Site
Inspection Summary
Site
Inspection Summary
Contract No. |
HY/2012/06 |
Date: |
5 May 2015 |
Time: |
14:00 |
Inspection No.: |
77 |
|
Nil |
|
|
|
Follow-up
Observation(s) |
1. |
The
chemical containers have been removed off site. (Closed) |
2. |
More
frequent watering for haul road has been arranged. (Closed) |
|
New
Observation(s) |
|
Nil. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Nil |
Contract No. |
HY/2012/06 |
Date: |
14 May 2015 |
Time: |
14:00 |
Inspection No.: |
78 |
|
Nil |
|
|
|
Follow-up
Observation(s) |
|
Nil. |
|
|
|
New
Observation(s) |
1. |
Dry
site area was observed at Area 346. The Contractor should water the
construction site frequently for dust suppression. |
|
Reminder |
|
Stagnant water was
observed at a drip tray and on top of chemical containers. The Contractor was
reminded to clear the water and provide drip trays to the chemical containers
to prevent mosquito breeding and retain any oil leakage. |
|
|
|
|
|
|
|
|
|
|
|
Nil |
Contract No. |
HY/2012/06 |
Date: |
19 May 2015 |
Time: |
14:00 |
Inspection No.: |
79 |
|
Nil |
|
|
|
Follow-up
Observation(s) |
1. |
Water
has been sprayed regularly for dry open ground. (Closed) |
|
|
|
New
Observation(s) |
2. |
General
refuse and C&D waste was accumulating on the ground. The Contractor
should clear the waste regularly or provide proper receptacles available for
waste collection. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Nil |
Contract No. |
HY/2012/06 |
Date: |
26 May 2015 |
Time: |
14:00 |
Inspection No.: |
80 |
|
Nil |
|
|
|
Follow-up
Observation(s) |
1. |
Construction
waste at SA329 has been removed. (Closed) |
|
|
|
New
Observation(s) |
|
Nil. |
|
Reminder |
|
The
Contractor was reminded to set up the wastewater treatment system as soon as
possible. |
|
|
|
|
|
|
|
|
|
|
|
Nil |