Appendix C - Implementation Schedule of Environmental Mitigation
Measures (EMIS)
Air Quality - Schedule of Recommended
Mitigation Measures
Impact |
Mitigation Measures |
Timing |
Implementation
Status |
Air
Quality during Construction |
¡P Restricting
heights from which materials are dropped, as far as practicable to minimize
the fugitive dust arising from unloading/loading. |
During
construction |
V |
¡P All
stockpiles of excavated materials or spoil of more than 50m3 shall
be enclosed, covered or dampened during dry or windy conditions. |
@ |
||
¡P Effective
water sprays shall be used to control potential dust emission sources such as
unpaved haul roads and active construction areas. |
V |
||
¡P All
spraying of materials and surfaces shall avoid excessive water usage. |
V |
||
¡P Vehicles
that have the potential to create dust while transporting materials shall be
covered, with the cover properly secured and extended over the edges of the
side and tail boards. |
V |
||
¡P Materials
shall be dampened, if necessary, before transportation. |
V |
||
¡P Travelling
speeds shall be controlled to reduce traffic induced dust dispersion and
resuspension within the site from the operating haul trucks. |
V |
||
¡P Vehicle
washing facilities shall be provided to minimize the quantity of material
deposited on public roads. |
@ |
Noise - Schedule of Recommended Mitigation
Measures
Impact |
Mitigation Measures |
Timing |
Implementation
Status |
Noise
during Construction |
¡P Use of
silenced plant or plant equipped with mufflers or dampers in substitute of
ordinary plant. |
During
construction |
V |
¡P Reduce
the number of equipment and their percentage on-time. |
V |
||
¡P 3.5 m and
5.5 m high temporary noise barrier at culvert construction work area (Figure
2a of the Environmental Permit). |
V |
||
¡P 3 m high
temporary noise barrier along the northern edge of Bridge 12 at ground level
(Figure 2b of the Environmental Permit). |
V |
||
¡P 2 m high
temporary noise barrier along the northern edge of Bridge 12 at bridge level
(Figure 2b of the Environmental Permit). |
In progress |
||
¡P 2.5 m
high temporary noise barrier along TaiWo Service Road West (Figure 2c of the
Environmental Permit). |
V |
||
¡P 3.5m high
temporary noise barrier along Tai Wo Services Road West near Tai Hang
(Figure2c of the Environmental Permit). |
In progress |
Water Quality - Schedule of Recommended
Mitigation Measures
Impact |
Mitigation Measures |
Timing |
Implementation
Status |
Water
quality during Construction |
Demolition and
reconstruction of bridges |
During
construction |
|
¡P Prevent
off-site migration through use of sheet piles. |
V |
||
¡P Minimize
duration of works as far as practical. |
V |
||
¡P All sewer
and drainage connections should be sealed to prevent debris, soil, sand, etc,
from entering public sewers/drains. |
V |
||
¡P Site
surface runoff should be settled to remove sand/silt before it is discharged
into the existing storm drains. |
V |
||
River training works |
|
||
¡P lnspection
and testing of water quality in the nullah on the Tai Po River. |
N/A |
||
Road Widening Works
and Earthworks |
|
||
¡P Wastewater
generated from any concrete batching washdown of equipment or similar
activities should be discharged into foul sewers, after the removal of
settable solids, and pH adjustment as necessary. All sewage discharges from
the study area should meet the TM standards and approval from EPD through the
licensing process is required. |
V |
||
¡P Sand
traps, oil interceptors and other pollution prevention installations should
be provided, properly cleaned and maintained. |
V |
||
¡P Runoff
from exposed working areas, unfinished slopes and from unlined temporary
channels should be directed to stilling basins and/or silt traps before
discharging to the drainage outfalls. |
V |
||
¡P Regular
inspections of stilling basins and/or silt traps are required to ensure that
sediment is not conveyed into the existing drainage system. |
V |
||
¡P Open
stockpiles should be covered with a tarpaulin cover. |
V |
||
¡P During
the wet season, any exposed top soils should be covered with a tarpaulin,
shotcreted or hydroseeded. |
V |
||
¡P Sand and
silt from wash-water from vehicle washing should be settled out before
discharging into storm drains. |
V |
||
¡P Fuels
should be stored in bunded areas such that spillage can be easily collected. |
V |
Waste - Schedule of Recommended Mitigation
Measures
Impact |
Mitigation Measures |
Timing |
Implementation
Status |
Waste
Management during Construction |
General Waste |
During
construction |
|
¡P Transport
of wastes off site as soon as possible. |
V |
||
¡P Maintenance
of accurate waste records |
V |
||
¡P Minimization
of waste generation for disposal (via reduction/recycling/re-use). |
V |
||
¡P No
on-site burning will be permitted. |
V |
||
¡P Use of
re-useable metal hoardings/signboards. |
V |
||
Vegetation from site
clearance |
|
||
¡P Segregation
of materials to facilitate disposal. |
V |
||
¡P Mulching
to reduce bulk and where possible review opportunities for the possible
beneficial use within landscaping areas. |
V |
||
Demolition Wastes |
|
||
¡P Segregation
of materials to facilitate disposal. |
V |
||
¡P Appropriate
stockpile management. |
V |
||
Excavated Materials |
|
||
¡P Segregation
of materials to facilitate disposal / reuse. |
V |
||
¡P Appropriate
stockpile management. |
V |
||
¡P Re-use of
excavated material on or off site (where possible). |
V |
||
¡P Special
handling and disposal procedures in the event that contaminated materials are
excavated. |
N/A |
||
Construction Wastes |
|
||
¡P Segregation
of materials to facilitate recycling/reuse (within designated area in
appropriate containers/stockpiles). |
V |
||
¡P Appropriate
stockpile management. |
V |
||
¡P Planning
to reduce over ordering and waste generation. |
V |
||
¡P Recycling
and re-use of materials where possible (e.g. metal, wood from formwork) |
V |
||
¡P For
material which cannot be re-used/recycled, collection should be carried out by
an approved waste contractor for landfill disposal. |
V |
||
Bentonite Slurries |
|
||
¡P Bentonite
slurries should be reused as far as possible. |
N/A |
||
¡P Disposal
in accordance with Practice Note For
Professional Persons ProPECC PN 1/94. |
N/A |
||
Chemical Wastes |
|
||
¡P Storage
within locked, covered and bunded area. |
V |
||
¡P The
storage area shall not be located adjacent to sensitive receivers e.g.
