Contents
Page
2.3 Construction Programme and
Activities
3 STATUS
OF ENVIRONMENTAL LICENSES, NOTIFICATION AND PERMITS
4.4 Monitoring
Parameters, Frequency and Duration
4.6 Monitoring Schedule for the
Reporting month
5.4 Monitoring Parameters, Frequency and
Duration
5.6 Monitoring
Schedule for the Reporting Month
8 ENVIRONMENTAL SITE INSPECTION AND
AUDIT
9 IMPLEMENTATION STATUS OF
ENVIRONMENTAL MITIGATION MEASURES
10 SUMMARY OF EP SUBMISSION IN THE REPORTING MONTH
11 ENVIRONMENTAL NON-CONFORMANCE
11.1 Summary of Monitoring Exceedances
11.2 Summary of Environmental
Non-Compliance
11.3 Summary of Environmental Complaints
11.4 Summary of Environmental Summon and
Successful Prosecutions
12.1 Construction Programme for the Next
Month
12.2 Key Issues for the Coming Month
12.3 Monitoring Schedule for the Next
Month
13 CONCLUSIONS AND RECOMMENDATIONS
List of Tables
Table 2.1 Contact
Information of Key Personnel
Table
3.1 Status
of Environmental Licenses, Notifications and Permits
Table
4.1 Air
Quality Monitoring Equipment
Table
4.2 Location
of Air Quality Monitoring
Table
4.3 Air
Quality Monitoring Parameters, Frequency and Duration
Table
4.4 Summary
of 1-hr TSP Monitoring Results
Table
4.5 Summary
of 24-hr TSP Monitoring Results
Table
5.1 Noise
Monitoring Equipment
Table
5.2 Location
of Noise Monitoring
Table
5.3 Noise
Monitoring Parameters, Frequency and Duration
Table
5.4 Summary
of Noise Monitoring Results
Table 8.1 Observations and
Recommendations of Site Audit
Table
10.1 Status
of Required Submission under Environmental Permit
List
of Figures
Figure 2 Air
and Noise Monitoring Locations
List
of Appendices
Appendix A Construction Programme
Appendix B Project Organization Structure
Appendix C Calibration Certificates of Monitoring
Equipment
Appendix D EM&A Monitoring Schedules
Appendix E Meteorological Data Extracted from Hong
Kong Observatory
Appendix F Air Quality Monitoring Results and their
Graphical Presentation
Appendix G Summary of Event and Action Plan
Appendix H Noise Monitoring Results and their
Graphical Presentation
Appendix I Not Used
Appendix J Not
Used
Appendix L Implementation Schedule of
Environmental Mitigation Measures (EMIS)
Appendix M Not
Used
Appendix N Statistics on Complaints, Notifications
of Summons and Successful Prosecutions
The Entrusted
Portion of Widening of Tolo Highway / Fanling Highway between Island House
Interchange and Fanling Stage 2 (hereafter called ¡§the Project¡¨) covers part of
the construction of the widening
of Tolo Highway / Fanling Highway between Island House Interchange and Fanling
which aimed to widen Tolo Highway and Fanling Highway to dual 4-lane
carriageway in order to alleviate the current traffic congestion problems and
to cope with the increasing transport demands to and from the urban areas and
also cross boundary traffic. The
Project covers construction activities at Yuen Leng along the existing Fanling
Highway.
The
impact EM&A for the Project includes air quality, noise and water quality
monitoring. The EM&A programme
commenced on 5 November 2013.
This
report documents the findings of EM&A works conducted in February
2020. As informed by the
Contractor, the remaining activities in the reporting month were:
No exceedance of Action and Limit Level was
recorded for 24-hour TSP monitoring at the monitoring location AM1(SR77) in the
reporting month.
No exceedance of Action and Limit Level was
recorded for 1-hour TSP monitoring at the monitoring location AM1(SR77) in the
reporting month.
No
noise complaint was received in the reporting month, so no Action Level
exceedance was recorded. Also, no Limit
Level exceedance of noise monitoring was recorded in the reporting month.
