Contents
Page
2.3 Construction Programme and
Activities
3 STATUS OF ENVIRONMENTAL LICENSES,
NOTIFICATION AND PERMITS
4.4 Monitoring
Parameters, Frequency and Duration
4.6 Monitoring Schedule for the
Reporting month
5.4 Monitoring Parameters, Frequency and
Duration
5.6 Monitoring
Schedule for the Reporting Month
8 ENVIRONMENTAL SITE INSPECTION AND
AUDIT
9 IMPLEMENTATION STATUS OF
ENVIRONMENTAL MITIGATION MEASURES
10 SUMMARY OF EP SUBMISSION IN THE
REPORTING MONTH
11 ENVIRONMENTAL NON-CONFORMANCE
11.1 Summary of Monitoring Exceedances
11.2 Summary of Environmental
Non-Compliance
11.3 Summary of Environmental Complaints
11.4 Summary of Environmental Summon and
Successful Prosecutions
12.1 Construction Programme for the Next
Month
12.2 Key Issues for the Coming Month
12.3 Monitoring Schedule for the Next Month
13 CONCLUSIONS AND RECOMMENDATIONS
List of Tables
Table 2.1 Contact Information of Key Personnel
Table 3.1 Status of Environmental Licenses, Notifications and
Permits
Table 4.1 Air Quality Monitoring Equipment
Table 4.2 Location of Air Quality Monitoring
Table 4.3 Air Quality Monitoring Parameters, Frequency and
Duration
Table 4.4 Summary of 1-hr TSP Monitoring Results
Table 4.5 Summary of 24-hr TSP Monitoring Results
Table 5.1 Noise Monitoring Equipment
Table 5.2 Location of Noise Monitoring
Table 5.3 Noise Monitoring Parameters, Frequency and Duration
Table 5.4 Summary of Noise Monitoring Results
Table 8.1 Observations and Recommendations of Site Audit
Table 10.1 Status of Required Submission under Environmental
Permit
List of Figures
Figure 2 Air and Noise Monitoring Locations
List of Appendices
Appendix A Construction
Programme
Appendix B Project Organization Structure
Appendix C Calibration Certificates of Monitoring
Equipment
Appendix D EM&A Monitoring Schedules
Appendix E Meteorological Data Extracted from Hong
Kong Observatory
Appendix F Air Quality Monitoring Results and their
Graphical Presentation
Appendix G Summary of Event and Action Plan
Appendix H Noise Monitoring Results and their
Graphical Presentation
Appendix I Laboratory Results for Water Quality
Appendix J Water Quality Monitoring Results
and their Graphical Presentation
Appendix L Implementation Schedule of
Environmental Mitigation Measures (EMIS)
Appendix M Investigation
Report for ExceedancesNot Used
Appendix N Statistics on Complaints, Notifications
of Summons and Successful Prosecutions
The Entrusted Portion of Widening of Tolo
Highway / Fanling Highway between Island House
Interchange and Fanling Stage 2 (hereafter called
¡§the Project¡¨) covers part of the construction of the widening of Tolo Highway / Fanling Highway
between Island House Interchange and Fanling which
aimed to widen Tolo Highway and Fanling
Highway to dual 4-lane carriageway in order to alleviate the current traffic
congestion problems and to cope with the increasing transport demands to and
from the urban areas and also cross boundary traffic. The Project covers construction activities
at Yuen Leng along the existing Fanling
Highway.
The impact EM&A for the Project includes air quality, noise and
water quality monitoring. The
EM&A programme commenced on 5 November 2013.
This report documents the findings of EM&A works conducted in December January 20167. As informed by the Contractor, the major
activities in the reporting month were:
Abutment Construction;
Construction of Boundary Wall for DSD Pumping
Station;
Cable Detection and Trial Trenches;
Demolition of Existing Vehicular Bridge;
Extended Podium Construction;
Footbridge Construction;
Storm Drains Laying;
Noise Barrier Construction;
Pier / Pier Table Construction;
Portal Beam Construction;
Construction of Remaining Base Slab of Box Culvert
ID4;
Retaining Wall Construction;
Road Works;
Roundabout Modification Works;
Sewer Works;
Utilities Duct Laying;
Viaduct Segment Erection; and
Water Main Laying.
Cable Detection and Trial Trenches;
Demolition of Existing Vehicular Bridge;
Footbridge Construction;
Storm Drains Laying;
Noise Barrier Construction;
Pier / Pier Table Construction;
Pile Cap Works;
Portal Beam Construction;
Retaining Wall Construction;
Road Works;
Sewer Works;
Utilities Duct Laying;
Viaduct Segment Erection;
Water Main Laying;
Extended Podium Construction; and
Construction of Remaining Base Slab of Box Culvert
ID4.
No exceedance of
Action and Limit Level was recorded for 24-hour TSP monitoring at the
monitoring location AM1(SR77) in the reporting month.
No exceedance of
Action and Limit Level was recorded for 1-hour TSP monitoring at the monitoring
location AM1(SR77) in the reporting month.
No noise complaint was received in the
reporting month, so no Action Level exceedance was
recorded. Also, no Limit Level exceedance of noise monitoring was recorded in the
reporting month.
No exceedance of Action Level
or Limit Level was recorded at the monitoring location I5 in the
reporting month. One (1) exceedance of Action Level of Dissolved
Oxygen was recorded at the monitoring location I5 on 12 December 2016 in the
reporting month. Investigation for the exceedance was conducted which concluded
that the exceedance was not related to the project works. The investigation
report is presented in Appendix M.
No complaint, notification
of summons and successful prosecution was received in the reporting month.
