Contents

 

                                                                                                                                                           

EXECUTIVE SUMMARY                                                                                                               iii

1       INTRODUCTION AND PROJECT INFORMATION                                                           1

1.1         Background.............................................................................................................. 1

1.2         Construction Programme and Activities.................................................................. 1

1.3         Project Organisation................................................................................................ 1

1.4         Purpose of the Report.............................................................................................. 2

2       SUMMARY OF EM&A REQUIREMENTS                                                                           2

2.1         Monitoring Requirements......................................................................................... 2

2.2         Environmental Mitigation Measures........................................................................ 3

3       SUMMARY OF EM&A Monitoring Data                                                                              3

3.1         Monitoring Data........................................................................................................ 3

3.2         Summary of Monitoring Exceedances.................................................................... 4

4       WASTE MANAGEMENT                                                                                                      5

5       ENVIRONMENTAL NON-CONFORMANCE                                                                       5

6       CONCLUSION, COMMENTS AND RECOMMENDATIONS                                             6

 

 

List of Tables

Table 1.1      Contact Information of Key Personnel

Table 2.1      Monitoring Parameter

Table 3.1      Summary of Monitoring Data in the Reporting Quarter

Table 3.2      Summary of Exceedance Events in the Reporting Quarter

 

 

List of Figures

Figure 1        Demarcation of Entrusted Portion of Widening of Tolo Highway/Fanling Highway between Island House Interchange and Fanling ¡V Stage 2

Figure 2        Environmental Monitoring Locations

 

 

List of Appendices

Appendix A  Construction Programme

Appendix B  Project Organization Structure

Appendix C  Implementation Schedule of Environmental Mitigation Measures (EMIS)

Appendix D  Meteorological Data Extracted from Hong Kong Observatory

Appendix E  Environmental Monitoring Data for Air, Noise and Water Quality

Appendix F  Waste Flow Table

Appendix G  Statistics on Complaints, Notifications of Summons and Successful Prosecutions

 


EXECUTIVE SUMMARY

This report documents the findings of EM&A works conducted in the quarter between 1 February 2014 to 30 April 2014.

 

The impact stage EM&A programme for the Project includes air quality, noise and water quality monitoring. 

 

The EM&A programme was carried out by the ET in accordance with the EM&A Manual requirements.  It is concluded from the environmental monitoring and audit works that adequate environmental mitigation measures have been implemented by the civil works contractors where appropriate in the reporting quarter.

 

In the reporting quarter, a total of 9 exceedance events were recorded.  The exceedances were concluded not to be project related.  No necessary remedial actions have been taken.

 

No environmental non-compliance was noted. No environmental complaint was received. No environmental related prosecution or notification of summons was received in the reporting quarter. 

 

The box culvert works has been partially completed by the end of March 2014 except the last construction activity, installation of a base slab at Box Culvert ID4.  Due to the loading requirement of a fresh water main under the box culvert, installation of the base slab at Box Culvert ID4 has to be scheduled to be carried out in November 2015 after the utilities diversions complete.  The construction works are temporary suspended until the utilities diversion works complete.

As such, water quality monitoring has been conducted for the first week of April 2014 only to cover the temporary suspension of the construction work.  The 4-week post construction water quality monitoring will be commenced after the installation of the base slab finishes, hence the completion of the box culvert works.

 

 

 

 


1                 INTRODUCTION AND PROJECT INFORMATION

1.1              Background

1.1.1          The Project is a Designated Project under the Environmental Impact Assessment Ordinance (EIAO) (Cap. 499).  An Environmental Impact Assessment (EIA) Report together with an Environmental Monitoring and Audit (EM&A) Manual were approved on 14 July 2000 (Register Number: EIA-043/2000).  The Project is governed by an Environmental Permit (EP) (EP-324/2008) which was granted on 23 December 2008.  A variation of EP (VEP) was applied and the VEP (EP-324/2008/A) was subsequently granted on 31 January 2012.  An additional VEP has been applied on 24 February 2014 and the VEP (EP-324/2008/B) was subsequently granted on 17 March 2014.

