Site
Inspection Summary
Contract No. |
HY/2012/06 |
Date: |
4 March 2014 |
Time: |
14:00 |
Inspection No.: |
15 |
|
Nil |
|
|
|
Follow-up
Observation |
1. |
Due
to completion of works, all unused chemicals have been removed off site by
the subcontractor. |
|
|
|
New
Observation |
|
Nil. |
|
|
|
|
|
|
|
|
|
|
|
Nil |
Contract No. |
HY/2012/06 |
Date: |
13 March 2014 |
Time: |
14:00 |
Inspection No.: |
16 |
|
Nil |
|
|
|
Follow-up
Observation |
|
Nil |
|
|
|
New
Observation |
1. |
The Contractor was
reminded to properly store and label chemicals, and provide drip tray to hold
the chemical containers. |
2. |
The Contractor was reminded to label the chemical
container. |
|
|
|
|
|
|
|
|
|
Nil |
Contract No. |
HY/2012/06 |
Date: |
18 March 2014 |
Time: |
14:00 |
Inspection No.: |
17 |
|
Nil |
|
|
|
Follow-up
Observation |
1. |
The chemical
containers are stored in a metallic container and labeled (Closed). |
2. |
The chemical
container is labeled (Closed). |
|
New
Observation |
|
Nil. |
|
|
|
|
|
|
|
|
|
|
|
Nil |
Contract No. |
HY/2012/06 |
Date: |
25 March 2014 |
Time: |
14:00 |
Inspection No.: |
18 |
|
Nil |
|
|
|
Follow-up
Observation |
|
Nil. |
|
|
|
New
Observation |
|
Nil. |
|
|
|
|
|
|
|
|
|
|
|
Nil |