The major
construction works in the coming reporting month are anticipated to include:
Boundary Wall for Pumping Station;
Abutment Construction;
Cable Detection and Trial Trenches;
Construction of Remaining Slab of Box Culvert ID04;
Demolition of Existing Kiu
Tau Vehicular Bridge;
Extended Podium Construction;
Gabion Wall Construction;
Installation of Noise Barrier Steel Column and
Panel;
Re-provisioning of the Existing Kiu
Tau Footbridge;
Storm Drains Laying;
Installation Works of Mini-pile;
Noise Barrier Construction;
Pier / Pier Table Construction;
Pipe Jacking works for DN2200 Water Mains;
Portal Construction;
Profile Barrier Construction on Viaduct;
Retaining Wall Construction;
Road Works;
Roundabout Modification Works;
Sewer Works;
Slope Reinstatement Works near bridge E;
Utilities Duct Laying;
Viaduct Segment Erection; and
Water Main Laying.Boundary Wall for Pumping Station;
Cable Detection and Trial Trenches;
Construction of Remaining Slab of Box Culvert ID05;
Demolition of Valve Control House;
Footbridge Construction;
Gabion Wall construction;
Re-provisioning of Kiu Tau Footbridge;
Storm Drains Laying;
Noise Barrier Construction;
Pier / Pier Table Construction;
Pile Cap Works;
Portal Beam Construction;
Retaining Wall Construction;
Road Works;
Sewer Works;
Slope Reinstatement Works near Bridge E;
Utilities Duct Laying;
Viaduct Segment Erection;
Water Main Laying; and
Demolition of Existing WSD Telemetry House.
Potential environmental impacts arising from
the above construction activities are anticipated to be mainly associated with
construction dust, noise, water quality and waste management.
1.1.1
Chun
Wo Construction &
Engineering Co Ltd (Chun Wo) was commissioned by the Civil
Engineering and Development Department (CEDD) as the Civil Contractor for the Entrusted
Portion of Widening of Tolo Highway / Fanling Highway between Island House Interchange and Fanling Stage 2.
Meinhardt Infrastructure & Environment Ltd
(MIEL) has been appointed by Chun Wo
as the Environmental Team (ET) to fulfill the
corresponding EM&A requirements pursuant to Environmental Permit No. EP-324/2008/D in accordance with the Updated EM&A
Manual (dated October 2013) for Widening of Tolo
Highway/Fanling Highway between Island House
Interchange and Fanling Stage 2. The EM&A programme commenced on 5
November 2013.
1.2.1
This
is the monthly EM&A Report which summaries the impact monitoring results
and audit findings for the Project during the reporting month of December January 20167.
1.3.1
This
monthly EM&A Report comprises the following sections:
Section 1: Introduction
Section 2: Project Information
Section 3: Status of Environmental Licenses, Notifications and Permits
Section 4: Air Quality Monitoring
Section 5: Noise Monitoring
Section 6: Water Monitoring
Section 7: Waste Management
Section 8: Environmental Site Inspection and Audit
Section 9: Implementation Status of Environmental Mitigation Measures
Section 10: Summary of EP Submission in the Reporting Month
Section 11: Environmental Non-Conformance
Section 12: Future Key Issues
Section 13: Conclusions and Recommendations
2.1.1
Tolo Highway and Fanling Highway are expressways
in the North East New Territories connecting Sha Tin,
Tai Po and Fanling. These highways form a vital part of the
strategic Route 1, which links Hong Kong Island to Shenzhen. At present, this section of Route 1 is a
dual 3-lane carriageway. However,
at several major interchanges along this section of Route 1, the highway is
only dual-2 lane. Severe congestion
is a frequent occurrence during peak periods, particularly in the Kowloon bound
direction.
2.1.2
The
objective of the Widening of Tolo Highway / Fanling Highway between Island House Interchange and Fanling is to widen Tolo Highway
and Fanling Highway to dual 4-lane carriageway in
order to alleviate the current traffic congestion problems and to cope with the
increasing transport demands to and from the urban areas and also cross
boundary traffic.
2.1.3
The
construction works for the Widening of Tolo Highway /
Fanling Highway between Island House Interchange and Fanling are to be delivered in 2 stages:
Stage 1 ¡V Construction works between Island House Interchange and Tai Hang; and
Stage 2 ¡V Construction works between Tai Hang and Wo Hop Shek Interchange.
2.1.4
The
construction works of Stage 1 under the EP commenced in November 2009 and was planned
to be completed in December 2013 tentatively. The works of Stage 2 was planned to
commence in November 2013 and complete by end of 2016. Hyder-Arup-Black
and Veatch Joint Venture (HABVJV) was appointed by the Highways Department (HyD) as the consultants for the design and construction
assignment for the Project. Mott
MacDonald Hong Kong Ltd is the Independent Environmental Checker (IEC) of both
Stage 1 and Stage 2 works.
2.1.5
A
portion of Stage 2 works of Widening of Tolo Highway
/ Fanling Highway between Island House Interchange
and Fanling (hereafter called ¡§the Project¡¨) is
entrusted to the contractor of Contract No. CV/2012/09 Liantang
/ Heung Yuen Wai Boundary Control Point Site
Formation and Infrastructure Works Contract 3, i.e. Chun Wo. AECOM
Asia Co Ltd was appointed by the CEDD as the consultant for the design and
construction assignment for the Liantang development.
