Contract No. HY/2012/06
Widening of Fanling Highway ¡V Tai Hang to Wo Hop Shek Interchange
Impact Monitoring and Audit Schedule for November 2015
Sunday Monday Tuesday Wednesday Thursday Friday Saturday
1-Nov 2-Nov 3-Nov 4-Nov 5-Nov 6-Nov 7-Nov
    1-hr TSP        
    24-hr TSP        
    Noise        
               
8-Nov 9-Nov 10-Nov 11-Nov 12-Nov 13-Nov 14-Nov
  1-hr TSP       1-hr TSP
  24-hr TSP       24-hr TSP
  Noise        
                   
15-Nov 16-Nov 17-Nov 18-Nov 19-Nov 20-Nov 21-Nov
      1-hr TSP  
      24-hr TSP  
      Noise  
               
22-Nov 23-Nov 24-Nov 25-Nov 26-Nov 27-Nov 28-Nov
      1-hr TSP    
      24-hr TSP  
      Noise  
                 
29-Nov 30-Nov          
           
           
           
                         
Contract No. HY/2012/06
Widening of Fanling Highway ¡V Tai Hang to Wo Hop Shek Interchange
Tentative Impact Monitoring and Audit Schedule for December 2015
Sunday Monday Tuesday Wednesday Thursday Friday Saturday
    1-Dec 2-Dec 3-Dec 4-Dec 5-Dec
      1-hr TSP      
      24-hr TSP      
      Noise      
               
6-Dec 7-Dec 8-Dec 9-Dec 10-Dec 11-Dec 12-Dec
    1-hr TSP      
    24-hr TSP      
    Noise      
                   
13-Dec 14-Dec 15-Dec 16-Dec 17-Dec 18-Dec 19-Dec
  1-hr TSP       1-hr TSP
  24-hr TSP       24-hr TSP
  Noise        
               
20-Dec 21-Dec 22-Dec 23-Dec 24-Dec 25-Dec 26-Dec
      1-hr TSP    
      24-hr TSP    
      Noise    
                     
27-Dec 28-Dec 29-Dec 30-Dec 31-Dec    
           
           
           
                         
The schedule is subject to change due to unforeseeable circumstances (e.g. adverse weather, etc)