Site
Inspection Summary
Contract No. |
HY/2009/08 (Between Ma Wo
and Tai Hang) |
Date: |
7 August 2014 |
Time: |
14:00 |
Inspection No.: |
462 |
|
Nil |
|
Follow Up
Observations |
1. |
Open
stockpiles were removed (Closed). |
2. |
Mud on the footpath was cleared (Closed). |
|
|
|
New Observations |
|
Nil. |
|
|
|
|
|
|
|
|
|
|
|
|
|
Nil |
Contract No. |
HY/2009/08 (Between Ma Wo
and Tai Hang) |
Date: |
14 August 2014 |
Time: |
14:00 |
Inspection No.: |
463 |
|
Nil |
|
Follow Up
Observations |
|
Nil. |
|
|
|
|
|
New Observations |
|
Nil. |
|
Reminders |
|
The
Contractor was reminded to clear the stagnant water. |
|
|
|
|
|
|
|
|
|
|
|
Nil |
Contract No. |
HY/2009/08 (Between Ma Wo
and Tai Hang) |
Date: |
21 August 2014 |
Time: |
14:00 |
Inspection No.: |
464 |
|
Nil |
|
Follow Up
Observations |
|
Nil. |
|
|
|
|
|
New Observations |
|
Nil. |
|
Reminders |
|
Exposed
slope was observed. The Contractor was reminded to cover the slopes after
daily construction activities. |
|
|
|
|
|
|
|
|
|
|
|
Nil |
Contract No. |
HY/2009/08 (Between Ma Wo
and Tai Hang) |
Date: |
29 August 2014 |
Time: |
14:00 |
Inspection No.: |
465 |
|
Nil |
|
Follow Up
Observations |
|
Nil. |
|
|
|
|
|
New Observations |
|
Nil. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Nil |