The box culvert
works have been completed in the end of March 2017. The 4-week post
construction water quality monitoring has been completed in the end of April
2017 in the same manner as the impact monitoring.
No complaint,
notification of summons and successful prosecution was received in the
reporting month.
The remaining
construction works in the coming reporting month are anticipated to include:
Potential environmental impacts arising from the above construction
activities are anticipated to be mainly associated with construction dust,
noise, water quality and waste management.
1.1.1
Chun Wo
Construction & Engineering Co Ltd (Chun Wo) was commissioned by the Civil
Engineering and Development Department (CEDD) as the Civil Contractor for the Entrusted
Portion of Widening of Tolo Highway / Fanling Highway between Island House
Interchange and Fanling Stage 2. Meinhardt
Infrastructure & Environment Ltd (MIEL) has been appointed by Chun Wo as
the Environmental Team (ET) to fulfill the corresponding EM&A requirements
pursuant to Environmental Permit No. EP-324/2008/E
in accordance with the Updated EM&A Manual (dated October 2013) for
Widening of Tolo Highway/Fanling Highway between Island House Interchange and
Fanling Stage 2. The EM&A
programme commenced on 5 November 2013.
1.2.1
This is the monthly
EM&A Report which summaries the impact monitoring results and audit
findings for the Project during the reporting month of February 2020.
1.3.1
This
monthly EM&A Report comprises the following sections:
Section 1: Introduction
Section 2: Project Information
Section 3: Status
of Environmental Licenses, Notifications and Permits
Section 4: Air
Quality Monitoring
Section 5: Noise
Monitoring
Section 6: Water
Monitoring
Section 7: Waste
Management
Section 8:
Environmental Site Inspection and Audit
Section 9: Implementation
Status of Environmental Mitigation Measures
Section 10: Summary
of EP Submission in the Reporting Month
Section 11: Environmental
Non-Conformance
Section 12: Future
Key Issues
Section 13:
Conclusions and Recommendations
2.1.1
Tolo Highway and
Fanling Highway are expressways in the North East New Territories connecting
Sha Tin, Tai Po and Fanling. These
highways form a vital part of the strategic Route 1, which links Hong Kong
Island to Shenzhen. At present,
this section of Route 1 is a dual 3-lane carriageway. However, at several major interchanges
along this section of Route 1, the highway is only dual-2 lane. Severe congestion is a frequent
occurrence during peak periods, particularly in the Kowloon bound direction.
2.1.2
The objective of
the Widening of Tolo Highway / Fanling Highway between Island House Interchange
and Fanling is to widen Tolo Highway and Fanling Highway to dual 4-lane
carriageway in order to alleviate the current traffic congestion problems and
to cope with the increasing transport demands to and from the urban areas and
also cross boundary traffic.
2.1.3
The construction
works for the Widening of Tolo Highway / Fanling Highway between Island House
Interchange and Fanling are to be delivered in 2 stages:
Stage
1 ¡V Construction works between Island House Interchange and Tai Hang; and
Stage 2 ¡V Construction works between Tai
Hang and Wo Hop Shek Interchange.
2.1.4
The construction
works of Stage 1 under the EP commenced in November 2009 and was planned to be
completed in December 2013 tentatively.
The works of Stage 2 was planned to commence in November 2013 and
complete by end of 2016. Hyder-Arup-Black
and Veatch Joint Venture (HABVJV) was appointed by the Highways Department
(HyD) as the consultants for the design and construction assignment for the
Project. Mott MacDonald Hong Kong
Ltd is the Independent Environmental Checker (IEC) of both Stage 1 and Stage 2
works.
2.1.5
A portion of Stage
2 works of Widening of Tolo Highway / Fanling Highway between Island House
Interchange and Fanling (hereafter called ¡§the Project¡¨) is entrusted to the
contractor of Contract No. CV/2012/09 Liantang / Heung Yuen Wai Boundary
Control Point Site Formation and Infrastructure Works Contract 3, i.e. Chun Wo. AECOM Asia Co Ltd was appointed by the
CEDD as the consultant for the design and construction assignment for the
Liantang development.
