Site Inspection Summary

 

Inspection Information

Contract No.

HY/2008/09 (Between Island House Interchange and Ma Wo)

Date:

6 February 2013

Time:

14:00

Inspection No.:

309

 

Non-compliance

 

 

Nil

 

 

Observations

 

Follow Up Observation

 

 

 

 

1.

Broken concretes at Area NB17 had been removed. (Closed)

 

 

 

 

 

 

 

 

 

 

 

 

 

 

New Observation

 

2.

Insufficient mitigation measure was observed for an exposed slope at area TB1 West Abutment. The Contractor was reminded to cover the exposed slope by tarpaulin sheets properly.

 

 

 

 

 

 

 

Remarks

 

 

Nil

 

 

 

 

 

 

 

 

 

 

 

 

Site Inspection Summary

 

Inspection Information

Contract No.

HY/2009/08 (Between Ma Wo and Tai Hang)

Date:

7 February 2013

Time:

14:00

Inspection No.:

310

 

Non-compliance

 

 

Nil

 

 

Observations

 

Follow Up Observations

 

1.

 

Label had been provided for recycling bin of alminium’s can at Area NLKSA. (Closed)

 

 

 

 

 

 

2.

C&D wastes at Area NLKSA had been removed. (Closed)

 

 

 

 

 

 

 

 

 

 

 

 

 

New Observations

 

3.

Soil stockpiles were accumulated without cover at Area Bridge 15A North Ramp. The Contractor was reminded to cover the soil stockpiles.

4.

C&D wastes were not well sorted at Area Bridge 15A North Ramp. The Contractor was reminded to properly sort the C&D wastes.

 

 

 

 

 

 

 

 

 

 

 

Remarks

 

 

Nil

 

 

 

 

 

 

 

 

 

Site Inspection Summary

 

Inspection Information

Contract No.

HY/2008/09 (Between Island House Interchange and Ma Wo)

Date:

15 February 2013

Time:

9:30

Inspection No.:

311

 

Non-compliance

 

 

Nil

 

 

Observations

 

Follow Up Observation

 

 

 

 

1.

The exposed slope at area TB1 West Abutment had been covered. (Closed)

 

 

 

 

 

 

 

 

 

 

 

 

 

 

New Observation

 

 

Nil.

 

 

 

 

 

 

 

Remarks

 

 

Nil

 

 

 

 

 

 

 

 

 

 

 

 

Site Inspection Summary

 

Inspection Information

Contract No.

HY/2009/08 (Between Ma Wo and Tai Hang)

Date:

15 February 2013

Time:

14:00

Inspection No.:

312

 

Non-compliance

 

 

Nil

 

 

Observations

 

Follow Up Observations

 

1.

 

Soil stockpiles at Area Bridge 15A North Ramp had been covered. (Closed)

 

 

 

 

 

 

2.

C&D wastes at Area Bridge 15A North Ramp had been sorted. (Closed)

 

 

 

 

 

 

 

 

 

 

 

 

 

New Observation

 

 

Nil.

 

 

 

 

 

 

 

 

 

 

 

 

 

Remarks

 

 

Nil

 

 

 

 

 

 

 

 

 

Site Inspection Summary

 

Inspection Information

Contract No.

HY/2008/09 (Between Island House Interchange and Ma Wo)

Date:

20 February 2013

Time:

9:00

Inspection No.:

313

 

Non-compliance

 

 

Nil

 

 

Observations

 

Follow Up Observation

 

 

 

 

 

Nil.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

New Observation

 

1.

Mud trails were observed at Gate 33. The Contractor was reminded to implement preventive measures to avoid the spread of mud trails on the public road.

 

 

 

 

 

 

 

Remarks

 

 

Nil

 

 

 

 

 

 

 

 

 

 

 

 

Site Inspection Summary

 

Inspection Information

Contract No.

HY/2009/08 (Between Ma Wo and Tai Hang)

Date:

21 February 2013

Time:

14:00

Inspection No.:

314

 

Non-compliance

 

 

Nil

 

 

Observations

 

Follow Up Observations

 

 

Nil

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

New Observation

 

1.

General wastes were disposed near the river. The Contractor was reminded to clear the wastes.

 

 

 

 

 

 

 

 

 

 

 

 

 

Remarks

 

 

Nil

 

 

 

 

 

 

 

 

 

Site Inspection Summary

 

Inspection Information

Contract No.

HY/2008/09 (Between Island House Interchange and Ma Wo)

Date:

27 February 2013

Time:

9:00

Inspection No.:

315

 

Non-compliance

 

 

Nil

 

 

Observations

 

Follow Up Observation

 

 

 

 

1.

Mud trail outside site entrance was cleaned at once. The site entrance had been concrete paved to prevent dusty material from carrying out to public road. (Closed)

 

 

 

 

 

 

 

 

 

 

 

 

 

 

New Observation

 

 

Nil.

 

 

 

 

 

 

 

Remarks

 

 

Nil

 

 

 

 

 

 

 

 

 

 

 

Site Inspection Summary

 

Inspection Information

Contract No.

HY/2009/08 (Between Ma Wo and Tai Hang)

Date:

28 February 2013

Time:

14:00

Inspection No.:

316

 

Non-compliance

 

 

Nil

 

 

Observations

 

Follow Up Observations

1.

General wastes at area Bridge 12A were removed. (Closed)

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

New Observation

 

 

Nil.

 

 

 

 

 

 

 

 

 

 

 

 

 

Remarks

 

 

Nil