Site Inspection Summary

 

Inspection Information

Contract No.

HY/2009/08 (Between Ma Wo and Tai Hang)

Date:

05 July 2012

Time:

14:00

Inspection No.:

247

 

Non-compliance

 

 

Nil

 

 

Observations

 

Follow Up Observations

 

1.

 

 

2.

 

 

Cement on ground in the works area and on the access road at Bridge 15A were sprayed with water. (Closed)

 

Stagnant water accumulated inside the gullies and tyres on the bridge deck at Bridge 15A were removed. (Closed)

 

 

 

3.

 

 

4.

New Observations

 

Vegetation wastes were found accumulated along the site boundary at W35A. The Contractor was reminded to clear up the vegetation wastes to keep the site in a tidy condition.

 

Recyclable waste such as wood was found mixing with general refuse and construction material inside the waste skip at W38. The contractor was reminded to sort out the recyclable waste and clear the waste skip regularly.

 

 

 

 

Remarks

 

 

Nil

 

 


Site Inspection Summary

 

Inspection Information

Contract No.

HY/2008/09 (Between Island House Interchange and Ma Wo)

Date:

06 July 2012

Time:

14:00

Inspection No.:

248

 

Non-compliance

 

 

Nil

 

 

Observations

 

Follow Up Observation

 

 

1.

Exposed slopes at NBWNA were covered up by tarpaulin sheet completely. (Closed)

 

 

 

 

New Observation

 

2.

Stagnant water was found accumulated inside the excavation area near W8 Bay 2-3 and inside the drip tray at NB16. The Contractor was reminded to remove the stagnant water and dispose of as chemical waste.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Remarks

 

 

Nil

 

 


Site Inspection Summary

 

Inspection Information

Contract No.

HY/2008/09 (Between Island House Interchange and Ma Wo)

Date:

11 July 2012

Time:

9:00

Inspection No.:

249

 

Non-compliance

 

 

Nil

 

 

Observations

 

Follow Up Observation

 

 

1.

Stagnant water accumulated inside the excavation area near W8 Bay 2-3 and inside the drip tray at NB16 were removed. (Closed)

 

 

 

 

New Observation

 

 

Nil.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Remarks

 

 

Nil

 

 


Site Inspection Summary

 

Inspection Information

Contract No.

HY/2009/08 (Between Ma Wo and Tai Hang)

Date:

12 July 2012

Time:

14:00

Inspection No.:

250

 

Non-compliance

 

 

Nil

 

 

Observations

 

Follow Up Observations

 

1.

 

2.

 

 

Vegetation wastes accumulated along the site boundary at W35A were cleared. (Closed)

 

Recyclable waste inside the waste skip at W38 was removed. (Closed)

 

 

 

3.

 

 

New Observation

 

General refuse and C&D materials were observed near the u-channel at S20. The Contractor was reminded to remove the general refuse and C&D materials from the u-channel and properly maintain the drainage system on-site.

 

 

 

Remarks

 

 

Nil

 


Site Inspection Summary

 

Inspection Information

Contract No.

HY/2008/09 (Between Island House Interchange and Ma Wo)

Date:

18 July 2012

Time:

9:00

Inspection No.:

251

 

Non-compliance

 

 

Nil

 

 

Observations

 

Follow Up Observation

 

 

 

Nil.

 

 

 

 

New Observation

 

 

Nil.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Remarks

 

 

Nil

 

 

 

 

 

 

 

 

 

 

Site Inspection Summary

 

Inspection Information

Contract No.

HY/2009/08 (Between Ma Wo and Tai Hang)

Date:

19 July 2012

Time:

14:00

Inspection No.:

252

 

Non-compliance

 

 

Nil

 

 

Observations

 

Follow Up Observations

 

1.

 

 

General refuse and C&D materials near the u-channel at S20 were removed. (Closed)

 

 

 

2.

 

 

New Observation

 

Substandard run-off was found discharging to the public drainage at NB42. The Contractor was reminded to properly maintain and review the temporary drainage systems provided within works area and ensure that run-off was properly desilted prior to discharging to public drains. Any untreated run-off should be avoided from overflowing to public drains.

 

 

 

Remarks

 

 

Nil

 


Site Inspection Summary

 

Inspection Information

Contract No.

HY/2008/09 (Between Island House Interchange and Ma Wo)

Date:

25 July 2012

Time:

9:00

Inspection No.:

253

 

Non-compliance

 

 

Nil

 

 

Observations

 

Follow Up Observation

 

 

 

Nil.

 

 

 

 

New Observation

 

 

Nil.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Remarks

 

 

Nil

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Site Inspection Summary

 

Inspection Information

Contract No.

HY/2009/08 (Between Ma Wo and Tai Hang)

Date:

26 July 2012

Time:

14:00

Inspection No.:

254

 

Non-compliance

 

 

Nil

 

 

Observations

 

Follow Up Observation

 

1.

 

 

Untreated waste water was still observed running off and discharging to the public drain at NB42. The Contractor was reminded to enhance the drainage system properly and avoid any untreated water running off from site area and discharging to public drains. (Follow-up)

 

 

 

 

 

2.

 

 

New Observation

 

Cans and bottles were observed in site area at NB42. The Contractor was reminded to remove the cans and bottles regularly. The Contractor was also reminded to maintain the site cleanliness and tidiness.

 

 

 

Remarks

 

 

Nil