Contents
2.3 Construction
Programme and Activities
3 STATUS
OF ENVIRONMENTAL LICENSES, NOTIFICATION AND PERMITS
4.4 Monitoring Parameters, Frequency and
Duration
4.6 Monitoring
Schedule for the Reporting month
5.4 Monitoring
Parameters, Frequency and Duration
5.6 Monitoring Schedule for the Reporting Month
8 ENVIRONMENTAL
SITE INSPECTION AND AUDIT
9 IMPLEMENTATION
STATUS OF ENVIRONMENTAL MITIGATION MEASURES
10 SUMMARY
OF EP SUBMISSION IN THE REPORTING MONTH
11 ENVIRONMENTAL
NON-CONFORMANCE
11.1 Summary
of Monitoring Exceedances
11.2 Summary
of Environmental Non-Compliance
11.3 Summary
of Environmental Complaints
11.4 Summary
of Environmental Summon and Successful Prosecutions
12.1 Construction
Programme for the Next Month
12.2 Key
Issues for the Coming Month
12.3 Monitoring
Schedule for the Next Month
13 CONCLUSIONS
AND RECOMMENDATIONS
List of Tables
Table 2.1 Contact Information of Key Personnel
Table
3.1 Status of
Environmental Licenses, Notifications and Permits
Table
4.1 Air
Quality Monitoring Equipment
Table
4.2 Location
of Air Quality Monitoring
Table
4.3 Air
Quality Monitoring Parameters, Frequency and Duration
Table
4.4 Summary
of 1-hr TSP Monitoring Results
Table
4.5 Summary
of 24-hr TSP Monitoring Results
Table
5.1 Noise
Monitoring Equipment
Table
5.2 Location
of Noise Monitoring
Table
5.3 Noise
Monitoring Parameters, Frequency and Duration
Table
5.4 Summary
of Noise Monitoring Results
Table
8.1 Observations
and Recommendations of Site Audit
Table
9.1 Status
of Required Submission under Environmental Permit
List of Figures
Figure 2 Air and Noise Monitoring Locations
List of Appendices
Appendix A Construction
Programme
Appendix B Project
Organization Structure
Appendix C Calibration
Certificates of Monitoring Equipment
Appendix D EM&A
Monitoring Schedules
Appendix E Meteorological
Data Extracted from Hong Kong Observatory
Appendix F Air Quality
Monitoring Results and their Graphical Presentation
Appendix G Summary of
Event and Action Plan
Appendix H Noise
Monitoring Results and their Graphical Presentation
Appendix I Not
used
Appendix J Not used
Appendix L Implementation
Schedule of Environmental Mitigation Measures (EMIS)
Appendix M Investigation Report
for Exceedances
Appendix N Statistics on
Complaints, Notifications of Summons and Successful Prosecutions
The Entrusted Portion of
Widening of Tolo Highway / Fanling Highway between Island House Interchange and
Fanling Stage 2 (hereafter called ¡§the Project¡¨) covers part of the
construction of the widening
of Tolo Highway / Fanling Highway between Island House Interchange and Fanling
which aimed to widen Tolo Highway and Fanling Highway to dual 4-lane
carriageway in order to alleviate the current traffic congestion problems and
to cope with the increasing transport demands to and from the urban areas and
also cross boundary traffic. The
Project covers construction activities at Yuen Leng
along the existing
The impact EM&A for the Project includes air quality, noise and water quality monitoring. The EM&A programme commenced on 5 November 2013.
This report documents the findings of EM&A works conducted in October 2014. As informed by the Contractor, the major activities in the reporting month were:
¡P Abutment construction for Bridge E;
¡P Cable detection and trial trenches;
¡P Excavation by trenchless method;
¡P Extension of Bored pile for bored pile wall;
¡P Filling Works at Tong Hang East;
¡P Lay storm drains;
¡P Local diversion of DN1400;
¡P Load test for installed Mini pile;
¡P Noise barrier installation;
¡P Pier Construction;
¡P Pile Cap works;
¡P Pre-drilling;
¡P RC structure of new valve control & Telemetry House;
¡P Road works at Fanling Highway;
¡P Sewer works at TWSRW;
¡P Slope upgrading works;
¡P Socket H-pile installation;
¡P Tree Felling Works;
¡P Utilities duct laying; and
¡P Water pipe works.
