Site
Inspection Summary
Contract No. |
HY/2008/09 (Between Island House
Interchange and Ma Wo) |
Date: |
1 August
2012 |
Time: |
9:00 |
Inspection No.: |
255 |
|
Nil |
|
Follow
Up Observation |
|
|
|
Nil. |
|
|
|
New
Observations |
1. |
Broken sandbags were observed at the site
boundary of Gate 26. The Contractor was reminded to replace the broken
sandbags as soon as possible. The Contractor was recommended to review the
effectiveness of bunds/sand bags/channels at the site boundaries, soil
stockpile area and works areas regularly. |
2. |
Chemical containers were observed placed on
ground without drip trays at Gate 26. The Contractor was reminded to provide
drip trays or equivalent measure for all chemical containers to intercept any
chemical leakage occurred on site. |
|
Nil |
Site
Inspection Summary
Contract No. |
HY/2009/08 (Between Ma Wo and Tai Hang) |
Date: |
2 August 2012 |
Time: |
14:00 |
Inspection No.: |
256 |
|
Nil |
|
Follow Up
Observations |
1. |
Water filtration system had been set up at the
end of the u-channel at NB42 and the exposed slopes had been also covered by
tarpaulin sheet. No waste water was observed running off and discharging to
the public drain at NB42. However, the Contractor was recommended to maintain
the drainage system regularly and properly. (Closed) |
2. |
Cans and bottles in site area at NB42 had been removed. (Closed) |
|
|
|
New Observation Nil |
3. |
Reminder The
Contractor was reminded to provide proper mitigation measure to prevent any
oil stain leakage from the metal materials due to rainfall. |
|
Nil |
Site
Inspection Summary
Contract No. |
HY/2009/08 (Between Ma Wo and Tai Hang) |
Date: |
8 August 2012 |
Time: |
9:00 |
Inspection No.: |
257 |
|
Nil |
|
Follow Up
Observation |
|
Nil |
|
|
|
|
1. |
New Observations Mud and broken sandbags were observed on road at
Gate 40. The Contractor was reminded to remove the mud and replace the broken
sandbags as soon as possible to prevent any muddy water runoff from the
construction work area to the public drain due to rainfall. The Contractor
was recommended to review the effectiveness of sandbags regularly. |
2. |
Mitigation measure
for exposed slope at W50 was observed insufficient. The Contractor was
reminded to cover the exposed slope properly to prevent any surface runoff to
the nearby public drain. |
3. |
Stagnant water was
accumulated inside the drip tray of generator at W35A. The Contractor was
reminded to clear the stagnant water and handle it as chemical waste. The
Contractor was also reminded to remove the stagnant water inside the drip
trays regularly to prevent any overflow occurred. The Contractor was
recommended to provide skirt curtains for drip trays to prevent rainy water
accumulated inside the drip tray during rainfall. |
|
|
|
|
|
|
|
Nil |
Site
Inspection Summary
Contract No. |
HY/2008/09 (Between Island House
Interchange and Ma Wo) |
Date: |
9 August
2012 |
Time: |
14:00 |
Inspection No.: |
258 |
|
Nil |
|
Follow
Up Observations |
|
|
1. |
Broken sandbags at the site boundary of Gate 26
had been replaced. However, the Contractor was recommended to review the
effectiveness of bunds/sand bags/channels at the site boundaries, soil
stockpile area and works areas regularly. (Closed) |
2. |
Chemical
containers at Gate 26 had been removed. (Closed) |
|
|
|
|
|
New
Observation |
3. |
Stagnant water was accumulated in receiving pit
and drip tray of oil drum at TB2 respectively. The Contractor was reminded to
remove the stagnant water in the receiving pit more frequently. The
Contractor was also reminded to remove the stagnant water inside the drip
tray as soon as possible and handle it as chemical wastes. |
|
|
|
Nil |
Site
Inspection Summary
Contract No. |
HY/2008/09 (Between Island House
Interchange and Ma Wo) |
Date: |
15 August
2012 |
Time: |
9:00 |
Inspection No.: |
259 |
|
Nil |
|
Follow
Up Observation |
|
|
1. |
Stagnant water in receiving pit and drip tray of
oil drum at TB2 had been removed. (Closed) |
|
|
|
|
|
|
|
New
Observation |
|
Nil. |
|
|
|
Nil |
Site
Inspection Summary
Contract No. |
HY/2009/08 (Between Ma Wo and Tai Hang) |
Date: |
16 August 2012 |
Time: |
14:00 |
Inspection No.: |
260 |
|
Nil |
|
Follow Up
Observations |
1. |
Mud on road at Gate 40 had been removed and broken sandbags at Gate 40
had been replaced. (Closed) |
|
|
2. |
The exposed slope had been
properly covered by tarpaulin. (Closed) |
|
|
3. |
Stagnant water
inside the drip tray of generator at W35A had been removed. (Closed) |
|
|
4. |
New Observation Oil drum and chemical containers were placed on
ground at Gate 16 without drip trays. The Contractor was reminded to provide
drip trays for all oil drums and chemical containers to intercept any oil
leakage. |
|
|
|
|
|
|
|
|
|
|
|
Nil |
Site
Inspection Summary
Contract No. |
HY/2008/09 (Between Island House
Interchange and Ma Wo) |
Date: |
22 August
2012 |
Time: |
9:00 |
Inspection No.: |
261 |
|
Nil |
|
Follow
Up Observation |
|
|
|
Nil |
|
|
|
|
|
|
|
New
Observation |
1. |
Chemical containers were observed placed on
ground at Gate 25 without drip tray. The Contractor was reminded to provide
drip tray for all oil drums / chemical containers to prevent any oil /
chemical leakage occurred. |
|
|
|
Nil |
Site
Inspection Summary
Contract No. |
HY/2009/08 (Between Ma Wo and Tai Hang) |
Date: |
23 August 2012 |
Time: |
14:00 |
Inspection No.: |
262 |
|
Nil |
|
Follow Up
Observation |
1. |
Oil drum and chemical containers at Gate 16 had been removed. (Closed) |
|
|
|
|
|
New Observation Nil. |
|
|
|
|
|
|
|
|
|
|
|
Nil |
Site
Inspection Summary
Contract No. |
HY/2008/09 (Between Island House
Interchange and Ma Wo) |
Date: |
29 August
2012 |
Time: |
9:00 |
Inspection No.: |
263 |
|
Nil |
|
Follow
Up Observation |
|
|
1. |
Drip tray had been provided for chemical
containers at Gate 25. (Closed) |
|
|
|
|
|
|
|
New
Observation |
2. |
Valid noise emission label for air compressor at
Bridge 10A was observed missing. The Contractor was reminded to display a
valid noise emission label for the air compressor during operation. |
|
|
|
Nil |
Site
Inspection Summary
Contract No. |
HY/2009/08 (Between Ma Wo and Tai Hang) |
Date: |
30 August 2012 |
Time: |
14:00 |
Inspection No.: |
264 |
|
Nil |
|
Follow Up
Observation |
|
Nil. |
|
|
|
|
1. |
New Observation The Contractor was reminded to sort the general
refuse, paper, plastic bottles and aluminum cans at Area NLKB SA properly.
The Contractor was also reminded to provide labels for all recycling bins on
site. |
|
|
|
|
|
|
|
|
|
|
|
Nil |