Contents
Page
EXECUTIVE SUMMARY i
1 INTRODUCTION AND PROJECT INFORMATION 1
1.1 Background.............................................................................................................. 1
1.2 Construction
Programme and Activities.................................................................. 1
1.3 Project
Organisation............................................................................................ 232
1.4 Purpose of the
Report............................................................................................ 23
2 SUMMARY OF EM&A REQUIREMENTS 23
2.1 Environmental Impact Hypothesis under Monitoring............................................ 23
2.2 Monitoring
Requirements..................................................................................... 343
2.3 Environmental
Mitigation Measures.................................................................... 344
3 SUMMARY OF EM&A MONITORING DATA 35
3.1 Monitoring Data...................................................................................................... 35
3.2 Summary of
Monitoring Exceedances.................................................................. 45
4 ENVIRONMENTAL NON-CONFORMANCE 476
4.1 Summary of
Environmental Non-Compliance.................................................... 476
4.2 Summary of
Environmental Complaints............................................................... 47
4.3 Summary of
Environmental Summon and Successful Prosecutions.................. 57
5 REVIEW OF THE VALIDITY OF EIA
PREDICTIONS 57
6 REVIEW OF EM&A PROGRAMME 57
7 CONCLUSIONS 57
Table 1.1 Contact
Information of Key Personnel
Table 2.1 Monitoring
Parameter
Table 3.1 Summary
of Monitoring Data in the Reporting Period
Table 3.2 Summary
of Exceedance Events in the Reporting Period
List of Figures
Figure 2 Environmental
Monitoring Locations
List of Appendices
Appendix A Construction
Programme
Appendix B Project Organization Structure
Appendix C Summary of Event and Action Plan
Appendix D Implementation Schedule of Environmental
Mitigation Measures (EMIS)
Appendix E Summary of Meteorological Condition
Extracted from Hong Kong Observatory
Appendix F Environmental Monitoring Data for Air,
Noise and Water Quality
Appendix G Statistics on Complaints, Notifications
of Summons and Successful Prosecutions
This report documents the findings of EM&A works conducted during
the period between November 2018 and October 2019.
The impact stage EM&A programme for the Project includes air quality
and, noise quality monitoring.
The EM&A programme was carried out by the
ET in accordance with the EM&A Manual requirements. It is concluded from the environmental monitoring
and audit works that adequate environmental mitigation measures have been
implemented by the civil works contractors where appropriate in the reporting period.
In the reporting period, no exceedance event was
recorded. No necessary remedial actions
have been taken.
No environmental non-compliance was noted. One environmental complaint was
received,.
which was
concluded that it was
unlikely due to the construction works of this Project after
investigations, was received. No environmental related prosecution or
notification of summons was received in the reporting period.
1.1.1
The
Project is a Designated Project under the Environmental Impact Assessment
Ordinance (EIAO) (Cap. 499). An
Environmental Impact Assessment (EIA) Report together with an Environmental
Monitoring and Audit (EM&A) Manual were approved on 14 July 2000 (Register
Number: EIA-043/2000). The Project
is governed by an Environmental Permit (EP) (EP-324/2008) which was granted on
23 December 2008. A variation of EP
(VEP) was applied and the VEP (EP-324/2008/A) was subsequently granted on 31
January 2012. An additional VEP has
been applied on 24 February 2014 and the VEP (EP-324/2008/B) was subsequently
granted on 17 March 2014. Furthermore, an additional VEP has been applied on 9 March 2015 and the VEP
(EP-324/2008/C) was subsequently granted on 27 March 2015. The previous VEP
(EP-324/2008/D) was granted on 27 August 2015. The current VEP (EP-324/2008/E)
was granted on 26 January 2017.
1.1.2
Chun
Wo Construction &
Engineering Co Ltd (Chun Wo) was commissioned by the
Civil Engineering and Development Department (CEDD) as the Civil Contractor for
the Entrusted Portion of Widening of Tolo Highway/Fanling Highway between Island House Interchange and Fanling Stage 2.
