Contents
Page
EXECUTIVE SUMMARY i
1 INTRODUCTION AND PROJECT INFORMATION 1
1.1 Background.............................................................................................................. 1
1.2 Construction
Programme and Activities.................................................................. 1
1.3 Project
Organisation................................................................................................ 2
1.4 Purpose of the
Report.............................................................................................. 3
2 SUMMARY OF EM&A REQUIREMENTS 3
2.1 Environmental Impact Hypothesis under Monitoring.............................................. 3
2.2 Monitoring
Requirements......................................................................................... 3
2.3 Environmental
Mitigation Measures........................................................................ 5
3 SUMMARY OF EM&A MONITORING DATA 5
3.1 Monitoring Data........................................................................................................ 5
3.2 Summary of
Monitoring Exceedances.................................................................... 5
4 ENVIRONMENTAL NON-CONFORMANCE 7
4.1 Summary of Environmental Non-Compliance........................................................ 7
4.2 Summary of Environmental Complaints................................................................. 7
4.3 Summary of Environmental Summon and
Successful Prosecutions.................... 7
5 REVIEW OF THE VALIDITY OF EIA PREDICTIONS 7
6 REVIEW OF EM&A PROGRAMME 7
7 CONCLUSIONS 7
Table 1.1 Contact
Information of Key Personnel
Table 2.1 Monitoring
Parameter
Table 3.1 Summary
of Monitoring Data in the Reporting Period
Table 3.2 Summary
of Exceedance Events in the Reporting Period
List of Figures
Figure 2 Environmental Monitoring
Locations
List of Appendices
Appendix A Construction Programme
Appendix B Project Organization Structure
Appendix C Summary of Event and Action Plan
Appendix D Implementation Schedule of Environmental Mitigation Measures
(EMIS)
Appendix E Meteorological Data Extracted from Hong Kong Observatory
Appendix F Environmental Monitoring Data for Air, Noise and Water Quality
Appendix G Statistics on Complaints, Notifications of Summons and
Successful Prosecutions
This report documents the findings of EM&A works conducted during
the period between November 2013 and October 2014.
The impact stage EM&A programme for the Project includes air
quality, noise and water quality monitoring.
The EM&A programme was carried out by the
ET in accordance with the EM&A Manual requirements. It is concluded from the environmental
monitoring and audit works that adequate environmental mitigation measures have
been implemented by the civil works contractors where appropriate in the
reporting period.
In the reporting period, a total of 36 exceedance
events were recorded. Only 2 of the
exceedances of Suspended Solids and Turbidity
recorded on 18 December 2013 were concluded to be project related. Necessary remedial actions have been
taken and the exceedances have been rectified.
No environmental non-compliance was noted. One environmental complaint,
which was concluded as an invalid complaint under this Project after
investigations, was received. No environmental
related prosecution or notification of summons was received in the reporting
period.
The box culvert works have been partially completed by the end of March 2014 except the last
construction activity, i.e. installation of a base slab at Box Culvert
ID4. Due to the loading requirement
of a fresh water main under the box culvert, installation of the base slab at
Box Culvert ID4 has to be scheduled in November 2015 after the utilities
diversions were completed, and therefore the construction works were temporary
suspended. The 4-week post
construction water quality monitoring will be conducted after the installation
of the base slab finishes, hence the completion of the box culvert works. As such, impact monitoring for water
quality is anticipated to be resumed in November 2015 during the course of
remaining box culvert works.
1.1.1
The
Project is a Designated Project under the Environmental Impact Assessment
Ordinance (EIAO) (Cap. 499). An
Environmental Impact Assessment (EIA) Report together with an Environmental
Monitoring and Audit (EM&A) Manual were approved on 14 July 2000 (Register
Number: EIA-043/2000). The Project
is governed by an Environmental Permit (EP) (EP-324/2008) which was granted on
23 December 2008. A variation of EP
(VEP) was applied and the VEP (EP-324/2008/A) was subsequently granted on 31
January 2012. An additional VEP has been applied on 24 February 2014 and the VEP
(EP-324/2008/B) was subsequently granted on 17 March 2014.
1.1.2
Chun
Wo Construction &
Engineering Co Ltd (Chun Wo) was commissioned by the
Civil Engineering and Development Department (CEDD) as the Civil Contractor for
the Entrusted Portion of Widening of Tolo Highway/Fanling Highway between
Island House Interchange and Fanling Stage 2. Meinhardt Infrastructure &
Environment Ltd (MIEL) has been appointed by Chun Wo as the Environmental Team (ET) to fulfill the corresponding EM&A requirements pursuant to
Environmental Permit No. EP-324/2008/B in accordance with the Updated EM&A
Manual (dated October 2013) for Widening of Tolo Highway/Fanling Highway between Island House
Interchange and Fanling Stage 2.
