Site
Inspection Summary
Contract No. |
HY/2008/09 (Between Island House Interchange and
Ma Wo) |
Date: |
2
July 2014 |
Time: |
09:00 |
Inspection No.: |
455 |
|
Nil |
|
Follow Up
Observations |
|
|
|
Nil. |
|
|
|
|
|
|
|
New
Observations |
|
|
|
Nil. |
|
|
|
|
|
|
|
|
|
Nil |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Contract No. |
HY/2009/08 (Between Ma Wo and Tai Hang) |
Date: |
3
July 2014 |
Time: |
14:00 |
Inspection No.: |
456 |
|
Nil |
|
Follow Up Observations |
1. |
Water was removed together with the plastic
containers (Closed). |
2. |
Mud on the
footpath was cleared (Closed). |
3. |
Mud washed onto the footpath
was cleared (Closed). |
|
New Observations |
|
Nil. |
|
|
|
|
|
|
|
|
|
|
|
|
|
Nil |
Contract No. |
HY/2008/09 (Between Island House Interchange and
Ma Wo) |
Date: |
9
July 2014 |
Time: |
09:00 |
Inspection No.: |
457 |
|
Nil |
|
Follow Up
Observations |
|
|
|
Nil. |
|
|
|
|
|
|
|
New
Observations |
|
|
|
Nil. |
|
|
|
|
|
|
|
|
|
Nil |
Contract No. |
HY/2009/08 (Between Ma Wo and Tai Hang) |
Date: |
10
July 2014 |
Time: |
14:00 |
Inspection No.: |
458 |
|
Nil |
|
Follow Up Observations |
|
Nil. |
|
|
|
|
|
New Observations |
1. |
Stagnant water and general
refuse were observed on Bridge 18A. The Contractor should clear the stagnant
water to prevent mosquito breeding and clear the refuse to maintain site cleanliness. |
|
|
|
|
|
|
|
|
|
|
|
|
|
Nil |
Contract No. |
HY/2009/08 (Between Ma Wo and Tai Hang) |
Date: |
17
July 2014 |
Time: |
14:00 |
Inspection No.: |
459 |
|
Nil |
|
Follow Up Observations |
1. |
Stagnant water and general refuse were cleared on
Bridge 18A (Closed). |
|
|
|
|
|
New Observations |
2. |
General refuse was observed.
The Contractor should clear the general refuse to maintain site tidiness. |
3. |
Exposed
slope was observed. The Contractor should cover the exposed slope for
rainstorm protection by impervious sheeting. |
|
|
|
|
|
|
|
|
|
|
|
Nil |
Contract No. |
HY/2009/08 (Between Ma Wo and Tai Hang) |
Date: |
24
July 2014 |
Time: |
14:00 |
Inspection No.: |
460 |
|
Nil |
|
Follow Up Observations |
1. |
The
accumulated general refuse was cleared (Closed). |
2. |
Exposed slope was covered by tarpaulin sheets and
will be permanently covered by grass net (Closed). |
|
|
|
New Observations |
|
Nil. |
|
Reminders |
|
Exposed slopes were observed without dust
suppression measures. The Contractor was reminded to cover the slopes after
work for rainstorm protection. |
|
|
|
|
|
|
|
|
|
Nil |
Contract No. |
HY/2009/08 (Between Ma Wo and Tai Hang) |
Date: |
31
July 2014 |
Time: |
14:00 |
Inspection No.: |
461 |
|
Nil |
|
Follow Up Observations |
|
Nil. |
|
|
|
|
|
New Observations |
1. |
Open stockpiles were observed
without dust suppression measures. The Contractor should cover the stockpiles
with tarpaulin sheets or carry out equivalent dust suppression measures. |
2. |
Mud was observed on the
footpath. The Contractor should clear the mud regularly. |
|
|
|
|
|
|
|
|
|
|
|
Nil |