1.1.2          Chun Wo Construction & Engineering Co Ltd (Chun Wo) was commissioned by the Civil Engineering and Development Department (CEDD) as the Civil Contractor for the Entrusted Portion of Widening of Tolo Highway/Fanling Highway between Island House Interchange and Fanling Stage 2.  Meinhardt Infrastructure & Environment Ltd (MIEL) has been appointed by Chun Wo as the Environmental Team (ET) to fulfill the corresponding EM&A requirements pursuant to Environmental Permit No. EP-324/2008/B in accordance with the Updated EM&A Manual (dated March 2014) for Widening of Tolo Highway/Fanling Highway between Island House Interchange and Fanling Stage 2.  The EM&A programme commenced in 5 November 2013.

1.1.3          Figure 1 shows the works areas for the Entrusted Portion of Widening of Tolo Highway/Fanling Highway between Island House Interchange and Fanling Stage 2. 

1.2              Construction Programme and Activities

1.2.1          The construction programme is presented in Appendix A.  The major construction activities undertaken in the reporting quarter are summarized below:

¡P         Cable detection and trial trenches;

¡P         Tree felling works;

¡P         Pre-drilling works and piling works;

¡P         Extension of box culvert ID04, ID05 and BC01;

¡P         Bored pile and Bored pile wall construction;

¡P         Construction of haul road and temporary soil platform for geotechnical works;

¡P         Slope upgrading works;

¡P         Noise barrier installation; and

¡P         Waterworks.

1.3              Project Organisation

1.3.1          The project organization structure is shown in Appendix B.  The key personnel contact names and numbers for the Project, together with the general enquiry hotline, are summarised in Table 1.1.

Table 1.1     Contact Information of Key Personnel

Party

Role

Position

Name

Telephone

Fax

AECOM

Engineer¡¦s Representative

Senior Resident Engineer

Mr. Alan Lee

2472 7228

2472 0132

Resident Engineer (Environmental)

Mr. Perry Yam

2674 2273

--

Mott MacDonald

Independent Environmental Checker (IEC)

IEC

Mr. Terence Kong

2828 5919

2827 1823

Chun Wo

Contractor

Site Agent

Mr. Daniel Ho

2638 6144

2638 7077

Environmental Officer

Mr. Victor Huang

2638 6181

Environmental Officer

Mr. Sam Lam

2638 6147

Meinhardt

Environmental Team (ET)

ET Leader

Mr. Fredrick Leong

2859 1739

2540 1580

Enquiry Hotline

General Enquiry

--

Ms Helena Mak

6355 1731

--

 

1.4              Purpose of the Report

1.4.1          This is the Quarterly EM&A Report which summaries the impact monitoring results and audit findings for the Project during the reporting period of February 2014 to April 2014.

2                 SUMMARY OF EM&A REQUIREMENTS

2.1              Monitoring Requirements

2.1.1          In accordance with the Updated EM&A Manual, environmental parameters including Air Quality, Noise and Water quality have been monitored.  The specific parameters, monitoring frequency and the respective Action and Limit Levels are given in Table 2.1 and the locations of the monitoring and control stations are shown in the Figure 2 and Figure 3.