The EM&A programme commenced in 5 November 2013.
1.1.3
Figure 1 shows the works areas for the Entrusted
Portion of Widening of Tolo Highway/Fanling Highway between Island House
Interchange and Fanling Stage 2.
1.2.1
The
master construction programme for the entire construction period is presented
in Appendix A. The major
construction activities undertaken in the reporting period are summarized
below:
¡P Hoarding and fencing erection, initial survey and base slab demolition;
¡P Site clearance and tree felling;
¡P Excavation works and base slab demolition;
¡P Pre-drilling works and piling works;
¡P Piling works for Bridge E;
¡P Extension of box culverts;
¡P Cable detection and trial trenches;
¡P Tree Felling Works;
¡P Trial Pit Excavation;
¡P Bored pile and bored pile wall construction;
¡P Catch Fence Installation;
¡P Extension of Bored pile for bored pile wall;
¡P Erection of site office;
¡P Construction of haul road and temporary soil platform for geotechnical works;
¡P Slope upgrading works;
¡P Noise barrier installation;
¡P Mini pile construction;
¡P Load test for installed Mini pile;
¡P Water pipe Installation;
¡P Diversion of DN1400;
¡P Filling Works;
¡P Laying of storm drains;
¡P Laying of concrete pipe works;
¡P Pile Cap works;
¡P Receiving & Jacking Pit;
¡P Retaining Structure;
¡P Road works at Fanling Highway;
¡P Sewer works;
¡P Soil nail construction;
¡P RC structure of new valve control & Telemetry House;
¡P Demolition of Huts;
¡P Abutment construction for Bridge E;
¡P Excavation by trenchless method;
¡P Pier Construction;
¡P Socket H-pile installation;
¡P Site formation;
¡P Installation of DN1200 Drainage Pipe by Pipe Jacking Method Across Fanling Highway;
¡P Trim pile head for bored pile wall;
¡P Diversion of existing cycle track; and
¡P Utilities duct laying.
1.3.1
The
project organization structure is shown in Appendix B. The key personnel contact names and numbers
for the Project, together with the general enquiry hotline, are summarised in Table 1.1.
Table 1.1 Contact Information of Key Personnel
Party |
Role |
Position |
Name |
Tele-phone |
Fax |
AECOM |
Engineer¡¦s
Representative |
Senior
Resident Engineer |
Mr. Alan Lee |
2171 3303 |
2171 3498 |
Resident Engineer (Environmental) |
Mr. |
2171 3350 |
|||
Mott MacDonald |
Independent Environmental Checker (IEC) |
IEC |
Mr. Terence Kong |
2828 5919 |
2827 1823 |
Chun Wo |
Contractor |
Site Agent |
Mr. Daniel Ho |
2638 6144 |
2638 7077 |
Senior
Environmental Officer |
Mr. Sam Lam |
2638 6168 |
|||
Environmental Officer |
Mr. |
2638 6181 |
|
||
Meinhardt |
Environmental Team (ET) |
ET Leader |
Mr. Fredrick Leong |
2859 1739 |
2540 1580 |
Enquiry Hotline |
General Enquiry |
-- |
Ms Helena Mak |
6355 1731 |
-- |
1.4.1
This
is the Annual EM&A Review Report which summaries
the impact monitoring results and audit findings for the Project during the
reporting period between November 2013 and October 2014.
2.1.1
The
EIA Report concluded that with proper mitigation measures implemented, fugitive
dust emission during construction phase would be controlled and will not exceed
the acceptable criteria.
2.1.2
For
construction noise, exceedances were predicted only
at 2 schools (SR41 Wong Shiu Chi Middle School and
SR45 HK Teacher¡¦s
2.1.3
For
water quality, it is also anticipated that with proper protection measures
being implemented, the water quality during construction phase would be locally
confined and controllable.
2.1.4
The
above criteria have been tested under this EM&A Programme during the
reporting period.
2.2.1
In
accordance with the Updated EM&A Manual, environmental parameters including
air quality, noise and water quality have been monitored. The specific parameters, monitoring
frequency and the respective Action and Limit Levels are given in Table 2.1 and the location of the monitoring
station is shown in the Figure 2.
