Contents
Page
EXECUTIVE SUMMARY iii
1 INTRODUCTION AND PROJECT INFORMATION 1
1.1 Background.............................................................................................................. 1
1.2 Construction
Programme and Activities.................................................................. 1
1.3 Project
Organisation................................................................................................ 2
1.4 Purpose of the
Report.............................................................................................. 2
2 SUMMARY OF EM&A REQUIREMENTS 3
2.1 Monitoring
Requirements......................................................................................... 3
2.2 Environmental
Mitigation Measures........................................................................ 3
3 SUMMARY OF EM&A Monitoring Data 3
3.1 Monitoring Data........................................................................................................ 3
3.2 Summary of
Monitoring Exceedances.................................................................... 4
4 WASTE MANAGEMENT 5
5 ENVIRONMENTAL NON-CONFORMANCE 5
6 CONCLUSION, COMMENTS AND
RECOMMENDATIONS 5
Table 1.1 Contact
Information of Key Personnel
Table 2.1 Monitoring
Parameter
Table 3.1 Summary
of Monitoring Data in the Reporting Quarter
Table 3.2 Summary
of Exceedance Events in the Reporting Quarter
List of Figures
Figure 2 Environmental Monitoring
Locations
List of Appendices
Appendix A Construction Programme
Appendix B Project Organization Structure
Appendix C Implementation Schedule of Environmental Mitigation Measures
(EMIS)
Appendix D Meteorological Data Extracted from Hong Kong Observatory
Appendix E Environmental Monitoring Data for Air and Noise
Appendix G Statistics on Complaints, Notifications of Summons and
Successful Prosecutions
This report documents the findings of EM&A works conducted in the
quarter between 1 May 2014 and 31 July 2014.
The impact stage EM&A programme for the Project includes air quality
and noise monitoring.
The EM&A programme was carried out by the
ET in accordance with the EM&A Manual requirements. It is concluded from the environmental
monitoring and audit works that adequate environmental mitigation measures have
been implemented by the civil works contractors where appropriate in the reporting
quarter.
In the reporting quarter, a total of 2 exceedance
events were recorded. The exceedances were concluded not to be project related. No necessary remedial actions have been taken.
No environmental non-compliance was noted. No environmental complaint
was received. No environmental related prosecution or notification of summons
was received in the reporting quarter.
The box culvert works have been partially completed by the end of March 2014 except the last
construction activity, i.e. installation of a base slab at Box Culvert
ID4. Due to the loading requirement
of a fresh water main under the box culvert, installation of the base slab at
Box Culvert ID4 has to be scheduled in November 2015 after the utilities
diversions were completed, and therefore the construction works were temporary
suspended. The 4-week post
construction water quality monitoring will be conducted after the installation
of the base slab finishes, hence the completion of the box culvert works.
As such, impact monitoring for water quality was not necessary in the
reporting quarter due to temporary suspension of the construction works and is
anticipated to be resumed in November 2015 during the course of remaining box
culvert works.
1.1.1
The
Project is a Designated Project under the Environmental Impact Assessment
Ordinance (EIAO) (Cap. 499). An
Environmental Impact Assessment (EIA) Report together with an Environmental
Monitoring and Audit (EM&A) Manual were approved on 14 July 2000 (Register
Number: EIA-043/2000). The Project
is governed by an Environmental Permit (EP) (EP-324/2008) which was granted on
23 December 2008. A variation of EP
(VEP) was applied and the VEP (EP-324/2008/A) was subsequently granted on 31 January
2012. An additional VEP has been applied on 24 February 2014 and the VEP
(EP-324/2008/B) was subsequently granted on 17 March 2014.
1.1.2
Chun
Wo Construction &
Engineering Co Ltd (Chun Wo) was commissioned by the
Civil Engineering and Development Department (CEDD) as the Civil Contractor for
the Entrusted Portion of Widening of Tolo Highway/Fanling Highway between
Island House Interchange and Fanling Stage 2. Meinhardt Infrastructure &
Environment Ltd (MIEL) has been appointed by Chun Wo as the Environmental Team (ET) to fulfill the corresponding EM&A requirements pursuant to
Environmental Permit No. EP-324/2008/B in accordance with the Updated EM&A
Manual (dated October 2013) for Widening of Tolo Highway/Fanling Highway between Island House
Interchange and Fanling Stage 2.
The EM&A programme commenced in 5 November 2013.
1.1.3
Figure 1 shows the works areas for the
Entrusted Portion of Widening of Tolo Highway/Fanling Highway between Island
House Interchange and Fanling Stage 2.
