Site
Inspection Summary
Contract No. |
HY/2012/06 |
Date: |
2 December 2014 |
Time: |
14:00 |
Inspection No.: |
55 |
|
Nil |
|
|
|
Follow-up
Observation(s) |
1. |
The area has been
flattened to prevent stagnant water and refuse from accumulating. (Closed) |
|
|
|
New
Observation(s) |
|
Nil. |
|
Reminder |
|
The Contractor was
reminded to cover the slope entirely with tarpaulin to prevent soil from depositing
in drainage systems. |
|
|
|
|
|
|
|
|
|
Nil |
Contract No. |
HY/2012/06 |
Date: |
11 December 2014 |
Time: |
14:00 |
Inspection No.: |
56 |
|
Nil |
|
|
|
Follow-up
Observation(s) |
|
Nil. |
|
|
|
New
Observation(s) |
1. |
Oil stains were
observed on the cycling path of Wo Hop Shek Bridge.
The Contractor should clear the oil stains, and inspect and maintain the
machine whenever necessary. |
|
|
|
|
|
|
|
|
|
|
|
|
|
Nil |
Contract No. |
HY/2012/06 |
Date: |
16 December 2014 |
Time: |
14:00 |
Inspection No.: |
57 |
|
Nil |
|
|
|
Follow-up
Observation(s) |
1. |
Oil stains were
cleared. (Closed) |
|
|
|
New
Observation(s) |
2. |
Stagnant water was
observed in a skip. The Contractor should clear the stagnant water to prevent
mosquito breeding. |
3. |
General refuse was
observed accumulating. The Contractor should clear general refuse regularly
and provide receptacles for general refuse collection to maintain site
hygiene. |
|
|
|
|
|
|
|
|
|
|
|
Nil |
Contract No. |
HY/2012/06 |
Date: |
23 December 2014 |
Time: |
14:00 |
Inspection No.: |
58 |
|
Nil |
|
|
|
Follow-up
Observation(s) |
1. |
The unused waste
skip has been removed. (Closed) |
2. |
General refuse has
been cleared. (Closed) |
|
New
Observation(s) |
|
Nil. |
|
Reminder |
|
The Contractor was
reminded to cover the stockpiles entirely with tarpaulin for dust
suppression. |
|
|
|
|
|
|
|
|
|
Nil |
Contract No. |
HY/2012/06 |
Date: |
30 December 2014 |
Time: |
14:00 |
Inspection No.: |
59 |
|
Nil |
|
|
|
Follow-up
Observation(s) |
|
Nil. |
|
|
|
New
Observation(s) |
1. |
General refuse was
accumulating at ID1. The Contractor should clear the refuse regularly to
maintain site hygiene and tidiness. |
|
Reminder |
|
The Contractor was
reminded to cover the stockpiles entirely with tarpaulin for dust
suppression. |
|
|
|
|
|
|
|
|
|
Nil |