Contract No. HY/2012/06
Widening of Fanling Highway – Tai Hang to Wo Hop Shek Interchange
 Monitoring and Audit Schedule for May 2016
Sunday Monday Tuesday Wednesday Thursday Friday Saturday
1-May 2-May 3-May 4-May 5-May 6-May 7-May
      1-hr TSP      
      24-hr TSP      
      Noise      
                 
8-May 9-May 10-May 11-May 12-May 13-May 14-May
  1-hr TSP       1-hr TSP  
  24-hr TSP       24-hr TSP  
  Noise          
             
15-May 16-May 17-May 18-May 19-May 20-May 21-May
        1-hr TSP    
        24-hr TSP    
        Noise    
               
22-May 23-May 24-May 25-May 26-May 27-May 28-May
    1-hr TSP      
    24-hr TSP      
    Noise      
                     
29-May 30-May 31-May        
    1-hr TSP        
    24-hr TSP        
    Noise        
                       
Contract No. HY/2012/06
Widening of Fanling Highway – Tai Hang to Wo Hop Shek Interchange
Tentative Impact Monitoring and Audit Schedule for June 2016
Sunday Monday Tuesday Wednesday Thursday Friday Saturday
      1-Jun 2-Jun 3-Jun 4-Jun
             
             
             
               
5-Jun 6-Jun 7-Jun 8-Jun 9-Jun 10-Jun 11-Jun
  1-hr TSP         1-hr TSP
  24-hr TSP         24-hr TSP
  Noise          
               
12-Jun 13-Jun 14-Jun 15-Jun 16-Jun 17-Jun 18-Jun
          1-hr TSP  
          24-hr TSP  
          Noise  
             
19-Jun 20-Jun 21-Jun 22-Jun 23-Jun 24-Jun 25-Jun
      1-hr TSP    
      24-hr TSP    
      Noise    
                   
26-Jun 27-Jun 28-Jun 29-Jun 30-Jun    
      1-hr TSP      
      24-hr TSP      
      Noise      
                       
The schedule is subject to change due to unforeseeable circumstances (e.g. adverse weather, etc)