Appendix L

Statistics on Complaints, Notifications of Summons and Successful Prosecutions

 

Date Received

Subject

Status

Total no. followed up by ET in this month

Total no. followed up by ET since project commencement 

Environmental complaints

22 and 29 December 2011

Dust emission from construction site of the Tolo Highway widening works near Ma Wo on 22 December 2011, subsequently, the complainant made another call on 29 December 2011 regarding the same issue.

Closed

2

15

23 and 31 December 2011

The complainant expressed that noise was generated from the construction site of Widening of Tolo Highway near Ma Wo Tsuen. The complainant made another call on 31 December 2011 regarding the same issue.

Closed

Notification of summons

-

-

-

0

0

Successful Prosecutions

-

-

-

0

0