Table 2.1 Monitoring Parameter
Parameter |
Unit |
Action
Level |
Limit Level |
Frequency |
Air Quality |
||||
1-hour
TSP |
mg/m3 |
292.7 |
500 |
Three times every 6 days |
24-hour TSP |
mg/m3 |
170.3 |
260 |
Once every 6 days |
Construction Noise |
||||
Leq
30min |
dB(A) |
When
one documented valid complaint is received |
75 |
Once every Week |
Water Quality |
||||
Depth |
|
-- |
-- |
Three occasions per week |
Temperature |
¢XC |
-- |
-- |
Three occasions per week |
Salinity |
ppt |
-- |
-- |
Three occasions per week |
pH |
-- |
-- |
-- |
Three occasions per week |
DO |
mg/L |
6.7 |
4mg/L or 40% saturation at 15 degree Celsius |
Three occasions per week |
DO
Saturation |
% |
-- |
-- |
Three occasions per week |
Turbidity |
NTU |
81.9NTU
or 120% of upstream control station¡¦s Tby of the
same day |
91.9NTU or 130% of upstream control station¡¦s
Tby of the same day |
Three occasions per week |
SS |
mg/L |
42.6
mg/L or 120% of upstream control station¡¦s SS of the same day |
46.8 mg/L or 130% of upstream station¡¦s SS of
the same day and specific sensitive receiver water quality requirements |
Three occasions per week |
2.2.2
The Event and Action Plan for the
occurrence of non-compliance of the criteria of the monitoring parameters is annexed in Appendix C.
2.2.3 The box culvert works have been partially completed by the end of March 2014 except the last construction activity, which is the installation of a base slab at Box Culvert ID4. Due to the loading requirement of a fresh water main under the box culvert, installation of the base slab at Box Culvert ID4 has to be scheduled in November 2015 after the utilities diversions were completed, and therefore the construction works are temporarily suspended. The 4-week post construction water quality monitoring will be conducted after the installation of the base slab finishes, hence the completion of the box culvert works. As such, impact monitoring for water quality is anticipated to be resumed in November 2015 during the course of remaining box culvert works.
2.3.1
Environmental mitigation measures have been
recommended in the EM&A Manual and is given in Appendix D. The implementation status for the
reporting period is also given in the Appendix.
3.1.1
Monitoring has been conducted in accordance with the specification
in the EM&A Manual in the reporting period. Meteorological data for the reporting
period have been extracted from Hong Kong Observatory and are given in Appendix E. Monitoring data with graphical
presentation for the reporting period have been given in Appendix F. A summary on the monitoring results has
also been given in Table 3.1.
Table 3.1 Summary of Monitoring Data in the Reporting Period
Monitoring Location |
Minimum |
Maximum |
Average |
Air Quality |
|||
1-hour Total
Suspended Particulate |
|||
SR77 |
34.6mg/m3 |
283.0mg/m3 |
135.5mg/m3 |
24-hour Total
Suspended Particulate |
|||
SR77 |
14.7mg/m3 |
402.1mg/m3 |
137.8mg/m3 |
Construction Noise |
|||
SR77 |
54.5dB(A) |
73.5dB(A) |
64.4dB(A) |
Water Quality |
|||
DO |
|||
I5 |
4.4mg/L |
10.1mg/L |
8.0mg/L |
Baseline Data |
6.6mg/L |
8.8mg/L |
8.0mg/L |
30% disturbance due to human activity |
4.6mg/L |
6.2mg/L |
5.6mg/L |
Turbidity |
|||
I5 |
6.3NTU |
86.7NTU |
24.7NTU |
Baseline Data |
12.4NTU |
91.5NTU |
26.1NTU |
30% disturbance due to human activity |
16.1NTU |
118.9NTU |
34.0NTU |
SS |
|||
I5 |
2.0mg/L |
72.5mg/L |
11.9mg/L |
Baseline Data |
6.5mg/L |
46.5mg/L |
16.4mg/L |
30% disturbance due to human activity |
8.5mg/L |
60.5mg/L |
21.3mg/L |
3.2.1
The
number of exceedance events recorded in the reporting
period is summarized in Table 3.2.
3.2.2
Investigations
for the exceedance events in the reporting period
have been completed. Only 2 of the exceedances of Suspended Solids and Turbidity respectively
recorded on 18 December 2013 were concluded to be project related. Necessary remedial actions have been
taken and the exceedances have been rectified. The respective investigation reports
have been presented in the respective Monthly EM&A Reports.