2.1.6
The Project is a
Designated Project under the Environmental Impact Assessment Ordinance (EIAO) (Cap.
499). An Environmental Impact
Assessment (EIA) Report together with an Environmental Monitoring and Audit
(EM&A) Manual were approved on 14 July 2000 (Register Number: EIA-043/2000). The Project is governed by an
Environmental Permit (EP) (EP-324/2008) which was granted on 23 December 2008. A variation of EP (VEP) was applied and the
VEP (EP-324/2008/A) was subsequently granted on 31 January 2012. An additional VEP has been applied on 24
February 2014 and the VEP (EP-324/2008/B) was subsequently granted on 17 March
2014. Furthermore, an additional VEP has been applied on 9
March 2015 and the VEP (EP-324/2008/C) was subsequently granted on 27 March 2015.
The
previous VEP (EP-324/2008/D) was granted on 27
August 2015. The current VEP (EP-324/2008/E) was granted on 26 January 2017.
2.2.1
The major
construction activities under the Entrusted Portion of Widening of Tolo Highway
/ Fanling Highway between Island House Interchange and Fanling Stage 2 include:
At-Grade
Road Works ¡V Temporary and permanent road formation, pipe laying, road drainage,
footpath and noise barrier construction;
Demolition
of existing Kiu Tau Footbridge and Footbridge Reprovision; and
Box
Culvert Extension ¡V Flow diversion of existing stream, excavation, sub-base and
blinding, base, wall and top slab construction.
2.2.2
Figure
1
shows the works areas for the Entrusted Portion of Widening of Tolo Highway /
Fanling Highway between Island House Interchange and Fanling Stage 2.
2.3.1
The remaining
construction activities undertaken in the reporting month are summarized below:
¡P
Road pavement works; and
¡P
Remaining works of Kiu
Tau Footbridge.
2.3.2
The
construction programme is presented in Appendix A.
2.4.1
The
project organization structure is shown in Appendix B. The key personnel contact names and
numbers for the Project are summarised in Table 2.1.
Table 2.11 Contact
Information of Key Personnel
Party |
Role |
Position |
Name |
Telephone |
Fax |
AECOM |
Engineer¡¦s
Representative |
Senior Resident
Engineer |
Mr. Alan Lee |
2171 3303 |
2171
3498 |
Mott MacDonald |
Independent Environmental Checker (IEC) |
IEC |
Mr. Steven Tang |
2828 5920 |
2827 1823 |
Chun Wo |
Contractor |
Site Agent |
Mr. Chan |
2638 6144 |
2638 7077 |
Environmental
Officer |
Mr. Yip Yun
Lam |
3166 5111 |
|||
Environmental
Supervisor |
Mr. Franki Leung |
2638 7005 |
|||
Meinhardt |
Environmental
Team (ET) |
ET
Leader |
Mr.
Fredrick Leong/ Mr. W. K. Chiu |
2859 1739/ 2859 5881 |
2540 1580 |
3.1.1
The
relevant environmental licenses, permits and/or notifications on environmental
protection for this Project and valid in the reporting month are summarized in Table 3.1Table 3.1Table 3.1.
Table 3.11 Status of Environmental Licenses,
Notifications and Permits
Permit / License No. / Notification / Reference No. |
Valid Period |
Status |
Remarks |
|
From |
To |
|||
Environmental Permit |
||||
EP-324/2008/E |
26 Jan 2017 |
-- |
Granted on 26 Jan 2017 |
|
Construction Noise
Permit |
||||
Wastewater Discharge License |
||||
WT00032188-2018 |
20 Sep 2018 |
31 Aug 2023 |
Valid |
-- |
Chemical
Waste Producer Registration
|
||||
5113-634-C3817-01 |
7 Oct 2013 |
-- |
Valid |
-- |
Billing Account for Construction Waste Disposal |
||||
7017914 |
2 Aug 2013 |
-- |
Account Active |
-- |
Notification
Under Air Pollution Control (Construction Dust) Regulation |
||||
-- |
9 Aug 2019 |
-- |
Notified |
- |
4.1.1
In
accordance with the Updated EM&A Manual, 1-hr and 24-hr total suspended
particulate (TSP) levels at the designated air quality monitoring station are
required. Impact 24-hour TSP monitoring
should be carried out for at least once every 6 days. For the 1-hr TSP impact monitoring, the
sampling frequency of at least three times in every 6 days should be undertaken
when the highest dust impact occurs.