2.1.6
The
Project is a Designated Project under the Environmental Impact Assessment Ordinance
(EIAO) (Cap. 499). An Environmental
Impact Assessment (EIA) Report together with an Environmental Monitoring and
Audit (EM&A) Manual were approved on 14 July 2000 (Register Number:
EIA-043/2000). The Project is governed
by an Environmental Permit (EP) (EP-324/2008) which was granted on 23 December
2008. A variation of EP (VEP) was
applied and the VEP (EP-324/2008/A) was subsequently granted on 31 January
2012. An additional VEP has been applied
on 24 February 2014 and the VEP (EP-324/2008/B) was subsequently granted on 17
March 2014. Furthermore, an additional VEP has been applied on
9 March 2015 and the VEP (EP-324/2008/C) was subsequently granted on 27 March
2015. The current VEP (EP-324/2008/D) was granted on 27 August 2015.
2.2.1
The
major construction activities under the Entrusted Portion of Widening of Tolo Highway / Fanling Highway
between Island House Interchange and Fanling Stage 2
include:
At-Grade Road Works ¡V Temporary and permanent road formation, pipe laying, road drainage, footpath and noise barrier construction;
Demolition of existing Kiu Tau Footbridge and Footbridge Reprovision; and
Box Culvert Extension ¡V Flow diversion of existing stream, excavation, sub-base and blinding, base, wall and top slab construction.
2.2.2
Figure 1 shows the works areas for the
Entrusted Portion of Widening of Tolo Highway / Fanling Highway between Island House Interchange and Fanling Stage 2.
2.3.1
The
major construction activities undertaken in the reporting month are summarized
below:
Abutment Construction;
Construction of Boundary Wall for DSD Pumping
Station;
Cable Detection and Trial Trenches;
Demolition of Existing Vehicular Bridge;
Extended Podium Construction;
Footbridge Construction;
Storm Drains Laying;
Noise Barrier Construction;
Pier / Pier Table Construction;
Portal Beam Construction;
Construction of Remaining Base Slab of Box Culvert
ID4;
Retaining Wall Construction;
Road Works;
Roundabout Modification Works;
Sewer Works;
Utilities Duct Laying;
Viaduct Segment Erection; and
Water Main Laying.Cable
Detection and Trial Trenches;
Demolition of Existing Vehicular Bridge;
Footbridge Construction;
Storm Drains Laying;
Noise Barrier Construction;
Pier / Pier Table Construction;
Pile Cap Works;
Portal Beam Construction;
Retaining Wall Construction;
Road Works;
Sewer Works;
Utilities Duct Laying;
Viaduct Segment Erection;
Water Main Laying;
Extended Podium Construction; and
Construction of Remaining Base Slab of Box Culvert
ID4.
2.3.2
The
construction programme is presented in Appendix A.
2.4.1
The
project organization structure is shown in Appendix B. The key personnel contact names and
numbers for the Project are summarised in Table 2.1Table 2.1.
Table 2.1 Contact Information of Key Personnel
Party |
Role |
Position |
Name |
Telephone |
Fax |
AECOM |
Engineer¡¦s
Representative |
Senior
Resident Engineer |
Mr. Alan Lee |
2171 3303 |
2171 3498 |
Resident Engineer (Environmental) |
Mr. |
2171 3350 |
|||
Mott MacDonald |
Independent Environmental Checker (IEC) |
IEC |
Mr. Steven Tang |
2828 5920 |
2827 1823 |
Chun Wo |
Contractor |
Site Agent |
Mr. Daniel Ho |
2638 6144 |
2638 7077 |
Environmental Officer |
Mr. |
2638 6181 |
|||
Meinhardt |
Environmental Team (ET) |
ET Leader |
Mr. Fredrick Leong |
2859 1739 |
2540 1580 |
3.1.1
The
relevant environmental licenses, permits and/or notifications on environmental
protection for this Project and valid in the reporting month are summarized in Table 3.1Table 3.1.
Table 3.1 Status of Environmental Licenses, Notifications and Permits
Permit / License No. / Notification / Reference No. |
Valid Period |
Status |
Remarks |
|
From |
To |
|||
Environmental Permit |
||||
EP-324/2008/D |
27 Aug 2015 |
-- |
Granted on 27 Aug 2015 |
|
Construction Noise Permit |
||||
|
|
|
|
|
|
|
|
|
|
GW-RN0549-16 |
30 Jul 2016 |
9 Jan 2017 |
Valid |
For road resurfacing of Fanling Highway Southbound |
GW-RN0561-16 |
16 Aug 2016 |
11 Feb 2017 |
Valid |
For road diversion and maintenance of Fanling Highway Northbound |
GW-RN0581-16 |
25 Aug 2016 |
24 Feb 2017 |
Valid |
For segment Delivery to Kiu Tau |
GW-RN0580-16 |
25 Aug 2016 |
24 Feb 2017 |
Valid |
For general works at the northward of site office |
GW-RN0596-16 |
17 Aug 2016 |
15 Feb 2017 |
Valid |
For fuel delivery entering the construction site next to MTRC¡¦s East Rail Line at Tong Hang Tung |
GW-RN0619-16 |
22 Aug 2016 |
14 Feb 2017 |
Valid |
For tractor with trailer entering the Construction Site next to MTRC¡¦s East Rail Line at Tong Hang Tung |
GW-RN0646-16 |
10 Sep 2016 |
9 Mar 2017 |
Valid |