One (1) Action Level exceedance of 24-hour TSP
monitoring was recorded at the monitoring location AM1(SR77)
on 17 October 2014 in the reporting month. Investigation for the exceedance
was conducted which concluded that the exceedance was
not related to the project works.
The investigation report for the incident is presented in Appendix M.
No exceedance of
Action and Limit Level was recorded for 1-hour TSP monitoring at the monitoring
location AM1(SR77) in the reporting month.
No noise complaint was received in the reporting month, so no Action Level exceedance was recorded. Also, no Limit Level exceedance of noise monitoring was recorded in the reporting month.
The box culvert works have been partially
completed by the end of March 2014 except the last construction activity,
installation of a base slab at Box Culvert ID4. Due to the loading requirement of a
fresh water main under the box culvert, installation of the base slab at Box
Culvert ID4 has to be scheduled to be carried out in November 2015 after the
utilities diversions complete. The
construction works are temporarily suspended until the utilities diversion
works complete. The 4-week post
construction water quality monitoring will be commenced after the installation
of the base slab finishes, hence the completion of the box culvert works.
Impact monitoring for water quality was not
necessary in the reporting month due to temporary suspension of the construction
works and is anticipated to be resumed in November 2015 during the course of
remaining box culvert works.
No complaint, notification of summons and
successful prosecution was received in the reporting month.
The major construction works in the coming
reporting month are anticipated to include:
¡P Lagging wall and capping beam for bored pile wall;
¡P Cable detection and trial trenches;
¡P Catch Fence installation;
¡P Diversion of DN600;
¡P Demolition of central barrier at Fanling Highway;
¡P E & M work for new valve control & Telemetry House;
¡P Laying storm drains;
¡P Noise barrier works;
¡P Pier construction;
¡P Pile Cap;
¡P Piling works for Bridge E;
¡P Pre-drilling works and piling works for viaduct;
¡P Retaining Structure;
¡P Road works at Fanling highway;
¡P Sewer works at TWSRW;
¡P Socket H-pile installation;
¡P Traffic diversion for Fanling Highway;
¡P Tree Felling Works; and
¡P Water pipe works.
Potential environmental impacts arising from the above construction
activities are anticipated to be mainly associated with construction dust,
noise, water quality and waste management.
1.1.1 Chun Wo Construction & Engineering Co Ltd (Chun Wo) was commissioned by the Civil Engineering and Development Department (CEDD) as the Civil Contractor for the Entrusted Portion of Widening of Tolo Highway / Fanling Highway between Island House Interchange and Fanling Stage 2. Meinhardt Infrastructure & Environment Ltd (MIEL) has been appointed by Chun Wo as the Environmental Team (ET) to fulfill the corresponding EM&A requirements pursuant to Environmental Permit No. EP-324/2008/B in accordance with the Updated EM&A Manual (dated October 2013) for Widening of Tolo Highway/Fanling Highway between Island House Interchange and Fanling Stage 2. The EM&A programme commenced in 5 November 2013.
1.2.1 This is the monthly EM&A Report which summaries the impact monitoring results and audit findings for the Project during the reporting month of October 2014.
1.3.1 This monthly EM&A Report comprises the following sections:
¡P Section 1: Introduction
¡P Section 2: Project Information
¡P Section 3: Status of Environmental Licenses, Notifications and Permits
¡P Section 4: Air Quality Monitoring
¡P Section 5: Noise Monitoring
¡P Section 6: Water Monitoring
¡P Section 7: Waste Management
¡P Section 8: Environmental Site Inspection and Audit
¡P Section 9: Implementation Status of Environmental Mitigation Measures
¡P Section 10: Environmental Non-conformance
¡P Section 11: Future Key Issues
¡P Section 12: Conclusions and Recommendations
2.1.1 Tolo Highway and Fanling Highway are expressways in the North East New Territories connecting Sha Tin, Tai Po and Fanling. These highways form a vital part of the strategic Route 1, which links Hong Kong Island to Shenzhen. At present, this section of Route 1 is a dual 3-lane carriageway. However, at several major interchanges along this section of Route 1, the highway is only dual-2 lane. Severe congestion is a frequent occurrence during peak periods, particularly in the Kowloon bound direction.
2.1.2 The objective of the Widening of Tolo Highway / Fanling Highway between Island House Interchange and Fanling is to widen Tolo Highway and Fanling Highway to dual 4-lane carriageway in order to alleviate the current traffic congestion problems and to cope with the increasing transport demands to and from the urban areas and also cross boundary traffic.