4.2.1
The
1hr- TSP and 24-hr TSP air quality monitoring were performed using a High
Volume Sampler (HVS), of which its location and operation satisfy, as far as
practicable, all the requirements as specified in the Updated EM&A Manual. The brand and model of the equipment are
given in Table
4.1.
Table 4.11 Air
Quality Monitoring Equipment
Equipment |
Brand
and Model |
Quantity |
Serial Number |
High Volume Sampler |
Tisch Total Suspended Particulate Mass Flow Controlled High
Volume Air Sampler (Model No. TE-5170 MFC) |
1 |
2359 |
Handheld TSP meter |
TSI
AM520 |
1 |
5201735006 |
4.2.2
The
HVS and its accessories were maintained in good working condition, such as
replacing motor brushes routinely and checking electrical wiring to ensure a
continuous power supply.
4.2.3
Calibration of the HVS (five point calibration) using
Calibration Kit was carried out every two months. The HVS calibration orifice will be
calibrated annually.
4.2.4
The
electricity supply of HVS at
AM1(SR77) was suspended from 16 May 2019 and was no longer available. In order
to have a more secure electricity supply, an alternative Handheld TSP meter was
proposed to use for the temporary monitoring of 24-hr & 1hr air quality from 22
May 2019. In this regard, IEC and ER have no adverse comment on it. And
Calibration certificates of the Handheld TSP meter are provided in Appendix
C.
4.3.1
Air
quality monitoring was conducted at the location specified in the Updated
EM&A Manual. Table
4.2 describes the
details of the air quality monitoring station with its location as shown in Figure
2.
Table
4.22 Location of Air Quality Monitoring
Air
Monitoring Station ID |
Monitoring
Location |
Description |
AM1(SR77)
* |
Yuen
Leng 2 * |
Residential,
Ground floor |
Remark:
* Location
and Station / ASR ID as identified in Updated EM&A Manual / EIA Report for
Widening of Tolo Highway/Fanling Highway between Island House Interchange and
Fanling
4.4.1
Table 4.3 summarizes the
monitoring parameters, frequency and duration of impact TSP monitoring.
Table
4.33 Air Quality Monitoring Parameters,
Frequency and Duration
Parameter |
Frequency
and Duration |
1-hour
TSP |
At
least three times in every 6 days should be undertaken when the highest dust
impact occur |
24-hour
TSP |
Once
every 6 days |
4.5.1
With
the consideration of criteria stated in the Updated EM&A Manual, the HVS
was installed in the vicinity of the air sensitive receivers.
4.5.2
The
relevant data including temperature, pressure, weather conditions, elapsed-time
meter reading for the start and stop of the sampler, identification and weight
of the filter paper, and any special phenomena observed were recorded. The weather information was referenced
from Hong Kong Observatory (http://www.weather.gov.hk/wxinfo/pastwx/extractc.htm).
4.5.3
A
HOKLAS accredited laboratory with constant temperature and humidity control,
and equipped with necessary measuring and conditioning instruments, to handle
the 24-hr TSP samples, was employed for sample analysis.
4.5.4
Filter
papers of size 8"x10" were labelled before sampling. They were inspected to be clean with no
pin holes and conditioned in a humidity controlled chamber for over 24-hr and were
pre-weighed before use for the sampling.
4.5.5
The
24-hr TSP levels were measured by following the standard high volume sampling
method for TSP as set out in the Title 40 of the United States Code of Federal
Regulations, Chapter 1 (Part 50), Appendix B. TSP was sampled by drawing air through a
conditioned, pre-weighted filter paper inside the HVS at a controlled air flow
rate. After 24-hr sampling, the
filter papers loaded with dust were kept in a clean and tightly sealed plastic
bag, and then returned to the laboratory for reconditioning in the humidity
controlled chamber followed by accurate weighing by an electronic balance with
a readout down to 0.1 mg.
