Contract No. HY/2012/06
Widening of Fanling Highway ¡V Tai Hang to Wo Hop Shek Interchange
Impact Monitoring and Audit Schedule for August 2015
Sunday Monday Tuesday Wednesday Thursday Friday Saturday
            1-Aug
             
             
             
             
2-Aug 3-Aug 4-Aug 5-Aug 6-Aug 7-Aug 8-Aug
  1-hr TSP       1-hr TSP
  24-hr TSP       24-hr TSP
  Noise        
                     
9-Aug 10-Aug 11-Aug 12-Aug 13-Aug 14-Aug 15-Aug
      1-hr TSP  
      24-hr TSP  
      Noise  
               
16-Aug 17-Aug 18-Aug 19-Aug 20-Aug 21-Aug 22-Aug
    1-hr TSP       1-hr TSP
  24-hr TSP       24-hr TSP
    Noise      
               
23-Aug 24-Aug 25-Aug 26-Aug 27-Aug 28-Aug 29-Aug
        1-hr TSP  
        24-hr TSP  
        Noise  
                 
30-Aug 31-Aug          
             
             
             
                   
Contract No. HY/2012/06
Widening of Fanling Highway ¡V Tai Hang to Wo Hop Shek Interchange
Tentative Impact Monitoring and Audit Schedule for September 2015
Sunday Monday Tuesday Wednesday Thursday Friday Saturday
    1-Sep 2-Sep 3-Sep 4-Sep 5-Sep
    1-hr TSP       1-hr TSP
    24-hr TSP       24-hr TSP
    Noise        
                 
6-Sep 7-Sep 8-Sep 9-Sep 10-Sep 11-Sep 12-Sep
      1-hr TSP    
      24-hr TSP    
      Noise    
                     
13-Sep 14-Sep 15-Sep 16-Sep 17-Sep 18-Sep 19-Sep
  1-hr TSP      
  24-hr TSP      
  Noise      
                 
20-Sep 21-Sep 22-Sep 23-Sep 24-Sep 25-Sep 26-Sep
  1-hr TSP       1-hr TSP
  24-hr TSP     24-hr TSP
  Noise      
                 
27-Sep 28-Sep 29-Sep 30-Sep      
    1-hr TSP      
    24-hr TSP      
    Noise      
                         
The schedule is subject to change due to unforeseeable circumstances (e.g. adverse weather, etc)