2.1.3 The construction works for the Widening of Tolo Highway / Fanling Highway between Island House Interchange and Fanling are to be delivered in 2 stages:
¡P Stage 1 ¡V Construction works between Island House Interchange and Tai Hang; and
¡P Stage 2 ¡V Construction works between Tai Hang and Wo Hop Shek Interchange.
2.1.4 The construction works of Stage 1 under the EP commenced in November 2009 and was planned to be completed in December 2013 tentatively. The works of Stage 2 was planned to commence in November 2013 and complete by end of 2016. Hyder-Arup-Black and Veatch Joint Venture (HABVJV) was appointed by the Highways Department (HyD) as the consultants for the design and construction assignment for the Project. Mott MacDonald Hong Kong Ltd is the Independent Environmental Checker (IEC) of both Stage 1 and Stage 2 works.
2.1.5 A portion of Stage 2 works of Widening of Tolo Highway / Fanling Highway between Island House Interchange and Fanling (hereafter called ¡§the Project¡¨) is entrusted to the contractor of Contract No. CV/2012/09 Liantang / Heung Yuen Wai Boundary Control Point Site Formation and Infrastructure Works Contract 3, i.e. Chun Wo. AECOM Asia Co Ltd was appointed by the CEDD as the consultant for the design and construction assignment for the Liantang development.
2.1.6 The Project is a Designated Project under the Environmental Impact Assessment Ordinance (EIAO) (Cap. 499). An Environmental Impact Assessment (EIA) Report together with an Environmental Monitoring and Audit (EM&A) Manual were approved on 14 July 2000 (Register Number: EIA-043/2000). The Project is governed by an Environmental Permit (EP) (EP-324/2008) which was granted on 23 December 2008. A variation of EP (VEP) was applied and the VEP (EP-324/2008/A) was subsequently granted on 31 January 2012. An additional VEP has been applied on 24 February 2014 and the VEP (EP-324/2008/B) was subsequently granted on 17 March 2014.
2.2.1 The major construction activities under the Entrusted Portion of Widening of Tolo Highway / Fanling Highway between Island House Interchange and Fanling Stage 2 include:
¡P At-Grade Road Works ¡V Temporary and permanent road formation, pipe laying, road drainage, footpath and noise barrier construction;
¡P Demolition of existing Kiu Tau Footbridge and Footbridge Reprovision; and
¡P Box Culvert Extension ¡V Flow diversion of existing stream, excavation, sub-base and blinding, base, wall and top slab construction.
2.2.2 Figure 1 shows the works areas for the Entrusted Portion of Widening of Tolo Highway / Fanling Highway between Island House Interchange and Fanling Stage 2.
2.3.1 The major construction activities undertaken in the reporting month are summarized below:
¡P Abutment construction for Bridge E;
¡P Cable detection and trial trenches;
¡P Excavation by trenchless method;
¡P Extension of Bored pile for bored pile wall;
¡P Filling Works at Tong Hang East;
¡P Lay storm drains;
¡P Local diversion of DN1400;
¡P Load test for installed Mini pile;
¡P Noise barrier installation;
¡P Pier Construction;
¡P Pile Cap works;
¡P Pre-drilling;
¡P RC structure of new valve control & Telemetry House;
¡P Road works at Fanling highway;
¡P Sewer works at TWSRW;
¡P Slope upgrading works;
¡P Socket H-pile installation;
¡P Tree Felling Works;
¡P Utilities duct laying; and
¡P Water pipe works.
2.3.2 The construction programme is presented in Appendix A.
2.4.1 The project organization structure is shown in Appendix B. The key personnel contact names and numbers for the Project are summarised in Table 2.1.
Table 2.1 Contact Information of Key Personnel
Party |
Role |
Position |
Name |
Telephone |
Fax |
AECOM |
Engineer¡¦s Representative |
Senior Resident Engineer |
Mr. Alan Lee |
2171 3303 |
2171 3498 |
Resident Engineer (Environmental) |
Mr.
|
2171 3350 |
|||
Mott MacDonald |
Independent Environmental Checker (IEC) |
IEC |
Mr. Terence Kong |
2828 5919 |
2827 1823 |
Chun Wo |
Contractor |
Site Agent |
Mr. Daniel Ho |
2638 6144 |
2638 7077 |
Senior Environmental Officer |
Mr. Sam Lam |
2638 6168 |
|||
Environmental Officer |
Mr.
|
2638 6181 |
|||
Meinhardt |
Environmental Team (ET) |
ET Leader |
Mr. Fredrick Leong |
2859 1739 |
2540 1580 |
3.1.1 The relevant environmental licenses, permits and/or notifications on environmental protection for this Project and valid in the reporting month are summarized in Table 3.1.