4.5.6
All
the collected samples were kept in a good condition for 6 months before
disposal.
4.5.7
For
1-hr TSP monitoring, monitoring methodology is the same as 24-hr TSP monitoring
which has been presented in Section 4.5.1 to Section
4.5.6,
but with sampling period changed to 1 hour.
4.6.1
As informed by the contractor, all major construction
activities of the Entrusted Portion Project of Section 1A and 1B were substantially
completed on 28 September 2018 and 3 October 2018 respectively. In such regard,
the EM&A Programme of the captioned project, including monthly EM&A
reporting and the corresponding environmental monitoring and audit works, is no
longer required and we proposed to cease it by the end of December 2018 and we have
submitted the termination proposal to EPD on
24 December 2018. And EPD are replied the EM&A monitoring shall only be
terminated when insignificant environmental impacts of the remaining
outstanding construction works are expected and agreement of EPD. After that we
have submitted the termination proposal to EPD on 4 April 2019 again. EPD replied we
need to provide the Final EM&A Report to facilitate their consideration for
the termination on 14 May 2019. Therefore, the EM&A monitoring and audit
works will be ceased upon EPD¡¦s approval for the termination proposal is
approved. The tentative schedule
for environmental monitoring for the reporting month is provided in Appendix
D.
4.6.2
Meteorological
data extracted from Hong Kong Observatory for the reporting month is
provided in Appendix E.
4.7.1
The monitoring results for 1-hr and 24-hr TSP are summarised
in Table 4.4 and Table 4.5 respectively. Detailed air quality monitoring results
and the graphical presentation of air quality monitoring data for the current
and past three reporting months are presented in Appendix F.
Table 4.44 Summary of 1-hr TSP Monitoring
Results
ASR ID |
Average (mg/m3) |
Range (mg/m3) |
Action Level (mg/m3) |
Limit Level (mg/m3) |
AM1(SR77) * |
157.0 |
103.4
¡V 198.2 |
292.7 |
500 |
Remark:
* Station /
ASR ID as identified in Updated EM&A Manual / EIA Report for Widening of
Tolo Highway/Fanling Highway between Island House Interchange and Fanling
Table 4.55 Summary of 24-hr TSP Monitoring
Results
ASR ID |
Average (mg/m3) |
Range (mg/m3) |
Action Level (mg/m3) |
Limit Level (mg/m3) |
AM1(SR77) * |
91.6 |
61.4
¡V 121.2 |
170.3 |
260 |
Remark:
* Station
/ ASR ID as identified in Updated EM&A Manual / EIA Report for Widening of
Tolo Highway/Fanling Highway between Island House Interchange and Fanling
4.7.2
No exceedance of Action and Limit Level was recorded for
24-hour TSP monitoring at the monitoring location AM1(SR77) in the reporting
month.
4.7.3
No exceedance of Action and Limit Level was recorded for
1-hour TSP monitoring at the monitoring location AM1(SR77) in the reporting
month.
4.7.4
The Event and Action Plan for the occurrence of non-compliance
of the air quality criteria is annexed in Appendix G.
1.1.1
5.1.1
In
accordance with the Updated EM&A Manual, the impact noise monitoring
frequency shall depend on the scale of the construction activities. An initial guide on the regular
monitoring frequency should be at least once per week when noise generating
activities are underway.
5.2.1
Noise
monitoring was performed using a sound level meter at the monitoring station. The sound level meter deployed complies with
the International Electrotechnical Commission Publications 651:1979 (Type 1)
and 804:1985 (Type 1) specifications.
An acoustic calibrator was deployed to check the sound level
meter at a known sound pressure level.
The brand and model of the equipment is given in Table 5.1.
Table
5.11 Noise Monitoring Equipment
Equipment |
Brand and Model |
Quantity |
Serial Number |
Sound Level Calibrator |
Rion (Model No. NC-74) |
1 |
34678506 |
Sound Level Meter |
Rion (Model No. NL-52) |
1 |
00175560 |
5.2.2
The
sound level calibrator and sound level meter were verified by a certified
laboratory every year. Calibration
certificates of the sound level meter and acoustic calibrator are provided in Appendix
C.