Table 2.1     Monitoring Parameter

Parameter

Unit

Action Level

Limit Level

Frequency

Air Quality

1 hour TSP

mg/m3

292.7

500

Three times every 6 days

24 hour TSP

mg/m3

170.3

260

Once every 6 days

Construction Noise

Leq 30min

dB(A)

When one documented valid complaint is received

75

Once every Week

Water Quality

Depth

 

--

--

Three occasions per week

Temperature

¢XC

--

--

Three occasions per week

Salinity

ppt

--

--

Three occasions per week

pH

--

--

--

Three occasions per week

DO

mg/L

6.7

4mg/L or 40% saturation at 15 degree Celsius

Three occasions per week

DO Saturation

%

--

--

Three occasions per week

Turbidity

NTU

81.9NTU or 120% of upstream control station¡¦s Tby of the same day

91.9NTU or 130% of upstream control station¡¦s Tby of the same day

Three occasions per week

SS

mg/L

42.6 mg/L or 120% of upstream control station¡¦s SS of the same day

46.8 mg/L or 130% of upstream station¡¦s SS of the same day and specific sensitive receiver water quality requirements

Three occasions per week

 

Temporary Suspension of Box Culvert Works and Temporary of Water Quality Monitoring

2.1.2          The box culvert works has been partially completed by the end of March 2014 except the last construction activity, installation of a base slab at Box Culvert ID4.  Due to the loading requirement of a fresh water main under the box culvert, installation of the base slab at Box Culvert ID4 has to be scheduled to be carried out in November 2015 after the utilities diversions complete.  The construction works are temporary suspended until the utilities diversion works complete.

2.1.3          As such, water quality monitoring has been conducted for the first week of April 2014 only to cover the temporary suspension of the construction work.  The 4-week post construction water quality monitoring will be commenced after the installation of the base slab finishes, hence the completion of the box culvert works.

2.2              Environmental Mitigation Measures

2.2.1          Environmental mitigation measures have been recommended in the EM&A Manual and are given in Appendix C.  The implementation status for the reporting quarter is also given in the Appendix.

3                 SUMMARY OF EM&A Monitoring Data

3.1              Monitoring Data

3.1.1          Monitoring has been conducted in accordance to the specification in the EM&A Manual in the reporting quarter.  Meteorological data for the reporting quarter has been extracted from Hong Kong Observatory and are given in Appendix D.  Monitoring Data with graphical presentation for the reporting quarter have been given in Appendix E.  A summary on the monitoring results has also given in Table 3.1.

Table 3.1     Summary of Monitoring Data in the Reporting Quarter

Monitoring Location

Minimum

Maximum

Average

Air Quality

1 hour Total Suspended Particulate

SR77

129.0mg/m3

232.0mg/m3

180.8mg/m3

24 hour Total Suspended Particulate

SR77

67.1mg/m3

221.5mg/m3

134.3mg/m3

Construction Noise

SR77

54.5dB(A)

66.9dB(A)

62.2dB(A)

Water Quality

DO

I5

6.7mg/L

9.3mg/L

7.9mg/L

Baseline Data

6.6mg/L

8.8mg/L

8.0mg/L

30% disturbance due to human activity

4.6mg/L

6.2mg/L

5.6mg/L

Turbidity

I5

9.1NTU

86.7NTU

28.5NTU

Baseline Data

12.4NTU

91.5NTU

26.1NTU

30% disturbance due to human activity

16.1NTU

118.9NTU

34.0NTU

SS

I5

3.7mg/L

72.5mg/L

13.9mg/L

Baseline Data

6.5mg/L

46.5mg/L

16.4mg/L

30% disturbance due to human activity

8.5mg/L

60.5mg/L

21.3mg/L

 

3.1.2          The maximum recorded suspended solid in the reporting quarter is 72.5mg/L which is higher than the 30% disturbance of the baseline maximum value (60.5mg/L).  However, respective investigation has been conducted and concluded the exceedances would not be project related.

3.1.3          The other recorded water quality monitoring levels during the reporting quarter were not exceed the 30% disturbance over the baseline level for quarterly average.

3.2              Summary of Monitoring Exceedances

3.2.1          The number of exceedances event recorded in the reporting quarter is summarized in Table 3.2.

3.2.2          Investigations for the exceedances events in the reporting quarter have been completed.  The exceedances were considered not to be related to the construction works.  The respective investigation reports have been presented in the respective Monthly EM&A Reports.