Table 3.1 Status of Environmental Licenses, Notifications and Permits
Permit / License No. /
Notification / Reference No. |
Valid Period |
Status |
Remarks |
|
From |
To |
|||
Environmental Permit |
||||
EP-324/2008/B |
17 Mar 2014 |
-- |
Granted on 17/03/2014 |
-- |
Construction Noise Permit |
||||
GW-RN0397-14 |
29 Jun 2014 |
28 Dec 2014 |
Valid |
For tree felling / transplanting works |
GW-RN0445-14 |
28 Jul 2014 |
25 Jan 2015 |
Valid |
For operating water pump in Kiu Tau at
night |
GW-RN0485-14 |
5 Aug 2014 |
5 Feb 2015 |
Valid |
For operating water pump in jacking pit at
Nam Wah Po |
GW-RN0557-14 |
15 Sep 2014 |
28 Dec 2014 |
Valid |
For road diversion of Southbound of
Fanling Highway |
GW-RN0651-14 |
21 Oct 2014 |
20 Nov 2014 |
Valid |
For erection of catch fence near Pier AD11
& AB10 in the night time |
Wastewater Discharge License |
||||
WT00016832-2013 |
28 Aug 2013 |
31 Aug 2018 |
Valid |
-- |
Chemical Waste Producer
Registration |
||||
5113-634-C3817-01 |
7 Oct 2013 |
-- |
Valid |
-- |
Billing Account for Construction
Waste Disposal |
||||
7017914 |
2 Aug 2013 |
-- |
Account Active |
-- |
Notification Under Air Pollution
Control (Construction Dust) Regulation |
||||
-- |
31 Jul 2013 |
30 Jul 2019 |
Notified |
-- |
4.1.1 In accordance with the Updated EM&A Manual, 1-hr and 24-hr total suspended particulate (TSP) levels at the designated air quality monitoring station are required. Impact 24-hour TSP monitoring should be carried out for at least once every 6 days. For the 1-hr TSP impact monitoring, the sampling frequency of at least three times in every 6 days should be undertaken when the highest dust impact occurs.
4.2.1 The 1hr- TSP and 24-hr TSP air quality monitoring were performed using a High Volume Sampler (HVS), of which its location and operation satisfy, as far as practicable, all the requirements as specified in the Updated EM&A Manual. The brand and model of the equipment are given in Table 4.1.
Table 4.1 Air Quality Monitoring Equipment
Equipment |
Brand and Model |
Quantity |
Serial Number |
High Volume Sampler |
Tisch Total Suspended Particulate Mass Flow Controlled High Volume Air Sampler (Model No. TE-5170 MFC) |
1 |
2359 |
4.2.2 The HVS and its accessories were maintained in good working condition, such as replacing motor brushes routinely and checking electrical wiring to ensure a continuous power supply.
4.2.3 Calibration of the HVS (five point calibration) using Calibration Kit was carried out every two months. The HVS calibration orifice will be calibrated annually. Calibration certificate of the TE-5025A Calibration Kit and the HVS are provided in Appendix C.
4.3.1 Air quality monitoring was conducted at the location specified in the Updated EM&A Manual. Table 4.2 describes the details of the air quality monitoring station with its location as shown in Figure 2.
Table 4.2 Location of Air Quality Monitoring
Air Monitoring Station ID |
Monitoring Location |
Description |
AM1(SR77) * |
Yuen Leng 2 * |
Residential, Ground floor |
Remark:
* Location and Station / ASR ID as identified in Updated EM&A Manual / EIA Report for Widening of Tolo Highway/Fanling Highway between Island House Interchange and Fanling
4.4.1 Table 4.3 summarizes the monitoring parameters, frequency and duration of impact TSP monitoring.
Table 4.3 Air Quality Monitoring Parameters, Frequency and Duration
Parameter |
Frequency and Duration |
1-hour TSP |
At least three times in every 6 days should be undertaken when the highest dust impact occur |
24-hour TSP |
Once every 6 days |
4.5.1 With the consideration of criteria stated in the Updated EM&A Manual, the HVS was installed in the vicinity of the air sensitive receivers.