1.2.1
The
construction programme is presented in Appendix A. The major construction activities
undertaken in the reporting quarter are summarized below:
¡P Cable detection and trial trenches;
¡P Tree Felling Works;
¡P Pre-drilling works and piling works;
¡P Bored pile and bored pile wall construction;
¡P Construction of haul road and temporary soil platform for geotechnical works;
¡P Slope upgrading works;
¡P Noise barrier installation;
¡P Mini pile construction;
¡P Extension of box culvert ID04, ID05 and BC01;
¡P Water Pipe Installation;
¡P Diversion of DN1400;
¡P Filling Works;
¡P Laying diameter 1050mm storm drains;
¡P Pile Cap;
¡P Piling works for Bridge E;
¡P Receiving & Jacking Pit;
¡P Retaining Structure;
¡P Road works at Fanling Highway;
¡P Sewer works; and
¡P Soil nail construction.
1.3.1
The
project organization structure is shown in Appendix B. The key personnel contact names and
numbers for the Project, together with the general enquiry hotline, are
summarised in Table 1.1.
Table 1.1 Contact Information of Key Personnel
Party |
Role |
Position |
Name |
Telephone |
Fax |
AECOM |
Engineer¡¦s
Representative |
Senior
Resident Engineer |
Mr. Alan Lee |
2171 3303 |
2171 3498 |
Resident Engineer (Environmental) |
Mr. |
2171 3350 |
|||
Mott MacDonald |
Independent Environmental Checker (IEC) |
IEC |
Mr. Terence Kong |
2828 5919 |
2827 1823 |
Chun Wo |
Contractor |
Site Agent |
Mr. Daniel Ho |
2638 6144 |
2638 7077 |
Senior
Environmental Officer |
Mr. Sam Lam |
2638 6168 |
|||
Environmental Officer |
Mr. |
2638 6181 |
|
||
Meinhardt |
Environmental Team (ET) |
ET Leader |
Mr. Fredrick Leong |
2859 1739 |
2540 1580 |
Enquiry Hotline |
General Enquiry |
-- |
Ms Helena Mak |
6355 1731 |
-- |
1.4.1
This
is the Quarterly EM&A Report which summaries the impact monitoring results
and audit findings for the Project during the reporting period between 1 May
2014 and 31 July 2014.
2.1.1
In
accordance with the Updated EM&A Manual, environmental parameters including
Air Quality and Noise have been monitored.
The specific parameters, monitoring frequency and the respective Action
and Limit Levels are given in Table 2.1 and the location of the monitoring
station is shown in the Figure 2.
Table 2.1 Monitoring Parameter
Parameter |
Unit |
Action
Level |
Limit Level |
Frequency |
Air Quality |
||||
1 hour
TSP |
mg/m3 |
292.7 |
500 |
Three times every 6 days |
24 hour
TSP |
mg/m3 |
170.3 |
260 |
Once every 6 days |
Construction Noise |
||||
Leq
30min |
dB(A) |
When
one documented valid complaint is received |
75 |
Once every Week |
2.1.2 The box culvert works have been partially completed by the end of March 2014 except the last construction activity, i.e. installation of a base slab at Box Culvert ID4. Due to the loading requirement of a fresh water main under the box culvert, installation of the base slab at Box Culvert ID4 has to be scheduled in November 2015 after the utilities diversions were completed, and therefore the construction works are temporary suspended. The 4-week post construction water quality monitoring will be conducted after the installation of the base slab finishes, hence the completion of the box culvert works.
2.1.3 As such, impact monitoring for water quality was not necessary in the reporting quarter due to temporary suspension of the construction works and is anticipated to be resumed in November 2015 during the course of remaining box culvert works.
2.2.1
Environmental
mitigation measures have been recommended in the EM&A Manual and are given
in Appendix C. The implementation
status for the reporting quarter is also given in the Appendix.
3.1.1
Monitoring has been conducted in accordance with the
specification in the EM&A Manual in the reporting quarter. Meteorological data for the reporting
quarter have been extracted from Hong Kong Observatory and are given in Appendix D. Monitoring data with graphical
presentation for the reporting quarter have been given in Appendix E. A summary on the monitoring results has
also been given in Table 3.1.