For segment erection of pier AA4, AB6, AD7 and AA18 |
GW-RN0649-16 |
3 Sep 2016 |
7 Jan 2017 |
Valid |
For traffic road works at a section of Fanling Highway both bounds |
GW-RN0653-16 |
11 Sep 2016 |
10 Mar 2017 |
Valid |
For segment erection AB7 to AB10 |
GW-RN0654-16 |
15 Sep 2016 |
14 Mar 2017 |
Valid |
For segment erection crossing over MTRC¡¦s Rail Track of Pier AB11 and AD12 (1900-2300) |
GW-RN0708-16 |
8 Oct 2016 |
26 Jan 2017 |
Valid |
For demolition of vehicular bridge at Fanling Highway both bounds |
GW-RN0711-16 |
1 Oct 2016 |
13 Jan 2017 |
Valid |
For installation of temporary support system of existing vehicular flyover linking at Fanling Highway both bounds |
GW-RN0720-16 |
4 Oct 2016 |
31 Mar 2017 |
Valid |
For segment erection of spans AA5, AA6, AA7, AB3 and AB4 across Fanling Highway |
GW-RN0729-16 |
5 Oct 2016 |
31 Mar 2017 |
Valid |
For segment erection of spans AA11, AA12, AC3 and AC4 across Fanling Highway |
GW-RN0795-16 |
5 Nov 2016 |
29 Apr 2017 |
Valid |
For falsework modification of pier AD12 |
GW-RN0816-16 |
13 Nov 2016 |
27 Mar 2017 |
Valid |
For lane shifting work at Fanling Highway Northbound |
GW-RN0833-16 |
13 Nov 2016 |
10 May 2017 |
Valid |
For segment erection crossing over MTRC¡¦s Rail Track of Pier AB11 and AD12 (0115-0500) |
GW-RN0843-16 |
18 Nov 2016 |
17 May 2017 |
Valid |
For segment erection of Pier AB11 |
GW-RN0836-16 |
15 Nov 2016 |
31 Mar 2017 |
Valid |
For segment erection at AC1 end span |
GW-RN0856-16 |
17 Nov 2016 |
7 Jan 2017 |
Valid |
For loading and unloading along Fanling Highway both bounds |
GW-RN0871-16 |
29 Nov 2016 |
20 May 2017 |
Valid |
For segment stitches concreting between AA11 and AA12 crossing over Fanling Highway |
GW-RN0872-16 |
29 Nov 2016 |
20 May 2017 |
Valid |
For segment stitches concreting from AB3 to AB5 crossing over Fanling Highway |
GW-RN0870-16 |
30 Nov 2016 |
13 May 2017 |
Valid |
Road marking works in Fanling Highway bothbounds |
GW-RN0901-16 |
11 Dec 2016 |
4 Jun 2017 |
Valid |
Demolition of Vehicular Bridge at Fanling Highway Southbound in Sunday and Public Holidays |
GW-RN0939-16 |
22 Dec 2016 |
21 Jun 2017 |
Valid |
For general works at southward of site office |
GW-RN0947-16 |
24 Dec 2016 |
15 Jun 2017 |
Cancelled on 25 Jan 2017. |
For road diversion and maintenance of Fanling Highway Southbound |
GW-RN0965-16 |
28 Dec 2016 |
13 Jan 2017 |
Valid |
Demolition of Vehicular Bridge at Fanling Highway South Bound at Night during Weekdays |
GW-RN0002-17 |
8 Jan 2017 |
4 Jun 2017 |
Valid |
For welding
work of steel truss on Fanling Highway |
GW-RN0004-17 |
13 Jan 2017 |
18 Feb 2017 |
Valid |
For
dismantling of catch fence within MTR Protection Zone at Tong Hang Tung Chuen |
GW-RN0021-17 |
19 Jan 2017 |
8 Jul 2017 |
Valid |
For traffic
road works at a section of Fanling Highway both
bounds |
GW-RN0029-17 |
19 Jan 2017 |
8 Jul 2017 |
Valid |
For loading
and unloading along Fanling Highway both bounds |
Wastewater
Discharge License |
||||
WT00016832-2013 |
28 Aug 2013 |
31 Aug 2018 |
Valid |
-- |
Chemical
Waste Producer Registration
|
||||
5113-634-C3817-01 |
7 Oct 2013 |
-- |
Valid |
-- |
Billing
Account for Construction Waste Disposal |
||||
7017914 |
2 Aug 2013 |
-- |
Account Active |
-- |
Notification
Under Air Pollution Control (Construction Dust) Regulation |
||||
-- |
31 Jul 2013 |
30 Jul 2019 |
Notified |
-- |
4.1.1
In
accordance with the Updated EM&A Manual, 1-hr and 24-hr total suspended
particulate (TSP) levels at the designated air quality monitoring station are
required. Impact 24-hour TSP monitoring
should be carried out for at least once every 6 days. For the 1-hr TSP impact monitoring, the
sampling frequency of at least three times in every 6 days should be undertaken
when the highest dust impact occurs.
4.2.1
The
1hr- TSP and 24-hr TSP air quality monitoring were performed using a High
Volume Sampler (HVS), of which its location and operation satisfy, as far as
practicable, all the requirements as specified in the Updated EM&A Manual. The brand and model of the equipment are
given in Table
4.1Table 4.1.
Table 4.1 Air Quality Monitoring Equipment
Equipment |
Brand
and Model |
Quantity |
Serial Number |
High
Volume Sampler |
Tisch
Total Suspended Particulate Mass Flow Controlled High Volume Air Sampler
(Model No. TE-5170 MFC) |
1 |
2359 |
4.2.2
The
HVS and its accessories were maintained in good working condition, such as
replacing motor brushes routinely and checking electrical wiring to ensure a
continuous power supply.
4.2.3
Calibration
of the HVS (five point calibration) using Calibration Kit was carried out every
two months. The HVS calibration
orifice will be calibrated annually.