4.5.2 The relevant data including temperature, pressure, weather conditions, elapsed-time meter reading for the start and stop of the sampler, identification and weight of the filter paper, and any special phenomena observed were recorded. The weather information was referenced from Hong Kong Observatory (http://www.weather.gov.hk/wxinfo/pastwx/extractc.htm).
4.5.3 A HOKLAS accredited laboratory with constant temperature and humidity control, and equipped with necessary measuring and conditioning instruments, to handle the 24-hr TSP samples, was employed for sample analysis.
4.5.4 Filter papers of size 8"x10" were labelled before sampling. They were inspected to be clean with no pin holes and conditioned in a humidity controlled chamber for over 24-hr and were pre-weighed before use for the sampling.
4.5.5 The 24-hr TSP levels were measured by following the standard high volume sampling method for TSP as set out in the Title 40 of the United States Code of Federal Regulations, Chapter 1 (Part 50), Appendix B. TSP was sampled by drawing air through a conditioned, pre-weighted filter paper inside the HVS at a controlled air flow rate. After 24-hr sampling, the filter papers loaded with dust were kept in a clean and tightly sealed plastic bag, and then returned to the laboratory for reconditioning in the humidity controlled chamber followed by accurate weighing by an electronic balance with a readout down to 0.1 mg.
4.5.6 All the collected samples were kept in a good condition for 6 months before disposal.
4.5.7 For 1-hr TSP monitoring, monitoring methodology is the same as 24-hr TSP monitoring which has been presented in Section 4.5.1 to Section 4.5.6, but with sampling period changed to 1 hour.
4.6.1 The schedule for environmental monitoring for the reporting month is provided in Appendix D. Meteorological data extracted from Hong Kong Observatory for the reporting month is provided in Appendix E.
4.7.1 The monitoring results for 1-hr and 24-hr TSP are summarised in Table 4.4 and Table 4.5 respectively. Detailed air quality monitoring results and the graphical presentation of air quality monitoring data for the current and past three reporting months are presented in Appendix F.
Table 4.4 Summary of 1-hr TSP Monitoring Results
ASR ID |
Average (mg/m3) |
Range (mg/m3) |
Action Level (mg/m3) |
Limit Level (mg/m3) |
AM1(SR77) * |
117.0 |
75.0 ¡V 163.9 |
292.7 |
500 |
Remark:
* Station / ASR ID as identified in Updated EM&A Manual / EIA Report for Widening of Tolo Highway/Fanling Highway between Island House Interchange and Fanling
Table 4.5 Summary of 24-hr TSP Monitoring Results
ASR ID |
Average (mg/m3) |
Range (mg/m3) |
Action Level (mg/m3) |
Limit Level (mg/m3) |
AM1(SR77) * |
123.3 |
85.5 ¡V 180.8 |
170.3 |
260 |
Remark:
* Station / ASR ID as identified in Updated EM&A Manual / EIA Report for Widening of Tolo Highway/Fanling Highway between Island House Interchange and Fanling
4.7.2 One (1) Action Level exceedance of 24-hour TSP monitoring was recorded at the monitoring location AM1(SR77) on 17 October 2014 in the reporting month. Investigation for the exceedance was conducted which concluded that the exceedance was not related to the project works. The investigation report for the incident is presented in Appendix M.
4.7.3 No exceedance of Action and Limit Level was recorded for 1-hour TSP monitoring at the monitoring location AM1(SR77) in the reporting month.
4.7.4 The Event and Action Plan for the occurrence of non-compliance of the air quality criteria is annexed in Appendix G.
4.7.5 Meteorological data extracted from Hong Kong Observatory for the reporting month is provided in Appendix E.
5.1.1 In accordance with the Updated EM&A Manual, the impact noise monitoring frequency shall depend on the scale of the construction activities. An initial guide on the regular monitoring frequency should be at least once per week when noise generating activities are underway.
5.2.1 Noise monitoring was performed using a sound level meter at the monitoring station. The sound level meter deployed complies with the International Electrotechnical Commission Publications 651:1979 (Type 1) and 804:1985 (Type 1) specifications. An acoustic calibrator was deployed to check the sound level meter at a known sound pressure level. The brand and model of the equipment is given in Table 5.1.