Table 3.2 Summary of Exceedance Events in the Reporting Period
Parameter |
|
Number of Exceedance
Events |
Number of Project Related Exceedance Events |
Air Quality |
|||
1-hour Total
Suspended Particulates |
Action Level |
0 |
0 |
Limit
Level |
0 |
0 |
|
24-hour Total
Suspended Particulates |
Action Level |
17 |
0 |
Limit
Level |
4 |
0 |
|
Construction Noise |
|||
Leq 30min |
Action Level |
0 |
0 |
Limit
Level |
0 |
0 |
|
Water Quality |
|||
DO |
Action Level |
2 |
0 |
Limit
Level |
0 |
0 |
|
Turbidity |
Action Level |
2 |
0 |
Limit
Level |
2 |
1 |
|
SS |
Action Level |
1 |
0 |
Limit
Level |
8 |
1 |
3.2.3
The
Contractor has been reminded to strengthen the mitigation measures including:
¡P Building a river diversion structure at the river channel to protect the river from potential site runoff and fill up the leakage and strengthen the river diversion works to avoid future leakage;
¡P Pay attention on accidental site runoff, including construction of additional protection structure if necessary, to minimize the risk of site runoff;
¡P Silty effluent should be treated/desilted before discharged. Untreated effluent should be prevented from entering public drain channel;
¡P Channels or earth bunds or sand bag barriers should be provided on site to prevent surface runoff and properly direct stormwater to silt removal facilities;
¡P Covering of exposed slopes near the river,
¡P Watering and covering of exposed slopes and stockpiles to avoid fugitive dust emission;
¡P Water spraying should be properly implemented whenever necessary for the unpaved roads, access roads and construction areas;
¡P All vehicles should be washed to remove any dusty materials before leaving the construction site, and the wheel washing facilities should be properly maintained to ensure proper functioning;
¡P Ensuring regular maintenance and cleaning of waste storage area;
¡P All types of wastes, both on land and floating in the river stream, should be collected and sorted properly, and also be disposed timely and properly;
¡P Refuse collection bins should be labelled properly;
¡P Ensuring the provision of tree protection zone for all existing trees to be transplanted or retained; and
¡P All chemicals stored on site should be provided with drip trays.
4.1.1
No
environmental non-compliance was recorded in the reporting period.
4.2.1
One
(1) environmental complaint was received in the reporting period regarding
water quality of Ma Wat River. Investigation has been conducted and the
complaint was considered as invalid under this Project.
4.3.1
No
environmental related prosecution or notification of summons was received in
the reporting period. The cumulative statistics are provided
in is provided in Appendix
G.
5.1.1 The EIA report predicted that with proper implementation of the mitigation measures for air, noise and water quality, environmental impact would be locally confined and controllable. During the reporting period, only 2 exceedances were recorded in 1 day due to a leakage at the bund used for river diversion. The exceedance event is rectified after the leakage has been blocked. Other exceedances were concluded not project related. Hence, it is considered that the EIA predictions is valid for the reporting period.
6.1.1
The
EM&A programme was considered successfully and adequately conducted during
the course of the reporting period.
6.1.2
The
box culvert works have been partially completed by the end of March 2014 except the last
construction activity, which is the installation of a base slab at Box Culvert
ID4. Due to the loading requirement
of a fresh water main under the box culvert, installation of the base slab at
Box Culvert ID4 has to be scheduled in November 2015 after the utilities
diversions were completed, and therefore the construction works were
temporarily suspended. The 4-week
post construction water quality monitoring will be conducted after the
installation of the base slab finishes, hence the completion of the box culvert
works. As such, impact monitoring for
water quality is anticipated to be resumed in November 2015 during the course
of remaining box culvert works.
7.1.1
The EM&A programme was carried out by the
ET in accordance with the EM&A Manual requirements. It is concluded from
the environmental monitoring and audit works that adequate environmental
mitigation measures have been implemented by the civil works contractors where
appropriate in the reporting period.
7.1.2
In
the reporting period, a total of 36 exceedance events
have been recorded. Only 2 of the exceedances of Suspended Solids and Turbidity recorded on
18 December 2013 were concluded to be project related. Necessary remedial actions have been
taken and the exceedances have been rectified.
7.1.3 No environmental non-compliances were noted. One environmental complaint, which was concluded as an invalid complaint under this Project after investigations, was received. No environmental related prosecution or notification of summons were received in the reporting period.
7.1.4
The box culvert works have been partially completed
by the end of March 2014 except the last construction activity, i.e.
installation of a base slab at Box Culvert ID4. Due to the loading requirement of a
fresh water main under the box culvert, installation of the base slab at Box
Culvert ID4 has to be scheduled in November 2015 after the utilities diversions
were completed, and therefore the construction works are temporarily
suspended. The 4-week post construction water quality monitoring will be conducted
after the installation of the base slab finishes, hence the completion of the
box culvert works. As such, impact monitoring for water quality was not necessary in the reporting
period due to temporary suspension of the construction works and is anticipated
to be resumed in November 2015 during the course of remaining box culvert
works.