Table 3.1 Summary of Monitoring Data in the Reporting Quarter
Monitoring Location |
Minimum |
Maximum |
Average |
Air Quality |
|||
1 hour Total
Suspended Particulate |
|||
SR77 |
34.6mg/m3 |
178.9mg/m3 |
96.6mg/m3 |
24 hour Total
Suspended Particulate |
|||
SR77 |
14.7mg/m3 |
402.1mg/m3 |
102.8mg/m3 |
Construction Noise |
|||
SR77 |
58.5dB(A) |
64.0dB(A) |
60.0dB(A) |
3.1.2
The
maximum recorded 24-hour Total Suspended Particulate in the reporting quarter
is 402.1mg/m3
which is higher than the limit level of 260mg/m3. However, respective investigation has been
conducted and concluded the exceedances would not be
project related.
3.2.1
The
number of exceedances event recorded in the reporting
quarter is summarized in Table 3.2.
3.2.2
Investigations
for the exceedances events in the reporting quarter
have been completed. The exceedances were considered not to be related to the
construction works. The respective
investigation reports have been presented in the respective Monthly EM&A
Reports.
Table 3.2 Summary of Exceedance Events in the Reporting Quarter
Parameter |
|
Number of Exceedances
Events |
Number of Project Related Exceedance Events |
Air Quality |
|||
1 hour Total
Suspended Particulate |
Action Level |
0 |
0 |
Limit
Level |
0 |
0 |
|
24 hour Total
Suspended Particulate |
Action Level |
1 |
0 |
Limit
Level |
1 |
0 |
|
Construction Noise |
|||
Leq 30min |
Action Level |
0 |
0 |
Limit
Level |
0 |
0 |
3.2.3
The
Contractor has been reminded to strengthen the mitigation measures including:
¡P Water spraying should be properly implemented whenever necessary for the unpaved roads, access roads and construction areas;
¡P All vehicles should be washed to remove any dusty materials before leaving the construction site;
¡P Wheel washing facilities should be properly maintained to ensure proper functioning;
¡P Silty effluent should be treated/desilted before discharged. Untreated effluent should be prevented from entering public drain channel;
¡P Channels or earth bunds or sand bag barriers should be provided on site to prevent surface runoff and stormwater should be properly directed to silt removal facilities;
¡P Temporarily exposed slopes and stockpiles of dusty materials should be covered by tarpaulin or similar fabric during rainy seasons; and
¡P All chemicals stored on site should be provided with drip trays.
4.1.1
The
Contractor has registered as a chemical waste producer of the Project. The C&D materials and waste sorting
were carried out on-site.
Receptacles were provided for general refuse collection.
4.1.2
During
the reporting quarter, a total of 9,492m3 of excavated material has
been generated. 7,182m3 of
inert C&D materials was disposed of at public fill to Tuen
Mun Area 38, while 1,369m3 of inert
C&D materials was reused on site.
540m3 of general refuse was disposed of at North East New
Territories (NENT) Landfill. 5m3
of plastics and no paper/cardboard packaging and metals were collected by
recycling contractor in the reporting quarter. 21m3 of chemical waste was
collected by licensed contractor in the reporting quarter. Details of the waste management data are
presented in Appendix F.
5.1.1
No
environmental non-compliance was recorded in the reporting quarter. No environmental complaints were received
in the reporting quarter. Investigations
for the exceedances have been conducted. No environmental related prosecution or
notification of summons was received in the reporting quarter. The summary for the non-compliance, complaints
and prosecutions is provided in Appendix G.
6.1.1
The EM&A programme was carried out by the
ET in accordance with the EM&A Manual requirements. It is concluded from
the environmental monitoring and audit works that adequate environmental
mitigation measures have been implemented by the civil works contractors where
appropriate in the reporting quarter.
6.1.2
In
the reporting quarter, a total of 2 exceedance events
have been recorded. No exceedances were concluded to be project related. No necessary remedial actions have been taken.
6.1.3 No environmental non-compliances were noted. No environmental complaint was received. No environmental related prosecution or notification of summons were received in the reporting quarter.
6.1.4 The box culvert works have been partially completed by the end of March 2014 except the last construction activity, i.e. installation of a base slab at Box Culvert ID4. Due to the loading requirement of a fresh water main under the box culvert, installation of the base slab at Box Culvert ID4 has to be scheduled in November 2015 after the utilities diversions were completed, and therefore the construction works are temporary suspended. The 4-week post construction water quality monitoring will be conducted after the installation of the base slab finishes, hence the completion of the box culvert works.
6.1.5 As such, impact monitoring for water quality was not necessary in the reporting quarter due to temporary suspension of the construction works and is anticipated to be resumed in November 2015 during the course of remaining box culvert works.