Table 5.1 Noise Monitoring Equipment
Equipment |
Brand and Model |
Quantity |
Serial Number |
Sound Level Calibrator |
B&K (Model No. 4231) |
1 |
2685684 |
Sound Level Meter |
B&K (Model No. 2238) |
1 |
2694908 |
5.2.2 The sound level calibrator and sound level meter were verified by a certified laboratory every year. Calibration certificates of the sound level meter and acoustic calibrator are provided in Appendix C.
5.3.1 Impact noise monitoring was conducted at the location specified in the Updated EM&A Manual. Table 5.2 describes the details of the noise monitoring station with its location as shown in Figure 2.
Table 5.2 Location of Noise Monitoring
NSR ID |
Monitoring Location |
Description |
M1(SR77) * |
Yuen Leng 2 * |
Residential, Ground floor |
Remark:
* Location and Station / NSR ID as identified in Updated EM&A Manual / EIA Report for Widening of Tolo Highway/Fanling Highway between Island House Interchange and Fanling
5.4.1 Table 5.3 summarizes the monitoring parameters, frequency and duration of impact noise monitoring.
Table 5.3 Noise Monitoring Parameters, Frequency and Duration
Parameter and Duration |
Frequency |
30-mins measurement at between 0700 and 1900 on normal weekdays. Leq, L10 and L90 would be recorded. |
At least once per week |
5.5.1
The monitoring procedures are summarised as
follows:
¡P
The sound level meter was set on a tripod at a height of 1.2 m above the
ground for free-field measurements at monitoring station SR77;
¡P
The battery condition was checked to ensure good functioning of the
meter;
¡P
Parameters such as frequency weighting, the time weighting and the
measurement time were set as follows:
¡P
Frequency weighting: A
¡P
Time weighting: Fast
¡P
Parameters: Leq, L10 and L90
¡P
Time measurement: Leq(30-minutes) during
non-restricted hours i.e. 07:00 ¡V 19:00 hrs on normal weekdays
¡P
Prior to and after each noise measurement, the meter was calibrated
using the acoustic calibrator for 94dB(A) at 1000 Hz. If the difference in the calibration
level before and after measurement was more than 1dB(A), the measurement would
be considered invalid and repeat of noise measurement would be required after
re-calibration or repair of the equipment.
¡P
At the end of the monitoring period, the Leq,
L10 and L90 were recorded. In
addition, site conditions and noise sources were recorded on a standard record
sheet.
¡P
A façade correction of +3dB (A) shall be made to the noise parameter
obtained by free field measurement.
5.6.1 The schedule for environmental monitoring for the reporting month is provided in Appendix D. Meteorological data extracted from Hong Kong Observatory for the reporting month is provided in Appendix E.
5.7.1
The monitoring results for noise are summarized in Table 5.4 and the monitoring results and
the graphical presentation of noise level for the
current and past three reporting months are presented in Appendix H.
Table 5.4 Summary of Noise Monitoring Results
Noise Monitoring Station ID |
Average,
dB(A), Leq (30min) (2) |
Range,
dB(A), |
Action Level |
Limit Level, dB(A) |
M1(SR77) (1) |
70.3 |
68.5 ¡V 71.5 |
When one documented valid complaint is received |
75 |
Remark:
(1) Station / NSR ID as identified in Updated EM&A Manual / EIA Report for Widening of Tolo Highway/Fanling Highway between Island House Interchange and Fanling
(2) +3dB(A) façade correction included
5.7.2 Major noise sources during the noise monitoring included construction activities of the Project and that along Tai Wo Service Road East, and nearby traffic noise.
5.7.3 No noise complaint was received in the reporting month, so no Action Level exceedance was recorded. Also, no Limit Level exceedance of noise monitoring was recorded in the reporting month.
5.7.4 The Event and Action Plan for the occurrence of non-compliance of the noise criteria is annexed in Appendix G.
6.1.1 The box culvert works have been partially completed by the end of March 2014 except the last construction activity, installation of a base slab at Box Culvert ID4. Due to the loading requirement of a fresh water main under the box culvert, installation of the base slab at Box Culvert ID4 has to be scheduled to be carried out in November 2015 after the utilities diversions complete. The construction works are temporarily suspended until the utilities diversion works complete. The 4-week post construction water quality monitoring will be commenced after the installation of the base slab finishes, hence the completion of the box culvert works.