Calibration certificate of the TE-5025A Calibration Kit and the HVS are
provided in Appendix C.
4.3.1
Air
quality monitoring was conducted at the location specified in the Updated
EM&A Manual. Table
4.2Table 4.2 describes the details of the air
quality monitoring station with its location as shown in Figure 2.
Table 4.2 Location of Air Quality Monitoring
Air
Monitoring Station ID |
Monitoring
Location |
Description |
AM1(SR77)
* |
Yuen Leng 2 * |
Residential,
Ground floor |
Remark:
* Location
and Station / ASR ID as identified in Updated EM&A Manual / EIA Report for
Widening of Tolo Highway/Fanling
Highway between Island House Interchange and Fanling
4.4.1
Table
4.3Table 4.3 summarizes the monitoring
parameters, frequency and duration of impact TSP monitoring.
Table 4.3 Air Quality Monitoring Parameters, Frequency and Duration
Parameter |
Frequency
and Duration |
1-hour
TSP |
At least
three times in every 6 days should be undertaken when the highest dust impact
occur |
24-hour
TSP |
Once
every 6 days |
4.5.1
With
the consideration of criteria stated in the Updated EM&A Manual, the HVS
was installed in the vicinity of the air sensitive receivers.
4.5.2
The
relevant data including temperature, pressure, weather conditions, elapsed-time
meter reading for the start and stop of the sampler, identification and weight
of the filter paper, and any special phenomena observed were recorded. The weather information was referenced
from Hong Kong Observatory (http://www.weather.gov.hk/wxinfo/pastwx/extractc.htm).
4.5.3
A
HOKLAS accredited laboratory with constant temperature and humidity control,
and equipped with necessary measuring and conditioning instruments, to handle
the 24-hr TSP samples, was employed for sample analysis.
4.5.4
Filter
papers of size 8"x10" were labelled before sampling. They were inspected to be clean with no
pin holes and conditioned in a humidity controlled chamber for over 24-hr and
were pre-weighed before use for the sampling.
4.5.5
The
24-hr TSP levels were measured by following the standard high volume sampling
method for TSP as set out in the Title 40 of the United States Code of Federal
Regulations, Chapter 1 (Part 50), Appendix B. TSP was sampled by drawing air through a
conditioned, pre-weighted filter paper inside the HVS at a controlled air flow
rate. After 24-hr sampling, the
filter papers loaded with dust were kept in a clean and tightly sealed plastic
bag, and then returned to the laboratory for reconditioning in the humidity
controlled chamber followed by accurate weighing by an electronic balance with
a readout down to 0.1 mg.
4.5.6
All
the collected samples were kept in a good condition for 6 months before
disposal.
4.5.7
For
1-hr TSP monitoring, monitoring methodology is the same as 24-hr TSP monitoring
which has been presented in Section 4.5.1 to Section 4.5.6, but with sampling period changed
to 1 hour.
4.6.1
The
schedule for environmental monitoring for the reporting month is provided in Appendix
D. Meteorological
data extracted from Hong Kong Observatory for the reporting month
is provided in Appendix E.
4.7.1
The
monitoring results for 1-hr and 24-hr TSP are summarised in Table
4.4Table 4.4 and Table
4.5Table 4.5 respectively. Detailed air quality monitoring results
and the graphical presentation of air quality monitoring data for the current
and past three reporting months are presented in Appendix F.
Table 4.4 Summary of 1-hr TSP Monitoring Results
ASR ID |
Average (mg/m3) |
Range (mg/m3) |
Action Level (mg/m3) |
Limit Level (mg/m3) |
AM1(SR77) * |
|
|
292.7 |
500 |
Remark:
* Station /
ASR ID as identified in Updated EM&A Manual / EIA Report for Widening of Tolo Highway/Fanling Highway
between Island House Interchange and Fanling
Table 4.5 Summary of 24-hr TSP Monitoring Results
ASR ID |
Average (mg/m3) |
Range (mg/m3) |
Action Level (mg/m3) |
Limit Level (mg/m3) |
AM1(SR77) * |
|
|
170.3 |
260 |
Remark:
* Station /
ASR ID as identified in Updated EM&A Manual / EIA Report for Widening of Tolo Highway/Fanling Highway
between Island House Interchange and Fanling
4.7.2
No
exceedance of Action and Limit Level was recorded for
24-hour TSP monitoring at the monitoring location AM1(SR77)
in the reporting month.
4.7.3
No
exceedance of Action and Limit Level was recorded for
1-hour TSP monitoring at the monitoring location AM1(SR77)
in the reporting month.
4.7.4
The
Event and Action Plan for the occurrence of non-compliance of the air quality
criteria is annexed in Appendix G.
5.1.1
In
accordance with the Updated EM&A Manual, the impact noise monitoring
frequency shall depend on the scale of the construction activities. An initial guide on the regular
monitoring frequency should be at least once per week when noise generating
activities are underway.
5.2.1
Noise
monitoring was performed using a sound level meter at the monitoring station. The sound level meter deployed complies with
the International Electrotechnical Commission
Publications 651:1979 (Type 1) and 804:1985 (Type 1) specifications. An acoustic calibrator was deployed to
check the sound level meter at a known sound pressure level. The brand and model of the equipment is
given in Table
5.1Table 5.1.
Table 5.1 Noise Monitoring Equipment
Equipment |
Brand and Model |
Quantity |
Serial Number |
Sound Level Calibrator |
Rion (Model No. NC-74) |
1 |
34857296 |
Sound Level Meter |
B&K (Model No. 2238) |
1 |
2694908 |
5.2.2
The
sound level calibrator and sound level meter were verified by a certified
laboratory every year. Calibration
certificates of the sound level meter and acoustic calibrator are provided in Appendix
C.
