Contract No. HY/2012/06
Widening of Fanling Highway ¡V Tai Hang to Wo Hop Shek Interchange
Impact Monitoring and Audit Schedule for September 2015
Sunday Monday Tuesday Wednesday Thursday Friday Saturday
    1-Sep 2-Sep 3-Sep 4-Sep 5-Sep
    1-hr TSP       1-hr TSP
    24-hr TSP       24-hr TSP
    Noise        
             
6-Sep 7-Sep 8-Sep 9-Sep 10-Sep 11-Sep 12-Sep
      1-hr TSP    
      24-hr TSP    
      Noise    
                     
13-Sep 14-Sep 15-Sep 16-Sep 17-Sep 18-Sep 19-Sep
  1-hr TSP      
  24-hr TSP      
  Noise      
               
20-Sep 21-Sep 22-Sep 23-Sep 24-Sep 25-Sep 26-Sep
  1-hr TSP         1-hr TSP
  24-hr TSP       24-hr TSP
  Noise        
               
27-Sep 28-Sep 29-Sep 30-Sep      
    1-hr TSP      
    24-hr TSP      
    Noise      
                     
Contract No. HY/2012/06
Widening of Fanling Highway ¡V Tai Hang to Wo Hop Shek Interchange
Tentative Impact Monitoring and Audit Schedule for October 2015
Sunday Monday Tuesday Wednesday Thursday Friday Saturday
        1-Oct 2-Oct 3-Oct
            1-hr TSP
            24-hr TSP
             
                 
4-Oct 5-Oct 6-Oct 7-Oct 8-Oct 9-Oct 10-Oct
      1-hr TSP    
      24-hr TSP    
      Noise    
                     
11-Oct 12-Oct 13-Oct 14-Oct 15-Oct 16-Oct 17-Oct
  1-hr TSP      
  24-hr TSP      
  Noise      
                 
18-Oct 19-Oct 20-Oct 21-Oct 22-Oct 23-Oct 24-Oct
  1-hr TSP       1-hr TSP
  24-hr TSP     24-hr TSP
  Noise      
                 
25-Oct 26-Oct 27-Oct 28-Oct 29-Oct 30-Oct 31-Oct
    1-hr TSP      
    24-hr TSP      
    Noise      
                         
The schedule is subject to change due to unforeseeable circumstances (e.g. adverse weather, etc)