6.1.2 Impact monitoring for water quality was not necessary in the reporting month due to temporary suspension of the construction works and is anticipated to be resumed in November 2015 during the course of remaining box culvert works.
7.1.1 The Contractor has registered as a chemical waste producer of the Project. The C&D materials and waste sorting were carried out on-site. Receptacles were provided for general refuse collection.
7.1.2 As advised by the Contractor, a total of 6,494m3 of excavated material has been generated. 4,244m3 of inert C&D materials was disposed of at public fill to Tuen Mun Area 38. 2,160m3 of inert C&D materials was reused on site. 85m3 of general refuse was disposed of at North East New Territories (NENT) Landfill. 5m3 of plastics, paper/cardboard packaging was collected, and no metals were collected by recycling contractor in the reporting month. No chemical waste was collected by licensed contractor in the reporting period. Details of the waste management data are presented in Appendix K.
8.1.2 In the reporting month, 4 site inspections were carried out on 6, 13, 22 and 27 October 2014. The one held on 27 October 2014 was a joint inspection with the IEC, ER, ET and Contractor. No site inspection was conducted by the EPD during the reporting month. No non-compliance was recorded during the site inspection. A summary of the reminders and observations recorded during the site inspections are presented in Table 8.1.
Table 8.1 Observations and Recommendations of Site Audit
Parameters |
Date |
Observations
and Recommendations |
Follow-up |
Water Quality |
N/A |
N/A |
N/A |
Air Quality |
6 Oct 2014 |
Reminder: The Contractor is reminded to implement proper sign to stop the driver at the wheel washing facilities at SA16. |
A signage of washing area has been put up at the wheel washing facility at SA16 as observed during the ET weekly site inspection on 13 Oct 2014. |
13 Oct 2014 |
Reminder: The Contractor is reminded to ensure all vehicles being washed properly to remove any dusty materials before leaving the site at SA16. |
Dusty material was not observed at the site entrance of SA16. Personnel is now in place to wash the wheels of the vehicles before leaving the site as observed during the ET weekly site inspection on 22 Oct 2014. |
|
22 Oct 2014 |
Observation: Stockpile was observed on site without proper cover or water spraying (SA12) |
Impervious sheets have been provided to cover the stockpile during the ET weekly site inspection on 27 Oct 2014. |
|
22 Oct 2014 |
Reminder: A portion of the construction site was observed not having enough water spraying (SA12) |
The Contractor has implemented sufficient water spraying at SA12 as observed during the ET weekly site inspection on 27 Oct 2014. |
|
27 Oct 2014 |
Reminder: The Contractor is reminded to place signage at appropriate locations to indicate the washing area of wheel washing facilities for the drivers at SA13 and SA16. |
The signage of washing area has been put up at the wheel washing facilities at SA13 and SA16 as observed during the ET weekly site inspection on 3 Nov 2014. |
|
Noise |
N/A |
N/A |
N/A |
Waste / Chemical Management |
6 Oct 2014 |
Reminder: Proper labelling should be
provided to the bins at SA16 and SA12. |
Proper labelled bins for general refuse have been provided at SA16 and SA12 as observed during the ET weekly site inspection on 13 Oct 2014. |
6 Oct 2014 |
Observation: Piles of C&D Waste were
observed near the site entrance at SA16. The contractor was reminded to clean
the waste storage area in a regular basis. |
The C&D waste had been removed
and sorted as far as practicable according to the Contractor. Only the reused
soil has been remained on site and covered with tarpaulin as observed during
the ET weekly site inspection on 13 Oct 2014. |
|
Landscape & Visual |
N/A |
N/A |
N/A |
Permits / Licenses |
N/A |
N/A |
N/A |
9.1.1 The Contractor has implemented the relevant environmental mitigation measures as specified in the EIA Reports, EPs and updated EM&A Manual. The implementation status of environmental mitigation measures during the reporting period is summarized in Appendix L.
10.1.1 The status of the required submission under the EP during the reporting period is summarized in Table 10.1.
Table 10.1 Status of Required Submission under Environmental Permit
EP Condition |
Submission |
Submission Date |
Condition 3.3 |
Monthly EM&A Report for September 2014 |
13 October 2014 |
11.1.1 One (1) Action Level exceedance of 24-hour TSP monitoring was recorded at the monitoring location AM1(SR77) on 17 October 2014 in the reporting month. Investigation for the exceedance was conducted which concluded that the exceedance was not related to the project works. The investigation report for the incident is presented in Appendix M.