5.3.1
Impact
noise monitoring was conducted at the location specified in the Updated
EM&A Manual. Table
5.2Table 5.2 describes the details of the noise monitoring
station with its location as shown in Figure 2.
Table 5.2 Location of Noise Monitoring
NSR ID |
Monitoring Location |
Description |
M1(SR77) * |
Yuen Leng 2 * |
Residential, Ground floor |
Remark:
* Location and
Station / NSR ID as identified in Updated EM&A Manual / EIA Report for
Widening of Tolo Highway/Fanling
Highway between Island House Interchange and Fanling
5.4.1
Table
5.3Table 5.3 summarizes the monitoring
parameters, frequency and duration of impact noise monitoring.
Table 5.3 Noise Monitoring Parameters, Frequency and Duration
Parameter
and Duration |
Frequency |
30-mins
measurement at between 0700 and 1900 on normal weekdays. Leq, L10 and
L90 would be recorded. |
At least
once per week |
5.5.1
The monitoring procedures are summarised as follows:
The sound
level meter was set on a tripod at a height of 1.2 m above the ground for
free-field measurements at monitoring station SR77;
The
battery condition was checked to ensure good functioning of the meter;
Parameters
such as frequency weighting, the time weighting and the measurement time were
set as follows:
Frequency weighting:
A
Time weighting:
Fast
Parameters:
Leq, L10 and L90
Time measurement:
Leq(30-minutes) during non-restricted hours i.e. 07:00
¡V 19:00 hrs on normal weekdays
Prior to
and after each noise measurement, the meter was calibrated using the acoustic
calibrator for 94dB(A) at 1000 Hz. If
the difference in the calibration level before and after measurement was more
than 1dB(A), the measurement would be considered invalid and repeat of noise
measurement would be required after re-calibration or repair of the equipment.
At the end
of the monitoring period, the Leq, L10 and L90 were
recorded. In addition, site
conditions and noise sources were recorded on a standard record sheet.
A façade
correction of +3dB (A) shall be made to the noise parameter obtained by free
field measurement.
5.6.1
The
schedule for environmental monitoring for the reporting month is provided in Appendix
D. Meteorological
data extracted from Hong Kong Observatory for the reporting month
is provided in Appendix E.
5.7.1
The monitoring results for noise are summarized in Table
5.4Table 5.4 and the monitoring results and the graphical
presentation of noise level for the current and past three reporting months are presented in Appendix
H.
Table 5.4 Summary of Noise Monitoring Results
Noise Monitoring Station ID |
Average, dB(A), Leq
(30min) (2) |
Range, dB(A), |
Action Level |
Limit Level, dB(A) |
M1(SR77) (1) |
|
|
When one documented
valid complaint is received |
75 |
Remark:
(1) Station / NSR ID as identified in
Updated EM&A Manual / EIA Report for Widening of Tolo
Highway/Fanling Highway between Island House
Interchange and Fanling
(2) +3dB(A)
façade correction included
5.7.2
Major
noise sources during the noise monitoring included construction activities of
the Project and that along Tai Wo Service Road East, and
nearby traffic noise.
5.7.3
No
noise complaint was received in the reporting month, so no Action Level exceedance was recorded. Also, no Limit Level exceedance
of noise monitoring was recorded in the reporting month.
5.7.4
The Event and Action Plan for the occurrence of
non-compliance of the noise criteria is annexed in Appendix G.
6.1.1
The box culvert works have been partially completed
by the end of March 2014 except the last construction activity, installation of
a base slab at Box Culvert ID4. Due
to the loading requirement of a fresh water main under the box culvert,
installation of the base slab at Box Culvert ID4 has been commenced
in December 2016.
6.1.2
The 4-week post construction water quality
monitoring will be commenced after the installation of the base slab finishes,
hence the completion of the box culvert works.
6.1.3
Impact monitoring for water quality were carried
out twelve (12) times in the reporting month. The water quality
monitoring was taken on 2, 5, 7, 9, 12, 14, 16, 19, 21, 23, 283, 5, 7, 9, 11, 13, 16, 18, 20, 23, 25
and 3027
December 2016January 2017.
6.2.1 In accordance with the Updated EM&A Manual, during the course of the culvert extension works, monitoring shall be undertaken on three occasions per week. The interval between two sets of monitoring shall not be less than 36 hours except where there are exceedances of Action and/or Limit levels. The results are included in Appendix I and Appendix J.
6.3.1
The equipment used in the
water quality monitoring programme is summarised in Table
6.1Table 6.1.
Table 6.1 Water Quality Monitoring Equipment
Equipment |
Model and Make |
Turbidity meter |
HACH Model 2100Q is (Serial No.
13120C029845) |
Multifunctional Meter (Scope of Test: Conductivity, Dissolved Oxygen, pH, Salinity and Temperature) |
Professional
Plus (Serial
No. 10D101566) |
6.3.2 The monitoring instruments were checked, calibrated and certified by a laboratory accredited under HOKLAS before use and subsequently re-calibrated at 3-monthly intervals throughout all stages of the water quality monitoring. Copies of the calibration certificates for the water quality monitoring equipment are attached in Appendix C.
6.4.1
Measurements for each
monitoring station were conducted 3 days per week for the reporting month. Table
6.2Table 6.2 summarises the monitoring parameters, frequency and
duration of the baseline water quality monitoring.
