Site Inspection Summary

 

Inspection Information

Contract No.

HY/2008/09 (Between Island House Interchange and Ma Wo)

Date:

5 April 2013

Time:

9:15

Inspection No.:

325

 

Non-compliance

 

 

Nil

 

 

Observations

 

Follow Up Observation

 

 

 

 

 

Nil.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

New Observation

 

 

Nil.

 

 

 

 

 

 

 

Remarks

 

 

Nil

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Site Inspection Summary

 

Inspection Information

Contract No.

HY/2009/08 (Between Ma Wo and Tai Hang)

Date:

5 April 2013

Time:

14:15

Inspection No.:

326

 

Non-compliance

 

 

Nil

 

 

Observations

 

Follow Up Observations

1.

Oil stains on the ground had been removed. (Closed)

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

New Observation

 

 

Nil.

 

 

 

 

 

 

 

 

 

 

 

 

 

Remarks

 

 

Nil

 

 

 

 

 

 

 

 

 

 

 

 

 

Site Inspection Summary

 

Inspection Information

Contract No.

HY/2008/09 (Between Island House Interchange and Ma Wo)

Date:

10 April 2013

Time:

14:00

Inspection No.:

327

 

Non-compliance

 

 

Nil

 

 

Observations

 

Follow Up Observation

 

 

 

 

 

Nil.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

New Observation

 

1.

Cement bags at Area Gate 3 were exposed. The Contractor was reminded to cover the cement bags properly.

 

 

 

 

 

 

 

Remarks

 

 

Nil

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Site Inspection Summary

 

Inspection Information

Contract No.

HY/2009/08 (Between Ma Wo and Tai Hang)

Date:

11 April 2013

Time:

14:15

Inspection No.:

328

 

Non-compliance

 

 

Nil

 

 

Observations

 

Follow Up Observations

 

Nil.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

New Observation

 

1.

Construction wastes were placed near the retained trees at Area LB 2. The Contractor was reminded to remove the wastes and avoid disposing of the wastes near the retained trees.

 

 

 

 

 

 

 

 

 

 

 

 

 

Remarks

 

 

Nil

 

 

 

 

 

 

 

 

 

 

Site Inspection Summary

 

Inspection Information

Contract No.

HY/2008/09 (Between Island House Interchange and Ma Wo)

Date:

17 April 2013

Time:

9:15

Inspection No.:

329

 

Non-compliance

 

 

Nil

 

 

Observations

 

Follow Up Observation

 

 

 

 

1.

Cement bags at Area Gate 3 had been removed. (Closed)

 

 

 

 

 

 

 

 

 

 

 

 

 

 

New Observation

 

 

Nil.

 

 

 

 

 

 

 

Remarks

 

 

Nil

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Site Inspection Summary

 

Inspection Information

Contract No.

HY/2009/08 (Between Ma Wo and Tai Hang)

Date:

18 April 2013

Time:

14:15

Inspection No.:

330

 

Non-compliance

 

 

Nil

 

 

Observations

 

Follow Up Observations

1.

Construction wastes placed near the retained trees at Area LB 2 had been removed. (Closed)

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

New Observation

 

 

Nil.

 

 

 

 

 

 

 

 

 

 

 

 

 

Remarks

 

 

Nil

 

 

 

 

 

 

 

 

 

 

Site Inspection Summary

 

Inspection Information

Contract No.

HY/2008/09 (Between Island House Interchange and Ma Wo)

Date:

24 April 2013

Time:

9:15

Inspection No.:

331

 

Non-compliance

 

 

Nil

 

 

Observations

 

Follow Up Observation

 

 

 

 

 

Nil.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

New Observation

 

1.

Standing water was observed at Gate 3. The Contractor was reminded to remove the standing water to prevent mosquito breeding.

 

 

 

 

 

 

 

Remarks

 

 

Nil

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Site Inspection Summary

 

Inspection Information

Contract No.

HY/2009/08 (Between Ma Wo and Tai Hang)

Date:

25 April 2013

Time:

14:00

Inspection No.:

332

 

Non-compliance

 

 

Nil

 

 

Observations

 

Follow Up Observations

 

Nil.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

New Observation

 

1.

General refuse was dumped on bare ground at Area C. The Contractor was reminded to clear the general refuse regularly.

2.

General refuse was found dumped into the recycling bins. The Contractor was reminded to remove the general refuse and dump only the recylcing materials into the recycling bins.

 

 

 

 

 

 

 

 

 

 

 

Remarks

 

 

Nil