11.1.2 No exceedance of Action and Limit Level was recorded for 1-hour TSP monitoring at the monitoring location AM1(SR77) in the reporting month.
11.1.3 No noise complaint was received in the reporting month, so no Action Level exceedance was recorded. Also, no Limit Level exceedance of noise monitoring was recorded in the reporting month.
11.2.1 No environmental non-compliance was recorded in the reporting month. The cumulative statistics are provided in Appendix N.
11.3.1 No environmental complaint was received in the reporting month. The cumulative statistics are provided in Appendix N.
11.4.1 No environmental related prosecution or notification of summons was received in the reporting month. The cumulative statistics are provided in Appendix N.
12.1.1 The major construction works in the coming reporting month are anticipated to include:
¡P ADMS installation;
¡P Lagging wall and capping beam for bored pile wall;
¡P Cable detection and trial trenches;
¡P Catch Fence installation;
¡P Diversion of DN600;
¡P Demolition of central barrier at Fanling Highway;
¡P E & M work for new valve control & Telemetry House;
¡P Laying storm drains;
¡P Noise barrier works;
¡P Pier construction;
¡P Pile Cap;
¡P Piling works for Bridge E;
¡P Pre-drilling works and piling works for viaduct;
¡P Retaining Structure;
¡P Road works at Fanling highway;
¡P Sewer works at TWSRW;
¡P Socket H-pile installation;
¡P Traffic diversion for Fanling Highway;
¡P Tree Felling Works; and
¡P Water pipe works.
12.2.1 Key issues to be considered in the coming month are anticipated to include:
¡P Site discharges should be properly collected and treated prior to discharge;
¡P Properly maintain all drainage facilities and wheel washing facilities on site;
¡P Expose slopes and dusty stockpile should be covered up properly if no work will be conducted; and
¡P Operation of construction plant should be sequenced where practicable.
12.3.1 The tentative schedule for environmental monitoring for the coming month is provided in Appendix D.
13.1.1 The construction phase EM&A programme of the Project commenced on 5 November 2013.
13.1.2 The 1-hr TSP, 24-hr TSP and noise monitoring were carried out in the reporting period.
13.1.1 One (1) Action Level exceedance of 24-hour TSP monitoring was recorded at the monitoring location AM1(SR77) on 17 October 2014 in the reporting month. Investigation for the exceedance was conducted which concluded that the exceedance was not related to the project works. The investigation report for the incident is presented in Appendix M.
13.1.2 No exceedance of Action and Limit Level was recorded for 1-hour TSP monitoring at the monitoring location AM1(SR77) in the reporting month.
13.1.3 No noise complaint was received in the reporting month, so no Action Level exceedance was recorded. Also, no Limit Level exceedance of noise monitoring was recorded in the reporting month.
13.1.4 Four (4) environmental site inspections were carried out in the reporting month. Recommendations on remedial actions were given to the Contractors for the deficiencies identified during the site audit.
13.1.5 The box culvert works have been partially completed by the end of March 2014 except the last construction activity, installation of a base slab at Box Culvert ID4. Due to the loading requirement of a fresh water main under the box culvert, installation of the base slab at Box Culvert ID4 has to be scheduled to be carried out in November 2015 after the utilities diversions complete. The construction works are temporarily suspended until the utilities diversion works complete. The 4-week post construction water quality monitoring will be commenced after the installation of the base slab finishes, hence the completion of the box culvert works.
13.1.6 Impact monitoring for water quality was not necessary in the reporting month due to temporarily suspension of the construction works and is anticipated to be resumed in November 2015 during the course of remaining box culvert works.
13.2.1 According to the environmental site inspections performed in the reporting month, the following recommendations were provided:
¡P Water spraying or covering of tarpaulin should be properly implemented whenever necessary for the unpaved roads, access roads and construction areas.
¡P All vehicles should be washed to remove any dusty materials before leaving the construction site.
¡P Wheel washing facilities should be properly maintained to ensure proper functioning.
¡P All types of wastes, both on land and floating in the river stream, should be collected and sorted properly, and also be disposed timely and properly.
¡P Refuse collection bins should be labelled properly.