Site
Inspection Summary
Contract No. |
HY/2008/09 (Between Island House
Interchange and Ma Wo) |
Date: |
5 September
2012 |
Time: |
9:00 |
Inspection No.: |
265 |
|
Nil |
|
Follow
Up Observation |
|
|
1. |
Valid noise emission label for air compressor at
Bridge 10A had been displayed. (Closed) |
|
|
|
|
|
|
|
New
Observation |
|
Nil. |
|
|
|
Nil |
Site
Inspection Summary
Contract No. |
HY/2009/08 (Between Ma Wo and Tai Hang) |
Date: |
6 September 2012 |
Time: |
14:00 |
Inspection No.: |
266 |
|
Nil |
|
Follow Up
Observation |
1. |
General refuse, papers, plastic bottles and aluminum cans at Area NLKB
SA had been sorted properly and labels had been also provided to the recycling
bins on site. (Closed) |
|
|
|
|
|
New Observation Nil. |
|
|
|
|
|
|
|
|
|
|
|
Nil |
Site
Inspection Summary
Contract No. |
HY/2009/08 (Between Ma Wo and Tai Hang) |
Date: |
13 September 2012 |
Time: |
14:00 |
Inspection No.: |
267 |
|
Nil |
|
Follow Up
Observation |
|
Nil. |
|
|
|
|
1. |
New Observation General refuse were accumulated at Gate 30 and
LB3 WA. The Contractor was reminded to dispose the general refuse more
frequently and provide sufficient receptacles for general refuse collection
on site. The Contractor was also reminded to maintain the site cleanness and
tidiness. |
|
|
|
|
|
|
|
|
|
|
|
Nil |
Site
Inspection Summary
Contract No. |
HY/2008/09 (Between Island House
Interchange and Ma Wo) |
Date: |
14 September
2012 |
Time: |
14:30 |
Inspection No.: |
268 |
|
Nil |
|
Follow
Up Observation |
|
|
|
Nil |
|
|
|
|
|
|
|
New
Observations |
1. |
Stagnant water was accumulated at Area NB16. The
Contractor was reminded to remove the stagnant water regularly. The
Contractor was also recommended to maintain the drainage system properly. |
2. |
No drip tray provided for a generator at Area
NB16 was observed and oil leakage was also found from the generator. The
Contractor was reminded to provide drip tray for the generator to retain any
leaked oil. Oil stain on ground should be removed and disposed as chemical
wastes. |
|
|
|
|
|
Nil |
Site
Inspection Summary
Contract No. |
HY/2008/09 (Between Island House
Interchange and Ma Wo) |
Date: |
19 September
2012 |
Time: |
9:00 |
Inspection No.: |
269 |
|
Nil |
|
Follow
Up Observations |
|
|
1. |
Stagnant water at Area NB16 had been removed.
(Closed) |
2. |
Oil
stains on ground at Area NB16 had been cleared and the generator at Area NB16
had also been removed from the site. (Closed) |
|
|
|
|
|
New
Observation |
|
Nil. |
|
|
|
|
|
Nil |
Site
Inspection Summary
Contract No. |
HY/2009/08 (Between Ma Wo and Tai Hang) |
Date: |
20 September 2012 |
Time: |
14:00 |
Inspection No.: |
270 |
|
Nil |
|
Follow Up
Observation |
1. |
General refuse at Gate 30 and LB3 WA had been
removed. (Closed) |
|
|
|
|
2. |
New Observation Oil drum was observed placed on ground at Area
NLKP9 without drip tray. The Contractor was reminded to provide drip tray or
equivalent measures for all oil drums on site to avoid any oil leakage
occurred. |
|
|
|
|
|
|
|
|
|
|
|
Nil |
Site
Inspection Summary
Contract No. |
HY/2008/09 (Between Island House
Interchange and Ma Wo) |
Date: |
26 September
2012 |
Time: |
9:00 |
Inspection No.: |
271 |
|
Nil |
|
Follow
Up Observation |
|
|
|
Nil. |
|
|
|
|
|
|
|
New
Observations |
1. |
Broken sandbags were observed near the entrance
of Gate 26. The Contractor was reminded to replace all broken sandbags and
maintain the sandbag bunding properly to prevent surface runoff from
construction work flowing outside the work area and discharging to public drain.
Silt accumulated near the broken sandbags should be removed as soon as
possible to avoid any silty water discharging to nearby gully. The Contractor
was also recommended to review and maintain the effectiveness of sandbag
bunding regularly. |
2. |
Oil drums were observed placed on ground without
drip tray at New Banyan West Bridge. The Contractor was reminded to provide
drip trays for all oil drums on site to prevent oil leakage. |
|
|
|
|
|
Nil |
Site
Inspection Summary
Contract No. |
HY/2009/08 (Between Ma Wo and Tai Hang) |
Date: |
27 September 2012 |
Time: |
14:00 |
Inspection No.: |
272 |
|
Nil |
|
Follow Up
Observation |
1. |
Oil drum at Area NLKP9 had been removed. (Closed) |
|
|
|
|
2. |
New Observation Oily water was accumulated inside the drip trays
at Area W45. The Contractor was reminded to remove the oily water and handle
it chemical waste. The Contractor was recommended to remove the oily water /
leaked oil inside the drip trays regularly to prevent any overflow. |
|
|
|
|
|
|
|
|
|
|
|
Nil |