Site Inspection Summary

 

Inspection Information

Contract No.

HY/2012/06

Date:

3 March 2015

Time:

14:00

Inspection No.:

68

 

Non-compliance

 

 

Nil

 

 

Observations

 

 

 

Follow-up Observation(s)

1.

The compactor has been removed off site for repairing and all contaminated soil has been cleared. (Closed)

 

 

 

New Observation(s)

2.

The Contractor should review their mechanism to collect muddy water to prevent muddy water from discharging to public areas by clearing the mud accumulating in the U-channel or carrying out equivalent measures.

 

 

 

 

 

 

 

 

 

 

 

 

Remarks

 

 

Nil

 

 


 

Inspection Information

Contract No.

HY/2012/06

Date:

10 March 2015

Time:

14:00

Inspection No.:

69

 

Non-compliance

 

 

Nil

 

 

Observations

 

 

 

Follow-up Observation(s)

1.

The U-channel has been cleared, slurry on the concrete surface has been removed and a water pump at the end of the U-channel has been deployed to prevent leakage of muddy water. (Closed)

 

 

 

New Observation(s)

 

Nil.

 

 

 

 

 

 

 

 

 

 

 

Remarks

 

 

Nil

 

 


 

Inspection Information

Contract No.

HY/2012/06

Date:

19 March 2015

Time:

14:00

Inspection No.:

70

 

Non-compliance

 

 

Nil

 

 

Observations

 

 

 

Follow-up Observation(s)

 

Nil.

 

 

 

New Observation(s)

1.

An oil drum was placed on bare ground without drip tray. The Contractor should provide a drip tray to the oil drum to retain oil leakage, if any.

2.

A chemical container was observed without chemical label. The Contractor should stick appropriate labels on the chemical container.

 

Reminder(s)

 

 

1.

The Contracotr was reminded to use another means such as pH papers to monitor the pH of the water in the sedimentation tank regularly.

 

 

2.

The Contractor was reminded to post the latest version of Environmental Permit at all site entrances.

3.

The Contractor was reminded to ensure all water discharged from the construction site has passed the sedimentation tank.

 

Remarks

 

 

Nil

 

 


 

Inspection Information

Contract No.

HY/2012/06

Date:

24 March 2015

Time:

14:00

Inspection No.:

71

 

Non-compliance

 

 

Nil

 

 

Observations

 

 

 

Follow-up Observation(s)

1.

A drip tray has been provided to chemicals. (Closed)

2.

Corresponding chemical label has been affixed to the chemical container. (Closed)

 

New Observation(s)

3.

Stagnant water and general refuse was observed in a trench. The Contractor should clear the stagnant water to prevent mosquito breeding and clear the refuse to maintain site hygiene.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Remarks

 

 

Nil

 

 


 

Inspection Information

Contract No.

HY/2012/06

Date:

31 March 2015

Time:

14:00

Inspection No.:

72

 

Non-compliance

 

 

Nil

 

 

Observations

 

 

 

Follow-up Observation(s)

1.

Stagnant water and general refuse was cleared. (Closed)

 

 

 

New Observation(s)

 

Nil.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Remarks

 

 

Nil