drains. |
V |
||
¡P Minimize
waste production and recycle oils/solvents where possible. |
V |
||
¡P A spill
response procedure shall be in place and absorption material available for
minor spillages. |
V |
||
¡P Use
appropriate and labelled containers. |
V |
||
¡P Educate
site workers on site cleanliness/waste management procedures. |
@ |
||
¡P lf
chemical wastes are to be generated, the contractor must register with EPD as
a Chemical Waste Producer. |
V |
||
¡P The
chemical wastes shall be collected by a licensed chemical waste collector. |
V |
||
Municipal Wastes |
|
||
¡P Waste
shall be stored within a temporary refuse collection facility, in appropriate
containers prior to collection and disposal. |
V |
||
¡P Regular,
daily collections are required by an approved waste collector. |
V |
Ecology - Schedule of Recommended Mitigation
Measures
Impact |
Mitigation Measures |
Timing |
Implementation
Status |
Ecology
during Construction |
Accurate Delineation
of Works Area |
During
construction |
|
¡P Boundaries
of proposed works areas shall be clearly identified and separated from
external areas by a physical barrier to prevent encroachment of adjacent
habitats. |
V |
||
¡P lndividual
trees which fall within the works areas but which work plans show do not
require removal are to be retained and fenced off to maximize protection. |
V |
||
Vegetation Clearance |
|
||
¡P No fires
shall be lit within the works area for the purpose of burning cleared
vegetation. |
V |
||
¡P The
Contractor shall give consideration to mulching the cleared vegetation for
recycling within the works area / adjacent land. |
V |
||
Dust generation |
|
||
¡P Vehicle
washing facilities to be provided at every discernible or designated vehicle
exit point; |
V |
||
¡P All
temporary site access roads shall be sprayed with water to suppress dust as
necessary; |
V |
||
¡P All dusty
materials should be sprayed with water immediately prior to any handling; and |
V |
||
¡P All
debris should be covered entirely by impervious sheeting or stored in a
sheltered debris collection area. |
V |
||
Surface Run-off |
|
||
¡P Bund and
cover stockpiles to avoid run-off; |
V |
||
¡P Channel
any run-off through a system of oil, grease and sediment / silt traps and
reuse water on site where ever practical; |
V |
||
¡P All
vehicle maintenance to be undertaken within a bunded area; and |
N/A |
||
¡P Maximize
vegetation retention on-site to maximize absorption (minimize transport). |
V |
Landscape and Visual Impact - Schedule of
Recommended Mitigation Measures
Impact |
Mitigation Measures |
Timing |
Implementation
Status |
Landscape
and Visual Impact during Construction |
Preservation of
Existing Vegetation |
During
construction |
|
¡P Trees
identified for retention within the project limit would be protected during
the works |
V |
||
¡P The tree
transplanting and planting works shall be implemented by approved Landscape
Contractors |
V |
||
Temporary Works
Areas |
|
||
¡P Where
feasible the works areas would be screened using hoarding and existing
vegetation would be retained where possible to reduce the landscape and
visual impacts arising from the construction activity. The landscape of these
works areas would be restored following the completion of the construction
phase. |
V |
||
Hoarding |
|
||
¡P A
hoarding would be erected where practicable in the most visually sensitive
locations to screen the temporary construction works from the local VSR's. |
V |
||
Top Soils |
|
||
¡P The works
will result in disturbance to extensive areas of topsoil. Topsoil worthy of
retention should be stockpiled for use following completion of the civil
engineering works. lt should either be temporarily vegetated with hydroseeded
grass or turned over on a regular basis. |
N/A |
||
Protection of Important
Landscape Features |
|
||
¡P lmportant
features such as temples, lsland House and kilns within the study area,
although remote from the proposed works retained and adequately protected. |
V |
Legend: V = implemented;
x = not implemented;
@
= partially implemented;
N/A
= not applicable - No such work was undertaken or no such material was used on
site.