/C) was subsequently granted on 27 March 2015. The previous VEP (EP-324/2008/D) was granted on 27 August 2015. The current VEP (EP-324/2008/E) was granted on 26 January 2017.
1.1.2
Chun
Wo Construction & Engineering Co Ltd (Chun Wo) was
commissioned by the Civil Engineering and Development Department (CEDD) as the
Civil Contractor for the Entrusted Portion of Widening of Tolo Highway/Fanling
Highway between Island House Interchange and Fanling
Stage 2. Meinhardt Infrastructure
& Environment Ltd (MIEL) has been appointed by Chun Wo
as the Environmental Team (ET) to fulfill the
corresponding EM&A requirements pursuant to Environmental Permit No.
EP-324/2008/D in accordance with the Updated EM&A Manual (dated March
2015) for Widening of Tolo
Highway/Fanling Highway between Island House
Interchange and Fanling Stage 2. The EM&A programme commenced in 5
November 2013.
1.1.3
Figure 1 shows the works areas for the
Entrusted Portion of Widening of Tolo Highway/Fanling Highway between Island
House Interchange and Fanling Stage 2.
1.2.1
The
construction programme is presented in Appendix A. The major construction activities
undertaken in the reporting quarter are summarized below:
¡P
Cable
Detection and Trial Trenches; |
¡P
Remaining
Works on New |
¡P
Noise
Barrier Construction; |
¡P
Road Pavement Works; |
¡P
Viaduct segment erection; |
¡P
Demolition
of Existing Kiu Tau Vehicular Bridge; |
¡P
Water
main laying works (on Grade and on bridge deck) |
¡P
Installation
of Noise barrier steel column & panel |
¡P
Parapet
Installation on bridge deck |
¡P
Drainage
Work ¡P
Mini-pile
installation; |
¡P
Construction
of Profile Barrier & Planter Wall on Bridge Deck; |
¡P
Stressing
of External Tendon; |
¡P
Construction
of Retaining Wall Behind Abutment; ¡P
Bitumen paving on bridge deck; ¡P
Installation of deck cell light inside the bridge
deck; ¡P
Installation of movement joint on the bridge ¡P
Construction of retaining wall; and ¡P
Landscaping works. |
|
|
1.3.1
The
project organization structure is shown in Appendix B. The key personnel contact names and
numbers for the Project, together with the general enquiry hotline, are
summarised in Table 1.1Table 1.1.
Table 1.1 Contact Information of Key Personnel
Party |
Role |
Position |
Name |
Telephone |
Fax |
AECOM |
Engineer¡¦s
Representative |
Senior
Resident Engineer |
Mr. Alan Lee |
2171 3303 |
2171 3498 |
Resident Engineer (Environmental) |
Mr. Perry Yam |
2171 3350 |
|||
Mott MacDonald |
Independent Environmental Checker (IEC) |
IEC |
Mr. Steven Tang |
2828 5920 |
2827 1823 |
Chun Wo |
Contractor |
Site Agent |
Mr. Daniel Ho |
2638 6144 |
2638 7077 |
Environmental Officer |
Ms. Tiffany Tsang |
2638 6150 |
|||
Meinhardt |
Environmental Team (ET) |
ET Leader |
Mr. Fredrick Leong |
2859 1739 |
2540 1580 |
Enquiry Hotline |
General Enquiry |
-- |
Ms Helena Mak |
6355 1731 |
-- |
1.4.1
This
is the Quarterly EM&A Report which summaries the impact monitoring results
and audit findings for the Project during the reporting period between 11
August FebruaryNovember 20187 and 301 October AprilJanuary 20178.
2.1.1
In
accordance with the Updated EM&A Manual, environmental parameters including
Air Quality and Noise have been monitored.
The specific parameters, monitoring frequency and the respective Action
and Limit Levels are given in Table
2.1Table 2.1 and the location of the monitoring
station is shown in the Figure 2.
Table 2.1 Monitoring Parameter
Parameter |
Unit |
Action
Level |
Limit Level |
Frequency |
Air Quality |
||||
1-hour
TSP |
mg/m3 |
292.7 |
500 |
Three times every 6 days |
24-hour
TSP |
mg/m3 |
170.3 |
260 |
Once every 6 days |
Construction Noise |
||||
Leq
30min |
dB(A) |
When
one documented valid complaint is received |
75 |
Once every Week |
2.1.2 The box culvert works have been completed in the end of March 2017. The 4-week post construction water quality monitoring has been completed in the end of April 2017 in the same manner as the impact monitoring.
2.2.1
Environmental
mitigation measures have been recommended in the EM&A Manual and are given
in Appendix C. The implementation
status for the reporting quarter is also given in the Appendix.
3.1.1
Monitoring has been conducted in accordance with the
specification in the EM&A Manual in the reporting quarter. Meteorological data for the reporting
quarter have been extracted from Hong Kong Observatory and are given in Appendix D. Monitoring data with graphical
presentation for the reporting quarter have been given in Appendix E. A summary on the monitoring results has
also been given in Table
3.1Table 3.1.
