Site
Inspection Summary
Contract No. |
HY/2008/09 (Between Island House Interchange and
Ma Wo) |
Date: |
8
May 2014 |
Time: |
14:00 |
Inspection No.: |
439 |
|
Nil |
|
Follow Up
Observations |
|
|
|
Nil. |
|
|
|
|
|
|
|
New
Observations |
|
|
1. |
Open
stockpiles were observed at the top of NB9. The Contractor was reminded to
cover them with tarpaulin sheets, especially during rainstorm. |
|
|
|
|
|
|
|
|
|
Nil |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Contract No. |
HY/2009/08 (Between Ma Wo and Tai Hang) |
Date: |
8
May 2014 |
Time: |
14:00 |
Inspection No.: |
440 |
|
Nil |
|
Follow Up Observations |
1. |
The water
at the wheel-washing facilities was cleared (Closed). |
|
|
|
|
|
New Observations |
2. |
Stockpiles of dusty materials
were not covered entirely by impervious sheets on Tai Wo Service Road West.
The Contractor was reminded to cover them with tarpaulin sheets entirely. |
3. |
Open
stockpile at W74 was not covered with tarpaulin sheets. The Contractor was reminded
to cover the stockpile with tarpaulin sheets entirely. |
|
|
|
|
|
|
|
|
|
|
|
Nil |
Contract No. |
HY/2008/09 (Between Island House Interchange and
Ma Wo) |
Date: |
14
May 2014 |
Time: |
09:00 |
Inspection No.: |
441 |
|
Nil |
|
Follow Up
Observations |
|
|
1. |
Open stockpiles have been covered (Closed). |
|
|
|
|
|
|
|
New
Observations |
|
|
|
Nil. |
|
|
|
|
|
|
|
|
|
Nil |
Contract No. |
HY/2009/08 (Between Ma Wo and Tai Hang) |
Date: |
15
May 2014 |
Time: |
14:00 |
Inspection No.: |
442 |
|
Nil |
|
Follow Up Observations |
1. |
Stockpiles of dusty material were removed (Closed). |
2. |
Open stockpile was covered by tarpaulin sheet
(Closed). |
|
|
|
New Observations |
|
Nil. |
|
|
|
|
|
|
|
|
|
|
|
|
|
Nil |
Contract No. |
HY/2008/09 (Between Island House Interchange and
Ma Wo) |
Date: |
21 May 2014 |
Time: |
09:00 |
Inspection No.: |
443 |
|
Nil |
|
Follow Up
Observations |
|
|
|
Nil. |
|
|
|
|
|
|
|
New Observations |
|
|
|
Nil. |
|
|
|
|
|
|
|
|
|
Nil |
Contract No. |
HY/2009/08 (Between Ma Wo and Tai Hang) |
Date: |
22
May 2014 |
Time: |
14:00 |
Inspection No.: |
444 |
|
Nil |
|
Follow Up Observations |
|
Nil. |
|
|
|
|
|
New Observations |
1. |
Construction
waste was observed near Gate 11. The Contractor was reminded to clear the
waste t maintain site tidiness. |
|
|
|
|
|
|
|
|
|
|
|
|
|
Nil |
Contract No. |
HY/2008/09 (Between Island House Interchange and
Ma Wo) |
Date: |
28 May 2014 |
Time: |
09:00 |
Inspection No.: |
445 |
|
Nil |
|
Follow Up
Observations |
|
|
|
Nil. |
|
|
|
|
|
|
|
New
Observations |
|
|
|
Nil. |
|
|
|
|
|
|
|
|
|
Nil |
Contract No. |
HY/2009/08 (Between Ma Wo and Tai Hang) |
Date: |
29
May 2014 |
Time: |
14:00 |
Inspection No.: |
446 |
|
Nil |
|
Follow Up Observations |
1. |
Construction waste was cleared (Closed). |
|
|
|
|
|
New Observations |
2. |
General refuse was observed.
The Contractor should clear the refuse to maintain site tidiness. |
3. |
Muddy water
and sand were obseved near the drainge system in road. The Contractor should clear
the muddy water and sand, and prevent muddy water from entering the draingae
system by arranging sandbags or equivalent measures. |
4. |
Chemicals were observed on bar ground without
drip trays. The Contractor should provide drip tray to chemicals. |
|
|
|
|
|
|
|
|
|
Nil |