Site
Inspection Summary
Contract No. |
HY/2008/09 (Between Island House
Interchange and Ma Wo) |
Date: |
2
May 2012 |
Time: |
9:00 |
Inspection No.: |
229 |
|
Nil |
|
Follow
Up Observation |
|
|
|
Nil. |
|
New
Observation |
|
Nil. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Nil |
Site
Inspection Summary
Contract No. |
HY/2009/08 (Between Ma Wo and Tai Hang) |
Date: |
3 May 2012 |
Time: |
14:00 |
Inspection No.: |
230 |
|
Nil |
|
Follow
Up Observations |
|
|
1. 2. |
Stagnant water accumulated inside the drip trays of
chemical contianers on Lam Kam Bridge Pier 2 was cleared. (Closed) Construction waste accumulated on Lam Kam Bridge was cleared. (Closed) |
|
New
Observation |
|
Nil. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Nil |
Site
Inspection Summary
Contract No. |
HY/2009/08 (Between Ma Wo and Tai Hang) |
Date: |
9 May 2012 |
Time: |
14:00 |
Inspection No.: |
231 |
|
Nil |
|
Follow
Up Observation |
|
Nil. |
|
New
Observation |
1. |
Construction material was found placed
near the retained tree at NB44. The Contractor was reminded to remove the
construction material and provide proper protective measure to the retained
tree. |
|
|
|
|
|
|
|
|
|
|
|
|
|
Nil |
Site
Inspection Summary
Contract No. |
HY/2008/09 (Between Island House
Interchange and Ma Wo) |
Date: |
10
May 2012 |
Time: |
9:00 |
Inspection No.: |
232 |
|
Nil |
|
Follow
Up Observations |
|
|
|
Nil. |
|
|
|
|
|
New
Observations |
1. 2. |
Oil stains were found on ground near the breaking
tip of breaker under Bridge 11 near Gate 4. The Contractor was reminded to
clear the oil stains and provide tarpaulin sheet to the breaking tip to
retain oil leakage. Mud was found accumulated inside the u-channel at
Wall 8. The Contractor was reminded to clear the mud inside the u-channel. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Nil |
Site
Inspection Summary
Contract No. |
HY/2008/09 (Between Island House
Interchange and Ma Wo) |
Date: |
16
May 2012 |
Time: |
9:00 |
Inspection No.: |
233 |
|
Nil |
|
Follow
Up Observation |
|
|
1. 2. |
Oil stains on ground near the breaking tip of breaker were cleared and
coverage of tarpaulin sheet was provided to the breaking tip to retain oil
leakage under Bridge 11 near Gate 4. (Closed) Mud accumulated inside the u-channel at Wall 8
was cleared. (Closed) |
|
Mud accumulated inside the u-channel at Wall 8
was cleared. (Closed) |
|
New
Observations |
3. 4. |
Mud trails were observed at the site entrance in Gate 44. The
Contractor should clear the mud trails on the public road. The absorptive material wrapping to the breaking tip of the breakers
working in works area were found improper at Gate 44. The Contractor should
provide proper absorptive material wrapping to the breaking tips of the
breakers working in works area to minimize the noise impact. |
|
|
|
|
|
|
|
Nil |
Site
Inspection Summary
Contract No. |
HY/2009/08 (Between Ma Wo and Tai Hang) |
Date: |
17 May 2012 |
Time: |
9:00 |
Inspection No.: |
234 |
|
Nil |
|
Follow
Up Observations |
|
|
1. |
Construction material placed near the retained tree
at NB44 was removed and protective measure was
provided for the retained tree. (Closed) |
|
New
Observations |
2. 3. 4. |
Breaking tip of breaker was
found placed on bare ground at S38. The Contractor was reminded to place the
breaking tip onto the tarpaulin sheet to avoid the oil leaked from the
breaking tip to the ground. Mud trails were observed on
ground at the site entrance at S37. The Contractor should review and maintain
the wheel washing facilities provided at works area regularly to ensure the
deposited silt on vehicles’ wheels and bodies was washed off effectively. Mus
trails on the piblic road should be cleared. Accumulation of silty water was observed inside
the wheel washing bay at W71. The Contractor was reminded to clear the
deposited silt inside the wheel washing bay regularly and maintain the wheel
washing facilities properly. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Nil |
Site
Inspection Summary
Contract No. |
HY/2008/09 (Between Island House
Interchange and Ma Wo) |
Date: |
23
May 2012 |
Time: |
9:00 |
Inspection No.: |
235 |
|
Nil |
|
Follow
Up Observation |
1. 2. |
Mud trails at the site entrance at Gate 44 were
cleared. High pressure water jet was provided at the site entrance to remove
any dusty materials from their bodies and wheels before leaving construction
site. A water truck was arranged to clean the site entrance regularly. (Closed) Absorptive
material wrapping was provided to the breaking tip of the breaker worked at
Gate 44. (Closed) |
|
|
|
New
Observations |
|
Nil. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Nil |
Site
Inspection Summary
Contract No. |
HY/2009/08 (Between Ma Wo and Tai Hang) |
Date: |
24 May 2012 |
Time: |
14:00 |
Inspection No.: |
236 |
|
Nil |
|
Follow
Up Observations |
|
|
1. 2. 3 |
Breaking tip of breaker placed on bare ground at S38
was placed on tarpaulin sheet. (Closed) Mud trails on ground at the site entrance at S37 were cleared. The
Contractor was reminded to review and maintain the wheel washing facilities
provided at works area regularly to ensure the deposited silt on vehicles’
wheels and bodies was washed off effectively. (Closed) Silty water inside the wheel washing bay at W71 was cleared. However, the Contractor should clear
the deposited silt inside the wheel washing bay regularly and maintain
the wheel washing facilities properly. (Follow-up) |
|
New
Observations |
4. |
Some leaves were observed inside the u-channel at
access to W35A. The Contractor was reminded to remove the leaves inside the
drainage channel to maintain the drainage system properly. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Nil |
Site
Inspection Summary
Contract No. |
HY/2008/09 (Between Island House
Interchange and Ma Wo) |
Date: |
30
May 2012 |
Time: |
9:00 |
Inspection No.: |
237 |
|
Nil |
|
Follow
Up Observations |
|
|
|
Nil. |
|
New
Observations |
1. 2. |
Muddy water was found accumulated inside the sump pit at NB20. The
Contractor was reminded to clear the muddy water to avoid any substandard
water flowing outside the works area. Cement water was found accumulated inside the u-channel at Bridge 10
East Abutment. The Contractor was reminded to clear the cement water and deposited
cement inside the u-channel. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Nil |
Site
Inspection Summary
Contract No. |
HY/2009/08 (Between Ma Wo and Tai Hang) |
Date: |
31 May 2012 |
Time: |
14:00 |
Inspection No.: |
238 |
|
Nil |
|
Follow
Up Observations |
|
|
1. 2. |
Deposited silt inside the wheel washing bay at W71 was cleared. (Closed) Leaves inside the u-channel at access to W35A were removed. (Closed) |
|
New
Observations |
3. |
Broken sand bags were observed placed on ground
near the public drainage at Bridge 12A. The Contractor was reminded to
replace the broken sand bags on ground. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Nil |