Table 3.1 Summary of Monitoring Data in the Reporting Quarter
Monitoring Location |
Minimum |
Maximum |
Average |
Air Quality |
|||
1 hour Total
Suspended Particulate |
|||
SR77 |
|
|
|
24 hour Total
Suspended Particulate |
|||
SR77 |
|
|
|
Construction Noise |
|||
SR77 |
|
|
|
3.2.1
The
number of exceedances event recorded in the reporting
quarter is summarized in Table
3.2Table 3.2.
Table 3.2 Summary of Exceedance Events in the Reporting Quarter
Parameter |
Criteria |
Number of Exceedances
Events |
Number of Project Related Exceedance Events |
Air Quality |
|||
1-hour Total
Suspended Particulates |
Action Level |
0 |
0 |
Limit
Level |
0 |
0 |
|
24-hour Total
Suspended Particulates |
Action Level |
0 |
0 |
Limit
Level |
0 |
0 |
|
Construction Noise |
|||
Leq 30min |
Action Level |
0 |
0 |
Limit
Level |
0 |
0 |
|
Limit
Level |
0 |
0 |
3.2.2
No
exceedance of 1-hour TSP air quality monitoring was recorded at SR77 in the
reporting quarter. OneNoNo exceedance of Action Level and no exceedance for Llimit level for 1-hour TSP
and 24-hour TSP air monitoring wasere recorded at SR77 in the
reporting quarter.
3.2.3 No exceedance of noise monitoring was recorded at SR77 in the reporting quarter.
3.2.4
The
Contractor has been reminded to strengthen the mitigation measures including:
Air Quality
¡P
Watering within site and vehicle washing facilities
shall be enhanced
¡P
Stockpiling shall be covered coverage with impervious
sheeting and/or sufficient water spraying for dust suppression.
¡P
Water spraying shall be enhanced to avoid dust
generation.
¡P Stockpiling shall be covered to avoid dust
generation
Water Quality
¡P
Preventive measure shall be enhanced to prevent
soil/ rock from engineering the WSD area.
¡P Drainage facilities shall be well maintained and
inspected regularly
¡P
Enhancement to water pumping pipe at NB 67 shall be
adopted.
Noise
¡P
NRMM label shall be provided for all relevant
mobile machinery on site.
¡P
Preventive
measure shall be enhanced to prevent soil/ rock from engineering the WSD area.
¡P
Implement sufficient mitigation measures to avoid
runoff leakage from road works areas and divert site effluent to wastewater
treatment facilities
Waste / Chemical Management
¡P Housekeeping shall be enhanced and refuse shall be
collected regularly
¡P Chemical drum should be placed on drip tray.
¡P General
housekeeping shall be enhanced throughout the construction site.
4.1.1
The
Contractor has registered as a chemical waste producer of the Project. The C&D materials and waste sorting
were carried out on-site.
Receptacles were provided for general refuse collection.
4.1.2
During
the reporting quarter, a total of 5,9018,5407,102m3
of excavated material has been generated. 4,3525,2896,563m3 of
inert C&D materials was disposed of at public fill to Tuen
Mun Area 38, while 630450m3
of inert C&D materials was reused on site. 335305425m3
of general refuse was disposed of at North East New Territories (NENT)
Landfill. No plastics and no
paper/cardboard packaging were collected by recycling contractor in the
reporting quarter. No metals were
collected by recycling contractor in the reporting quarter. NoNo33m3
chemical waste was collected by licensed contractor in the reporting quarter. Details of the waste management data are
presented in Appendix F.
5.1.1
No environmental non-compliance was recorded in the
reporting quarter. No
environmental complaint was received. No environmental related prosecution or
notification of summons was received in the reporting quarter. The summary for the non-compliance,
complaints and prosecutions is provided in Appendix G.
1.1.1
No environmental non-compliance was recorded in the
reporting quarter. An environmental complaint regarding air quality
near Kau Lung Hang and Hong Lok Yuen was received on 28 December 2017 in the
reporting quarter. The ET had conducted investigation for the complaint
which concluded that it was unlikely due to the construction works of this
Project. No
environmental complaint was received. No environmental related prosecution or
notification of summons was received in the reporting quarter. The summary for the non-compliance, complaints
and prosecutions is provided in Appendix G.
6.1.1
The
EM&A programme was carried out by the ET in
accordance with the EM&A Manual requirements. It is concluded from the environmental
monitoring and audit works that adequate environmental mitigation measures have
been implemented by the civil works contractors where appropriate in the
reporting quarter.
6.1.2
In
the reporting quarter, no oneno exceedance
events wereas recorded.
6.1.3
No environmental non-compliance was recorded in the reporting
quarter. No environmental complaints were received in the reporting quarter. No environmental related prosecution or
notification of summons was received in the reporting
quarter.
6.1.4 The box culvert works have been completed in the end of March 2017. The 4-week post construction water quality monitoring has been completed in the end of April 2017 in the same manner as the impact monitoring