Table 6.2 Water Quality Monitoring Parameters, Frequency and Duration
Monitoring Stations |
Parameter, unit |
Frequency |
Control Stations: C3a and C3b Impact Station: I5 |
- Depth, m - Temperature, ¢XC - Salinity, ppt - pH - DO,
mg/L - DO
Saturation, % - Turbidity, NTU - SS, mg/L |
3 days per week |
6.5.1
According to the Updated EM&A Manual, measurements were taken at all impact and control
stations as summarised in Table 6.3Table 6.3. The locations of the monitoring stations
are shown in Figure 3.
Table 6.3 Locations of Water Quality Monitoring
Station |
Description |
Easting |
Northing |
I5 |
Downstream of Ma (Yuen Leng) |
833931 |
837859 |
C3a |
Upstream of Ma ( |
833816 |
837644 |
C3b |
Upstream of Ma (Yuen Leng) |
833931 |
837736 |
6.6.1 The parameters of in-situ measurements included water depth, dissolved oxygen (DO), dissolved oxygen saturation (DOS), turbidity level, pH value and water temperature.
6.6.2 Since water depths for all monitoring stations were less than 1m throughout the whole baseline measurement period, only mid-depth level was monitored.
6.6.3 At each monitoring station, at least duplicate readings of dissolved oxygen content and turbidity were taken. The probes were retrieved out of the water after the first measurement and then re-deployed for the second measurement.
6.6.4 Water samples were collected by the water sampler and filled into polyethylene bottles for laboratory determination of suspended solids. Sampling bottles were pre-rinsed with the same water samples, and filled up to the rim, capped tightly and labeled immediately. The sample bottles were then packed into a cool-box kept at 4¢XC, and delivered to a HOKLAS accredited laboratory, Enviro Labs Ltd. (HOKLAS no.: 128) for analysis. The results for laboratory analysis of suspended solids are presented in Appendix I.
6.7.1 The schedule for environmental monitoring for the reporting month is provided in Appendix D. Meteorological data extracted from Hong Kong Observatory for the reporting month is provided in Appendix E.
6.8.1
The water quality criteria,
namely Action and Limit Levels, as specified in the Updated EM&A Manual are
shown in Table
6.4Table 6.4.
Table 6.4 Action and Limit Levels for Water Quality Monitoring
Parameters |
Action |
Limit |
DO in mg/L |
6.7 mg/L |
4 mg/L or 40% saturation at 15 degree Celsius |
SS in mg/L |
42.6 mg/L or 120% of upstream control station¡¦s SS of the
same day |
46.8 mg/L or 130% of upstream station¡¦s SS of the same day and specific sensitive receiver water quality requirements |
Turbidity (Tby) in NTU |
81.9NTU or 120% of upstream control station¡¦s Tby of the same day |
91.9NTU or 130% of upstream control station¡¦s Tby of the same day |
Notes:
For DO, non-compliance of the water quality limits occurs when monitoring result is lower than the limits.
For SS and Tby, non-compliance of the water quality limits occurs when monitoring result is higher than the limits.
6.8.2 The detailed water quality monitoring results and the graphical presentation of water quality monitoring data for the current and past three reporting months are presented in Appendix J.
6.8.3 The possible influences in monitoring results were suspected to be natural variation.
6.8.4
No exceedance of Action Level or
Limit Level was recorded in the reporting
month. One (1) exceedance of Action Level on Dissolved Oxygen was recorded at the monitoring location I5 on 12 December 2016. Investigation for the exceedance was conducted which concluded that the exceedance were
not related to the project works. The investigation reports are presented in Appendix
M.
6.8.5
The Event and Action Plan for
the occurrence of non-compliance of the water quality criteria is annexed in Appendix
G.
7.1.1
The
Contractor has registered as a chemical waste producer of the Project. The C&D materials and waste sorting were
carried out on-site. Receptacles
were provided for general refuse collection.
7.1.2
As
advised by the Contractor, a total of 1,150675m3 of excavated material
has been generated. 425796m3
of inert C&D materials was disposed of at public fill to Tuen Mun Area 38. 120150m3
inert C&D materials were reused on site. 120170m3 of general refuse was
disposed of at North East New Territories (NENT) Landfill. No1m3 of plastics
was collected by recycling contractor in the reporting month. No paper/cardboard packaging was
collected by recycling contractor in the reporting month. 1m3
ofNo metals
was collected by recycling contractor in the reporting month. No chemical waste was collected by
licensed contractor in the reporting period. Details of the waste management
data are presented in Appendix K.
Table 8.1 Observations and Recommendations of Site Audit
Parameters |
Date |
Observations and Recommendations |
Follow-up |
Water Quality |
N/A |
N/A |
N/A |
Air Quality |
|
|
|
09 Jan 2017 |
Contractor
is reminded to implement watering frequently during breaking activities
(SA17) |
Watering
during breaking activities has been adopted 9 January 2017 and there were no
breaking activities during the site inspection on 18 January 2017. |
|
Noise |
N/A |
N/A |
N/A |
Water Quality |
09 Jan 2017 |
Site surface runoff has been observed to be
flowing into the Nullah (SA12) |
Please refer to Observation identified during 23
January 2017 site inspection. |
23 Jan 2017 |
The contractor is reminded to provide sand/ silt
removing materials at the manhole before discharging (SA12) |
The follow up action will be reviewed in the next
monthly EM&A report. |
|
Waste
/ Chemical Managem-ent |
N/A |
N/A
|
N/A |
Landscape
& Visual |
N/A |
N/A |
N/A |
Permits /
Licenses |
N/A |
N/A |
N/A |
9.1.1
The
Contractor has implemented the relevant environmental mitigation measures as specified
in the EIA Reports, EPs and updated EM&A Manual. The implementation status of
environmental mitigation measures during the reporting period is summarized in Appendix
L.
