Site
Inspection Summary
Contract No. |
HY/2012/06 |
Date: |
3 June 2014 |
Time: |
14:00 |
Inspection No.: |
28 |
|
Nil |
|
|
|
Follow-up
Observations |
1. |
Deposition in the
U-channel was cleared. Public road outside the construction site was washed.
The Contractor has intercepted the site boundary with sand bags to prevent
leakage to the U-channel (Closed). |
|
|
|
New
Observations |
|
Nil. |
|
Reminders |
|
Stockpiles were
observed without entire covering. The Contractor was reminded to cover the
stockpiles entirely after work to prevent sand from depositing in the
drainage system nearby. |
|
|
|
|
|
|
|
|
|
Nil |
Contract No. |
HY/2012/06 |
Date: |
12 June 2014 |
Time: |
14:00 |
Inspection No.: |
29 |
|
Nil |
|
|
|
Follow-up
Observations |
|
Nil. |
|
|
|
New
Observations |
1. |
Non-paper wastes
were observed in the recycle bin for paper. The Contractor should educate
workers to recycle wastes properly and clear the refuse in the recycle bins
regularly. |
2. |
Chemicals were observed on bare ground without
drip trays. The Contractor should provide drip trays to chemicals. Moreover,
chemicals should be provided with labels. |
|
|
|
|
|
|
|
|
|
|
|
Nil |
Contract No. |
HY/2012/06 |
Date: |
17 June 2014 |
Time: |
14:00 |
Inspection No.: |
30 |
|
Nil |
|
|
|
Follow-up
Observations |
1. |
The
refuse in the recycle bins were cleared (Closed). |
2. |
Chemicals
were provided with a drip tray (Closed). |
|
New
Observations |
|
Nil. |
|
|
|
|
|
|
|
|
|
|
|
|
|
Nil |
Contract No. |
HY/2012/06 |
Date: |
24 June 2014 |
Time: |
14:00 |
Inspection No.: |
31 |
|
Nil |
|
|
|
Follow-up
Observations |
|
Nil. |
|
|
|
New
Observations |
|
Nil. |
|
|
|
|
|
|
|
|
|
|
|
|
|
Nil |