Meinhardt Infrastructure & Environment Ltd
(MIEL) has been appointed by Chun Wo
as the Environmental Team (ET) to fulfill the
corresponding EM&A requirements pursuant to Environmental Permit No.
EP-324/2008/D in accordance with the Updated EM&A Manual (dated October
2013) for Widening of Tolo Highway/Fanling Highway between Island House Interchange and Fanling Stage 2.
The EM&A programme commenced in 5 November 2013.
1.1.3
Figure 1 shows the works areas for the
Entrusted Portion of Widening of Tolo Highway/Fanling Highway between Island House Interchange and Fanling Stage 2.
1.2.1
The
master construction programme for the entire construction period is presented
in Appendix A. The major
construction activities undertaken in the reporting period are summarized
below:
¡P
Cable Detection and Trial Trenches; |
¡P
Noise Barrier Construction; |
¡P
Road Pavement Works; |
¡P
Water main laying works (on Grade and on bridge deck); |
¡P
Installation of Noise
barrier steel column & panel, and sign gantry (on Grade and on bridge
deck); ¡P
Construction of Pavilion and Pai Lau; ¡P
Parapet Installation on bridge deck; |
¡P
Road Drainage Work; ¡P
Waterproofing works on bridge deck; ¡P
Bitumen paving on bridge deck; ¡P
Construction of retaining wall; and ¡P
Landscaping works; ¡P
Construction of Police
Observation Platform on the Northbound Fanling
Highway; and ¡P
Remaining works of Kiu
Tau footbridge. |
1.3.1
The
project organization structure is shown in Appendix B. The key personnel contact names and
numbers for the Project, together with the general enquiry hotline, are
summarised in Table 1.1.
Table 1.1 Contact Information of Key Personnel
Party |
Role |
Position |
Name |
Tele-phone |
Fax |
AECOM |
Engineer¡¦s
Representative |
Senior
Resident Engineer |
Mr. Alan Lee |
2171 3303 |
2171 3498 |
Resident Engineer (Environmental) |
Mr. |
2171 3350 |
|||
Mott MacDonald |
Independent Environmental Checker (IEC) |
IEC |
Mr. Steven Tang |
2828 5920 |
2827 1823 |
Chun Wo |
Contractor |
Site Agent |
Mr. Ken Lun |
2638 6144 |
2638 7077 |
Environmental Officer |
Mr. Yip Yun Lam |
2638 6147 |
|||
Meinhardt |
Environmental Team (ET) |
ET Leader |
Mr. Fredrick Leong |
2859 1739 |
2540 1580 |
Enquiry Hotline |
General Enquiry |
-- |
Ms Helena Mak |
6355 1731 |
-- |
1.4.1
This
is the Annual EM&A Review Report which summaries
the impact monitoring results and audit findings for the Project during the
reporting period between November 2018 and October 2019.
2.1.1
The
EIA Report concluded that with proper mitigation measures implemented, fugitive
dust emission during construction phase would be controlled and will not exceed
the acceptable criteria.
2.1.2
For
construction noise, exceedances were predicted only
at 2 schools (SR41 Wong Shiu Chi Middle School and
SR45 HK Teacher¡¦s Association Secondary School) but they are out of the scope
of this EM&A Programme. Hence
the EIA did not anticipate any noise exceedances
during construction phase within the scope of this EM&A Programme.
2.1.3
The
above criteria have been tested under this EM&A Programme during the
reporting period.
2.2.1
In
accordance with the Updated EM&A Manual, environmental parameters including
air quality, noise have been monitored.
The specific parameters, monitoring frequency and the respective Action
and Limit Levels are given in Table 2.1 and the location of the monitoring
station is shown in the Figure 2.