10.1.1 The status of the required
submission under the EP during the reporting period is summarized in Table
10.1Table 10.1.
Table 10.1 Status of Required Submission under Environmental Permit
EP
Condition |
Submission |
Submission
Date |
Condition
3.3 |
Monthly
EM&A Report for |
1 |
1.1.1
The Quarterly EM&A Report (August 2016
to October 2016) was prepared and submitted on 9 December 2016 in accordance to
Section 8.3.4 of the EM&A Manual.
1.1.1
The Annual EM&A Review Report (November 2015 to
October 2016) was prepared and submitted on 9 December 2016 in accordance to
Section 8.3.4 of the EM&A Manual.
11.1.1 No exceedance of Action and Limit Level was recorded for 24-hour TSP monitoring at the monitoring location AM1(SR77) in the reporting month.
11.1.2 No exceedance
of Action and Limit Level was recorded for 1-hour TSP monitoring at the
monitoring location AM1(SR77) in the reporting month.
11.1.3 No noise complaint was received in
the reporting month, so no Action Level exceedance
was recorded. Also, no Limit Level exceedance of noise monitoring was recorded in the
reporting month.
11.1.4 No exceedance of ActionLimit Level was
recorded for water quality monitoring at the monitoring location I5 in the
reporting month. Also, no Limit Level exceedance
of water quality monitoring was recorded in the reporting month, One (1) exceedance of Action Level of Dissolved
Oxygen was recorded for water quality monitoring at the monitoring location I5
on 12 December 2016 in the reporting month.
11.2.1 No environmental non-compliance was
recorded in the reporting month.
The cumulative statistics are provided in Appendix N.
11.3.1 No
environmental complaints were received in the reporting month. The cumulative statistics are provided in Appendix
N.
11.4.1 No environmental related prosecution
or notification of summons was received in the reporting month. The cumulative statistics are provided
in Appendix N.
12.1.1 The major construction works in the coming
reporting month are anticipated to include:
Boundary Wall
for Pumping Station;
Abutment
Construction;
Cable
Detection and Trial Trenches;
Construction
of Remaining Slab of Box Culvert ID04;
Demolition of
Existing Kiu Tau Vehicular Bridge;
Extended
Podium Construction;
Gabion Wall
Construction;
Installation
of Noise Barrier Steel Column and Panel;
Re-provisioning
of the Existing Kiu Tau Footbridge;
Storm Drains
Laying;
Installation
Works of Mini-pile;
Noise Barrier
Construction;
Pier / Pier
Table Construction;
Pipe Jacking
works for DN2200 Water Mains;
Portal
Construction;
Profile
Barrier Construction on Viaduct;
Retaining
Wall Construction;
Road Works;
Roundabout
Modification Works;
Sewer Works;
Slope
Reinstatement Works near bridge E;
Utilities
Duct Laying;
Viaduct
Segment Erection; and
Water
Main Laying.
Boundary Wall
for Pumping Station;
Cable
Detection and Trial Trenches;
Construction
of Remaining Slab of Box Culvert ID05;
Demolition of
Valve Control House;
Footbridge
Construction;
Gabion Wall
construction;
Re-provisioning
of Kiu Tau Footbridge;
Storm Drains
Laying;
Noise Barrier
Construction;
Pier / Pier
Table Construction;
Pile Cap
Works;
Portal Beam
Construction;
Retaining
Wall Construction;
Road Works;
Sewer Works;
Slope
Reinstatement Works near Bridge E;
Utilities
Duct Laying;
Viaduct
Segment Erection;
Water Main
Laying; and
Demolition of
Existing WSD Telemetry House.
12.2.1 Key issues to be considered in the
coming month are anticipated to include:
Site discharges should be properly collected and treated prior to discharge;
Properly maintain all drainage facilities and wheel washing facilities on site;
Expose slopes and dusty stockpile should be covered up properly if no work will be conducted;
Operation of construction plant should be sequenced where practicable;
Good housekeeping should be maintained and general refuse should be removed regularly;
Chemical waste should be stored, handled and disposed of properly;
Properly
store and label oils and chemicals on site; and
A spill response procedure shall be in place and absorption material available for minor spillages.
12.3.1 The tentative schedule for
environmental monitoring for the coming month is provided in Appendix D.
13.1.1 The construction phase EM&A
programme of the Project commenced on 5 November 2013.
13.1.2 The 1-hr TSP, 24-hr TSP, noise and
water quality monitoring were carried out in the reporting period.
13.1.3 No exceedance
of Action and Limit Level was recorded for 24-hour TSP monitoring at the
monitoring location AM1(SR77) in the reporting month.
13.1.4 No exceedance
of Action and Limit Level was recorded for 1-hour TSP monitoring at the
monitoring location AM1(SR77) in the reporting month.
13.1.5 No noise complaint was received in
the reporting month, so no Action Level exceedance
was recorded. Also, no Limit Level exceedance of noise monitoring was recorded in the
reporting month.
13.1.6 One (1)No exceedance
of Action Level on Dissolved Oxygen and no exceedance of Limit Level wasere
recorded for water quality monitoring at the monitoring location I5 in the
reporting month.
13.1.7 Four (4) environmental site inspections were
carried out in the reporting month.
Recommendations on remedial actions were given to the Contractors for
the deficiencies identified during the site audit.
13.2.1 According to the environmental site
inspections performed in the reporting month, there was no recommendation.