5.3.1
Impact
noise monitoring was conducted at the location specified in the Updated
EM&A Manual. Table 5.2 describes the
details of the noise monitoring station with its location as shown in Figure
2.
Table 5.2 Location of Noise Monitoring
NSR ID |
Monitoring Location |
Description |
M1(SR77) * |
Yuen Leng 2 * |
Residential, Ground floor |
Remark:
* Location and
Station / NSR ID as identified in Updated EM&A Manual / EIA Report for
Widening of Tolo Highway/Fanling Highway between Island House Interchange and
Fanling
5.4.1
Table 5.3 summarizes the
monitoring parameters, frequency and duration of impact noise monitoring.
Table 5.33 Noise Monitoring Parameters,
Frequency and Duration
Parameter
and Duration |
Frequency |
30-mins
measurement at between 0700 and 1900 on normal weekdays. Leq, L10 and L90 would be recorded. |
At
least once per week |
5.5.1
The
monitoring procedures are summarised as follows:
¡P
The
sound level meter was set on a tripod at a height of 1.2 m above the ground for free-field
measurements at monitoring station SR77;
¡P
The
battery condition was checked to ensure good functioning of the meter;
¡P
Parameters
such as frequency weighting, the time weighting and the measurement time were
set as follows:
¡P
Frequency
weighting: A
¡P
Time
weighting: Fast
¡P
Parameters:
Leq, L10 and L90
¡P
Time
measurement: Leq(30-minutes) during non-restricted hours i.e. 07:00 ¡V 19:00 hrs
on normal weekdays
¡P
Prior
to and after each noise measurement, the meter was calibrated using the
acoustic calibrator for 94dB(A) at 1000 Hz. If the difference in the calibration
level before and after measurement was more than 1dB(A), the measurement would
be considered invalid and repeat of noise measurement would be required after
re-calibration or repair of the equipment.
¡P
At
the end of the monitoring period, the Leq, L10 and L90 were recorded. In addition, site conditions and noise
sources were recorded on a standard record sheet.
¡P
A
façade correction of +3dB (A) shall be made to the noise parameter obtained by
free field measurement.
5.6.1
The
schedule for environmental monitoring for the reporting month is provided in Appendix
D. Meteorological
data extracted from Hong Kong Observatory for the reporting month
is provided in Appendix E.
5.7.1
The
monitoring results for noise are summarized in Table 5.4
and the monitoring results
and
the graphical presentation of noise level for the current and past three reporting
months are
presented in Appendix H.
Table 5.44 Summary of Noise Monitoring Results
Noise Monitoring Station ID |
Average, dB(A), Leq (30min) (2) |
Range, dB(A), |
Action Level |
Limit Level, dB(A) |
M1(SR77) (1) |
64.4 |
63.5 ¡V 65.5 |
When
one documented valid complaint is received |
75 |
Remark:
(1) Station / NSR ID as identified in
Updated EM&A Manual / EIA Report for Widening of Tolo Highway/Fanling
Highway between Island House Interchange and Fanling
(2) +3dB(A) façade correction included
5.7.2
Major
noise sources during the noise monitoring included construction activities of
the Project and that along Tai Wo Service Road East, and nearby traffic noise.
5.7.3
No
noise complaint was received in the reporting month, so no Action Level
exceedance was recorded. Also, no Limit
Level exceedance of noise monitoring was recorded in the reporting month.
5.7.4
The
Event and Action Plan for the occurrence of non-compliance of the noise
criteria is annexed in Appendix
G.
6.1.1
The box culvert
works had been completed in March 2017. The
4-week post-construction water quality monitoring at I5 was completed in 28 April
2017.
7.1.1
The
Contractor has registered as a chemical waste producer of the Project. The C&D materials and waste sorting were
carried out on-site. Receptacles
were provided for general refuse collection.