Table 3.2     Summary of Exceedance Events in the Reporting Quarter

Parameter

 

Number of Exceedances Events

Number of Project Related Exceedance Events

Air Quality

1 hour Total Suspended Particulate

Action Level

0

0

Limit Level

0

0

24 hour Total Suspended Particulate

Action Level

3

0

Limit Level

0

0

Construction Noise

Leq 30min

Action Level

0

0

Limit Level

0

0

Water Quality

DO

Action Level

0

0

Limit Level

0

0

Turbidity

Action Level

1

0

Limit Level

0

0

SS

Action Level

0

0

Limit Level

5

0

 

3.2.3          Contractor has been reminded to strengthen the mitigation measures including:

¡P         Watering of exposed slope and earths to avoid fugitive dust emission;

¡P         Water spraying should be properly implemented whenever necessary for the unpaved roads, access roads and construction areas;

¡P         Silty effluent should be treated/desilted before discharged. Untreated effluent should be prevented from entering public drain channel;

¡P         Channels or earth bunds or sand bag barriers should be provided on site to prevent surface runoff and properly direct stormwater to silt removal facilities;

¡P         Ensuring regular maintenance and cleaning of waste storage area;

¡P         Improving site cleanliness especially avoid general refuse being left within the construction site;

¡P         All types of wastes, both on land and floating in the river stream, should be collected and sorted properly, and also be disposed timely and properly; and

¡P         Ensuring the provision of tree protection zone for all existing trees to be transplanted or retained.

4                 WASTE MANAGEMENT

4.1.1          The Contractor has registered as a chemical waste producer of the Project.  The C&D materials and waste sorting were carried out on-site.  Receptacles were provided for general refuse collection.

4.1.2          During the reporting quarter, a total of 8,323m3 of excavated material has been generated.  5,263m3 of inert C&D materials was disposed of at public fill to Tuen Mun Area 38, while 2,144m3 of inert C&D materials were reused on site.  440m3 of general refuse was disposed of at North East New Territories (NENT) Landfill.  No plastics and no paper/cardboard packaging, plastics and metals were collected by recycling contractor in the reporting quarter.  39m3 of chemical waste was collected by licensed contractor in the reporting quarter.  Details of the waste management data are presented in Appendix F.

5                 ENVIRONMENTAL NON-CONFORMANCE

5.1.1          No environmental non-compliance were recorded in the reporting quarter.  No environmental complaints were received in the reporting quarter.  Investigations have been conducted.  No environmental related prosecution or notification of summons was received in the reporting quarter.  The summary for the non-compliance, complaints and prosecutions is provided in Appendix G.

6                 CONCLUSION, COMMENTS AND RECOMMENDATIONS

6.1.1           The EM&A programme was carried out by the ET in accordance with the EM&A Manual requirements. It is concluded from the environmental monitoring and audit works that adequate environmental mitigation measures have been implemented by the civil works contractors where appropriate in the reporting quarter.

6.1.2          In the reporting quarter, a total of 9 exceedance events have been recorded.  No exceedances were concluded not to be project related.  No necessary remedial actions have been taken.

6.1.3          No environmental non-compliances were noted. No environmental complaint was received. No environmental related prosecution or notification of summons were received in the reporting quarter. 

6.1.4          The box culvert works has been partially completed by the end of March 2014 except the last construction activity, installation of a base slab at Box Culvert ID4.  Due to the loading requirement of a fresh water main under the box culvert, installation of the base slab at Box Culvert ID4 has to be scheduled to be carried out in November 2015 after the utilities diversions complete.  The construction works are temporary suspended until the utilities diversion works complete.

6.1.5          As such, water quality monitoring has been conducted for the first week of April 2014 only to cover the temporary suspension of the construction work.  The 4-week post construction water quality monitoring will be commenced after the installation of the base slab finishes, hence the completion of the box culvert works.