Contract No. HY/2012/06
Widening of Fanling Highway – Tai Hang to Wo Hop Shek Interchange
Impact  Monitoring and Audit Schedule for July 2019
Sunday Monday Tuesday Wednesday Thursday Friday Saturday
  1-Jul 2-Jul 3-Jul 4-Jul 5-Jul 6-Jul
    1-hr TSP        
    24-hr TSP        
    Noise        
    Site Audit        
7-Jul 8-Jul 9-Jul 10-Jul 11-Jul 12-Jul 13-Jul
  1-hr TSP         1-hr TSP
  24-hr TSP         24-hr TSP
  Noise          
      Site Audit        
14-Jul 15-Jul 16-Jul 17-Jul 18-Jul 19-Jul 20-Jul
          1-hr TSP  
          24-hr TSP  
          Noise  
          Site Audit    
21-Jul 22-Jul 23-Jul 24-Jul 25-Jul 26-Jul 27-Jul
        1-hr TSP    
        24-hr TSP    
        Noise    
      Site Audit        
28-Jul 29-Jul 30-Jul 31-Jul      
      1-hr TSP      
      24-hr TSP      
      Noise      
      Site Audit        
Contract No. HY/2012/06
Widening of Fanling Highway – Tai Hang to Wo Hop Shek Interchange
Tentative Impact Monitoring and Audit Schedule for August 2019
Sunday Monday Tuesday Wednesday Thursday Friday Saturday
        1-Aug 2-Aug 3-Aug
             
             
             
             
4-Aug 5-Aug 6-Aug 7-Aug 8-Aug 9-Aug 10-Aug
    1-hr TSP        
    24-hr TSP        
    Noise        
      Site Audit        
11-Aug 12-Aug 13-Aug 14-Aug 15-Aug 16-Aug 17-Aug
  1-hr TSP         1-hr TSP
  24-hr TSP         24-hr TSP
  Noise          
      Site Audit        
18-Aug 19-Aug 20-Aug 21-Aug 22-Aug 23-Aug 24-Aug
          1-hr TSP  
          24-hr TSP  
          Noise  
          Site Audit    
25-Aug 26-Aug 27-Aug 28-Aug 29-Aug 30-Aug 31-Aug
        1-hr TSP    
        24-hr TSP    
        Noise    
      Site Audit        
1-Sep            
             
             
             
               
The schedule is subject to change due to unforeseeable circumstances (e.g. adverse weather, etc)