7.1.2
As advised by the Contractor, a total of 69m3 of excavated material has been generated. 69m3 of inert C&D materials was disposed of at public
fill to TM Area 38. 0m3 of inert C&D
materials were reused on site. 20m3 of general refuse was disposed of
at North East New Territories (NENT) Landfill. No plastic was collected by
recycling contractor in the reporting month. No paper/cardboard packaging was
collected by recycling contractor in the reporting month. No metal was collected
by recycling contractor in the reporting month. No chemical waste was collected by
licensed contractor in the reporting period. Details of the waste management
data are presented in Appendix K.
Table 8.1 Observations and Recommendations of Site Audit
Parameters |
Date |
Observations and Recommendations |
Follow-up |
Air Quality |
N/A |
N/A |
N/A |
Noise |
N/A |
N/A |
N/A |
Water Quality |
N/A |
N/A |
N/A |
Waste/ Chemical Management |
N/A |
N/A |
N/A |
Landscape & Visual |
N/A |
N/A |
N/A |
Permits / Licenses |
N/A |
N/A |
N/A |
|
9.1.1
The Contractor has implemented the relevant environmental
mitigation measures as specified in the EIA Reports, EPs and updated EM&A
Manual. The implementation status
of environmental mitigation measures
during the reporting period is summarized in Appendix L.
10.1.1
The
status of the required submission under the EP during the reporting period is
summarized in Table 10.1.
Table 10.11 Status of Required Submission under
Environmental Permit
EP
Condition |
Submission |
Submission
Date |
Condition 3.3 |
Monthly EM&A Report for January 2020 |
14 Feb 2020
|
11.1.1 No exceedance of Action and Limit Level were recorded for 24-hour TSP monitoring at the monitoring location AM1(SR77) in the reporting month.
11.1.2
No
exceedance of Action and Limit Level was recorded for 1-hour TSP monitoring at
the monitoring location AM1(SR77) in the reporting month.
11.1.3
No
noise complaint was received in the reporting month, so no Action Level
exceedance was recorded. Also, no
Limit Level exceedance of noise monitoring was recorded in the reporting
month.
11.1.4 The 4-week post-construction
water quality monitoring at I5 was completed in April 2017.
11.2.1
No environmental non-compliance was recorded in the reporting
month. The cumulative statistics
are provided in Appendix N.
11.3.1
No environmental complaints were
received in the reporting month. The cumulative statistics are provided in Appendix N.
11.4.1
No
environmental related prosecution or notification of summons was received in
the reporting month. The cumulative
statistics are provided in Appendix N.
12.1.1
The remaining construction works in the coming reporting month
are anticipated to include:
¡P
Road pavement works; and
¡P
Remaining
works of Kiu Tau Footbridge.
12.2.1
Key issues to be considered in the coming month are
anticipated to include:
¡P
Properly maintain all drainage
facilities and wheel washing facilities on site;
¡P
Good housekeeping should be
maintained and general refuse should be removed regularly; and
¡P
Watering shall be enhanced over the construction site.
12.3.1
The tentative schedule for environmental monitoring for the coming
month is provided in Appendix D.
13.1.1
The
construction phase EM&A programme of the Project commenced on 5 November
2013.
13.1.2
The
1-hr TSP, 24-hr TSP, noise and water quality monitoring were carried out in the
reporting period.
13.1.3
No
exceedance of Action and Limit Level was recorded for 24-hour TSP monitoring at
the monitoring location AM1(SR77) in the reporting month.
13.1.4
No
exceedance of Action and Limit Level was recorded for 1-hour TSP monitoring at
the monitoring location AM1(SR77) in the reporting month.
13.1.5
No
noise complaint was received in the reporting month, so no Action Level
exceedance was recorded. Also, no
Limit Level exceedance of noise monitoring was recorded in the reporting month.
13.1.6
The
4-week post-construction water quality monitoring at I5 was completed in April
2017.
13.1.7
Four (4) environmental site inspections
were carried out in the reporting month.
Recommendations on remedial actions were given to the Contractors for
the deficiencies identified during the site audit.
According to the environmental site inspections performed in the reporting
month, no following
recommendation was provided.