Contract No. HY/2012/06 Widening of Fanling Highway ¡V Tai Hang to Wo Hop Shek Interchange |
|||||||||||||
Impact Monitoring and Audit Schedule for August 2015 | |||||||||||||
Sunday | Monday | Tuesday | Wednesday | Thursday | Friday | Saturday | |||||||
1-Aug | |||||||||||||
2-Aug | 3-Aug | 4-Aug | 5-Aug | 6-Aug | 7-Aug | 8-Aug | |||||||
1-hr TSP | 1-hr TSP | ||||||||||||
24-hr TSP | 24-hr TSP | ||||||||||||
Noise | |||||||||||||
9-Aug | 10-Aug | 11-Aug | 12-Aug | 13-Aug | 14-Aug | 15-Aug | |||||||
1-hr TSP | |||||||||||||
24-hr TSP | |||||||||||||
Noise | |||||||||||||
16-Aug | 17-Aug | 18-Aug | 19-Aug | 20-Aug | 21-Aug | 22-Aug | |||||||
1-hr TSP | 1-hr TSP | ||||||||||||
24-hr TSP | 24-hr TSP | ||||||||||||
Noise | |||||||||||||
23-Aug | 24-Aug | 25-Aug | 26-Aug | 27-Aug | 28-Aug | 29-Aug | |||||||
1-hr TSP | |||||||||||||
24-hr TSP | |||||||||||||
Noise | |||||||||||||
30-Aug | 31-Aug | ||||||||||||
Contract No. HY/2012/06 Widening of Fanling Highway ¡V Tai Hang to Wo Hop Shek Interchange |
|||||||||||||
Tentative Impact Monitoring and Audit Schedule for September 2015 | |||||||||||||
Sunday | Monday | Tuesday | Wednesday | Thursday | Friday | Saturday | |||||||
1-Sep | 2-Sep | 3-Sep | 4-Sep | 5-Sep | |||||||||
1-hr TSP | 1-hr TSP | ||||||||||||
24-hr TSP | 24-hr TSP | ||||||||||||
Noise | |||||||||||||
6-Sep | 7-Sep | 8-Sep | 9-Sep | 10-Sep | 11-Sep | 12-Sep | |||||||
1-hr TSP | |||||||||||||
24-hr TSP | |||||||||||||
Noise | |||||||||||||
13-Sep | 14-Sep | 15-Sep | 16-Sep | 17-Sep | 18-Sep | 19-Sep | |||||||
1-hr TSP | |||||||||||||
24-hr TSP | |||||||||||||
Noise | |||||||||||||
20-Sep | 21-Sep | 22-Sep | 23-Sep | 24-Sep | 25-Sep | 26-Sep | |||||||
1-hr TSP | 1-hr TSP | ||||||||||||
24-hr TSP | 24-hr TSP | ||||||||||||
Noise | |||||||||||||
27-Sep | 28-Sep | 29-Sep | 30-Sep | ||||||||||
1-hr TSP | |||||||||||||
24-hr TSP | |||||||||||||
Noise | |||||||||||||
The schedule is subject to change due to unforeseeable circumstances (e.g. adverse weather, etc) |