Site Inspection Summary

 

Inspection Information

Contract No.

HY/2012/06

Date:

2 September 2014

Time:

14:00

Inspection No.:

42

 

Non-compliance

 

 

Nil

 

 

Observations

 

 

 

Follow-up Observations

1.

The breaker has been fully wrapped with absorptive materials (Closed).

 

 

 

 

New Observations

2.

Oil leakage was observed under an excavator. The Contractor should clear the oil stain and prevent oil leakage to air, soil and water bodies.

 

 

 

 

 

 

 

 

 

 

 

 

 

Remarks

 

 

Nil

 

 


 Inspection Information

Contract No.

HY/2012/06

Date:

10 September 2014

Time:

14:00

Inspection No.:

43

 

Non-compliance

 

 

Nil

 

 

Observations

 

 

 

Follow-up Observations

1.

Ground contaminated with leaked oil was cleaned. The excavator was removed off site for repairing. (Closed)

 

 

 

 

 

New Observations

 

Nil.

 

 

 

 

 

 

 

 

 

 

 

 

 

Remarks

 

 

Nil

 

 


 

Inspection Information

Contract No.

HY/2012/06

Date:

18 September 2014

Time:

14:00

Inspection No.:

44

 

Non-compliance

 

 

Nil

 

 

Observations

 

 

 

Follow-up Observations

 

Nil.

 

 

 

 

New Observations

1.

Mud trails were observed near the site entrance. The Contractor should maintain effective wheel washing facilities and clear the mud trails left on public road.

 

Reminders

 

 

 

The Contractor was reminded to divert muddy water to desilting facilities prior to discharge.

 

 

 

 

 

 

 

Remarks

 

 

Nil

 

 


 

Inspection Information

Contract No.

HY/2012/06

Date:

23 September 2014

Time:

14:00

Inspection No.:

45

 

Non-compliance

 

 

Nil

 

 

Observations

 

 

 

Follow-up Observation(s)

1.

A water bowser was arranged to wash the section of the road with mud trails near the site entrance. (Closed)

 

 

 

 

New Observation(s)

2.

Stagnant water was observed. The Contractor should clear the stagnant water to prevent mosquito breeding.

 

 

 

 

 

 

 

 

 

 

 

 

 

Remarks

 

 

Nil

 

 


 

Inspection Information

Contract No.

HY/2012/06

Date:

30 September 2014

Time:

14:00

Inspection No.:

46

 

Non-compliance

 

 

Nil

 

 

Observations

 

 

 

Follow-up Observation(s)

1.

Stagnant water was cleared. (Closed)

 

 

 

 

New Observation(s)

2.

Chemicals were observed on bare ground without drip trays. The Contractor should provide drip trays to chemicals to prevent any oil leakage.

 

 

 

 

 

 

 

 

 

 

 

 

 

Remarks

 

 

Nil