Site Inspection Summary

 

Inspection Information

Contract No.

HY/2012/06

Date:

5 August 2014

Time:

14:00

Inspection No.:

38

 

Non-compliance

 

 

Nil

 

 

Observations

 

 

 

Follow-up Observations

 

Nil.

 

 

 

 

New Observations

 

Nil.

 

 

 

 

 

 

 

 

 

 

 

 

 

Remarks

 

 

Nil

 

 


Inspection Information

Contract No.

HY/2012/06

Date:

14 August 2014

Time:

14:00

Inspection No.:

39

 

Non-compliance

 

 

Nil

 

 

Observations

 

 

 

Follow-up Observations

 

Nil.

 

 

 

 

New Observations

 

Nil.

 

Reminders

 

The Contractor was reminded to use absorptive materials to soak leaked oil, if any, when maintaining the power pack.

 

 

 

 

 

 

 

 

 

Remarks

 

 

Nil

 

 


 

Inspection Information

Contract No.

HY/2012/06

Date:

19 August 2014

Time:

14:00

Inspection No.:

40

 

Non-compliance

 

 

Nil

 

 

Observations

 

 

 

Follow-up Observations

 

Nil.

 

 

 

 

New Observations

 

Nil.

 

 

 

 

 

 

 

 

 

 

 

 

 

Remarks

 

 

Nil

 

 


 

 

Inspection Information

Contract No.

HY/2012/06

Date:

26 August 2014

Time:

14:00

Inspection No.:

41

 

Non-compliance

 

 

Nil

 

 

Observations

 

 

 

Follow-up Observations

 

Nil.

 

 

 

 

New Observations

1.

The Contractor should further wrap the upper part of the breaker with absorptive materials to minimize noise generation.

 

 

 

 

 

 

 

 

 

 

 

 

 

Remarks

 

 

Nil