Widening of Tolo Highway / Fanling Highway (Stage 1) Between Island House Interchange and Tai Hang - Investigation
Impact Monitoring and Audit Schedule for April 2012
Sunday Monday Tuesday Wednesday Thursday Friday Saturday
1-Apr 2-Apr 3-Apr 4-Apr 5-Apr 6-Apr 7-Apr
             
    24-hour TSP Public Holiday Site inspection Public Holiday Public Holiday
    1-hour TSP & Noise   (Contract 1 & 2)    
                   
8-Apr 9-Apr 10-Apr 11-Apr 12-Apr 13-Apr 14-Apr
             
  Public Holiday 24-hour TSP Site inspection   Site inspection 24-hour TSP
    1-hour TSP (Contract 2)   (Contract 1) 1-hour TSP & Noise
                 
15-Apr 16-Apr 17-Apr 18-Apr 19-Apr 20-Apr 21-Apr
             
      Site inspection Site inspection 24-hour TSP  
      (Contract 1) (Contract 2) 1-hour TSP & Noise  
               
22-Apr 23-Apr 24-Apr 25-Apr 26-Apr 27-Apr 28-Apr
        Site inspection    
      Site inspection (Contract 2)   Public Holiday
      (Contract 1) 24-hour TSP    
          1-hour TSP & Noise      
29-Apr 30-Apr          
             
             
             
               
Widening of Tolo Highway / Fanling Highway (Stage 1) Between Island House Interchange and Tai Hang - Investigation
Tentative Impact Monitoring and Audit Schedule for May 2012
Sunday Monday Tuesday Wednesday Thursday Friday Saturday
    1-May 2-May 3-May 4-May 5-May
      Site inspection      
    Public Holiday (Contract 1) Site inspection    
      24-hour TSP (Contract 2)    
        1-hour TSP & Noise      
6-May 7-May 8-May 9-May 10-May 11-May 12-May
             
    24-hour TSP Site inspection Site inspection    
    1-hour TSP & Noise (Contract 2) (Contract 1)    
               
13-May 14-May 15-May 16-May 17-May 18-May 19-May
             
  24-hour TSP   Site inspection Site inspection   24-hour TSP
  1-hour TSP & Noise   (Contract 1) (Contract 2)   1-hour TSP
               
20-May 21-May 22-May 23-May 24-May 25-May 26-May
             
      Site inspection Site inspection 24-hour TSP  
      (Contract 1) (Contract 2) 1-hour TSP & Noise  
               
27-May 28-May 29-May 30-May 31-May    
        Site inspection    
      Site inspection (Contract 2)    
      (Contract 1) 24-hour TSP    
          1-hour TSP & Noise    
The schedule is subject to change due to unforeseeable circumstances (e.g. adverse weather, etc)