Contract No. HY/2012/06
Widening of Fanling Highway – Tai Hang to Wo Hop Shek Interchange
 Impact Monitoring and Audit Schedule for December 2019
Sunday Monday Tuesday Wednesday Thursday Friday Saturday
1-Dec 2-Dec 3-Dec 4-Dec 5-Dec 6-Dec 7-Dec
          1-hr TSP  
          24-hr TSP  
          Noise  
    Site Audit        
8-Dec 9-Dec 10-Dec 11-Dec 12-Dec 13-Dec 14-Dec
        1-hr TSP    
        24-hr TSP    
        Noise    
      Site Audit        
15-Dec 16-Dec 17-Dec 18-Dec 19-Dec 20-Dec 21-Dec
      1-hr TSP      
      24-hr TSP      
      Noise      
          Site Audit    
22-Dec 23-Dec 24-Dec 25-Dec 26-Dec 27-Dec 28-Dec
    1-hr TSP       1-hr TSP
    24-hr TSP       24-hr TSP
    Noise        
      Site Audit            
29-Dec 30-Dec 31-Dec        
             
             
             
      Site Audit        
The schedule is subject to change due to unforeseeable circumstances (e.g. adverse weather, etc) 
             
             
               
Contract No. HY/2012/06
Widening of Fanling Highway – Tai Hang to Wo Hop Shek Interchange
Tentative Impact Monitoring and Audit Schedule for January 2020
Sunday Monday Tuesday Wednesday Thursday Friday Saturday
      1-Jan 2-Jan 3-Jan 4-Jan
          1-hr TSP  
          24-hr TSP  
          Noise  
               
5-Jan 6-Jan 7-Jan 8-Jan 9-Jan 10-Jan 11-Jan
        1-hr TSP    
        24-hr TSP    
        Noise    
      Site Audit        
12-Jan 13-Jan 14-Jan 15-Jan 16-Jan 17-Jan 18-Jan
      1-hr TSP      
      24-hr TSP      
      Noise      
          Site Audit    
19-Jan 20-Jan 21-Jan 22-Jan 23-Jan 24-Jan 25-Jan
    1-hr TSP     1-hr TSP  
    24-hr TSP     24-hr TSP  
    Noise     Noise  
      Site Audit          
26-Jan 27-Jan 28-Jan 29-Jan 30-Jan 31-Jan  
        1-hr TSP    
        24-hr TSP    
        Noise    
            Site Audit      
The schedule is subject to change due to unforeseeable circumstances (e.g. adverse weather, etc)