Contract No. HY/2012/06
Widening of Fanling Highway – Tai Hang to Wo Hop Shek Interchange
Impact Monitoring and Audit Schedule for August 2014
Sunday Monday Tuesday Wednesday Thursday Friday Saturday
          1-Aug 2-Aug
           
          1-hr TSP
          24-hr TSP
             
3-Aug 4-Aug 5-Aug 6-Aug 7-Aug 8-Aug 9-Aug
        1-hr TSP    
        24-hr TSP  
        Noise  
                   
10-Aug 11-Aug 12-Aug 13-Aug 14-Aug 15-Aug 16-Aug
      1-hr TSP    
      24-hr TSP    
      Noise    
               
17-Aug 18-Aug 19-Aug 20-Aug 21-Aug 22-Aug 23-Aug
    1-hr TSP        
    24-hr TSP      
    Noise      
                 
24-Aug 25-Aug 26-Aug 27-Aug 28-Aug 29-Aug 30-Aug
  1-hr TSP        
  24-hr TSP       1-hr TSP
  Noise       24-hr TSP
               
31-Aug 1-Sep          
             
         
             
               
31-Aug            
           
           
           
               
Contract No. HY/2012/06
Widening of Fanling Highway – Tai Hang to Wo Hop Shek Interchange
Tentative Impact Monitoring and Audit Schedule for September 2014
Sunday Monday Tuesday Wednesday Thursday Friday Saturday
  1-Sep 2-Sep 3-Sep 4-Sep 5-Sep 6-Sep
        1-hr TSP  
        24-hr TSP  
        Noise  
             
7-Sep 8-Sep 9-Sep 10-Sep 11-Sep 12-Sep 13-Sep
        1-hr TSP    
        24-hr TSP  
        Noise  
                   
14-Sep 15-Sep 16-Sep 17-Sep 18-Sep 19-Sep 20-Sep
  1-hr TSP        
  24-hr TSP       1-hr TSP
  Noise       24-hr TSP
               
21-Sep 22-Sep 23-Sep 24-Sep 25-Sep 26-Sep 27-Sep
          1-hr TSP  
        24-hr TSP  
        Noise  
                 
28-Sep 29-Sep 30-Sep        
    1-hr TSP        
    24-hr TSP        
    Noise        
               
1-Jan 2-Jan          
             
         
             
               
31-Aug            
           
           
           
               
The schedule is subject to change due to unforeseeable circumstances (e.g. adverse weather, etc)