Table 2.1 Monitoring Parameter
Parameter |
Unit |
Action
Level |
Limit Level |
Frequency |
Air Quality |
||||
1-hour
TSP |
mg/m3 |
292.7 |
500 |
Three times every 6 days |
24-hour
TSP |
mg/m3 |
170.3 |
260 |
Once every 6 days |
Construction Noise |
||||
Leq
30min |
dB(A) |
When
one documented valid complaint is received |
75 |
Once every Week |
2.2.2
The
Event and Action Plan for the occurrence of non-compliance of the criteria of
the monitoring parameters is annexed in Appendix C.
2.3.1
Environmental
mitigation measures have been recommended in the EM&A Manual and are given
in Appendix D. The implementation
status for the reporting period is also given in the Appendix.
3.1.1
Monitoring has been conducted in accordance with the
specification in the EM&A Manual in the reporting period. Summary of meteorological
condition for the reporting period have been extracted from Hong Kong
Observatory and
are given in Appendix E. Monitoring
data with graphical presentation for the reporting period have been given in Appendix
F. A summary on the monitoring
results has also been given in Table 3.1.
Table 3.1 Summary of Monitoring Data in the Reporting Period
Monitoring Location |
Minimum |
Maximum |
Average |
Air Quality |
|||
1-hour Total
Suspended Particulate |
|||
SR77 |
38.7mg/m3 |
219.3mg/m3 |
134.2mg/m3 |
24-hour Total
Suspended Particulate |
|||
SR77 |
19.1mg/m3 |
164.2mg/m3 |
75.9mg/m3 |
Construction Noise |
|||
SR77 |
63.0dB(A) |
71.0dB(A) |
65.9dB(A) |
3.2.1
The
number of exceedance events recorded in the reporting
period is summarized in Table 3.2.
3.2.2
Investigation
for the exceedance event in the reporting period has been
completed and the exceedance was concluded not
related to the Project. No necessary
remedial actions have been taken. The
respective investigation report has been presented in the respective Monthly
EM&A Report.
Table 3.2 Summary of Exceedance Events in the Reporting Period
Parameter |
|
Number of Exceedance
Events |
Number of Project Related Exceedance Events |
Air Quality |
|||
1-hour Total
Suspended Particulates |
Action Level |
0 |
0 |
Limit
Level |
0 |
0 |
|
24-hour Total
Suspended Particulates |
Action Level |
1 |
0 |
Limit
Level |
0 |
0 |
|
Construction Noise |
|||
Leq 30min |
Action Level |
0 |
0 |
Limit
Level |
0 |
0 |
3.2.3
The
Contractor has been reminded to strengthen the mitigation measures including:
¡P
Stockpile
of dusty material shall be covered by impervious sheeting entirely.
¡P
Vehicle
washing facility shall be provided at all site exits to wash away any dusty
materials from vehicle before they leave the site.
¡P
Mud
and debris shall be removed to prevent potential muddy water flow to public
road.
¡P
Secondary
containment shall be provided for chemical to prevent potential leakage.
4.1.1
No
environmental non-compliance was recorded in the reporting period.
4.2.1
No
environmental complaint was received in the reporting period.
4.3.1
No
environmental related prosecution or notification of summons was received in
the reporting period. The cumulative
statistics are provided in is provided in Appendix G.
5.1.1
The
EIA report predicted that with proper implementation of the mitigation measures
for air and noise, environmental impact would
be locally confined and controllable.
During the reporting period, No exceedance was
recorded and it is concluded that the EIA predictions are valid for the reporting
period.
6.1.1
The
EM&A programme was considered successfully and adequately conducted during
the course of the reporting period.
7.1.1
The
EM&A programme were carried out by the ET in accordance with the EM&A
Manual requirements. It is concluded from the environmental monitoring and
audit works that adequate environmental mitigation measures have been
implemented by the civil works contractors where appropriate in the reporting
period.
7.1.2
In
the reporting period, No exceedance event has been recorded. No necessary remedial actions have been
taken.
7.1.3
No
environmental non-compliances were noted. No environmental complaint was
received in the reporting period.