Site Inspection Summary

 

Inspection Information

Contract No.

HY/2009/08 (Between Ma Wo and Tai Hang)

Date:

01 December 2011

Time:

14:00

Inspection No.:

186

 

Non-compliance

 

 

Nil

 

 

Observations

 

Follow Up Observation

 

 

1.

Exposed slope near Gate 30 was sprayed with water. (Closed)

 

 

 

 

 

 

 

 

 

 

 

 

 

New Observation

 

2.

 

 

3.

 

 

 

4.

 

Oil mixing with water was found underneath the vehicle at Bridge 18.  The Contractor was reminded to clear the oily mixture.

 

C&D materials, vegetation and excavated materials waste were found accumulated on ground at Bridge 18 north abatement. The Contractor should clear up the C&D materials, vegetation and excavated materials waste and sort out the recyclable waste to keep the site in a tidy condition.

 

Smoke was observed emitting from the roller at W72. The Contractor was requested to repair and maintain the plant on site properly.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Remarks

 

 

Nil

 

 


Site Inspection Summary

 

Inspection Information

Contract No.

HY/2009/08 (Between Ma Wo and Tai Hang)

Date:

07 December 2011

Time:

14:00

Inspection No.:

187

 

Non-compliance

 

 

Nil

 

 

Observations

 

Follow Up Observations

 

 

1.

Oily mixture underneath the vehicle at Bridge 18 was cleared. (Closed)

 

 

2.

Recyclable wastes were sorted out and C&D materials were cleared up near Bridge 18 north abatement. (Closed)

 

3.

No dark smoke emitting from the roller at W72 was observed. (Closed)

 

 

 

 

 

 

 

 

New Observation

 

4.

 

 

 

5.

 

 

 

6.

Muddy runoff was found on ground near NLKP 9. The Contractor was reminded to clear the muddy runoff and provide preventive measures to prevent surface run-off discharge to the nearby public drains.

 

Mud trails were found on ground at the exit point near NLKP 9. The Contractor was reminded to clear up the mud trails and provide measure to ensure the vehicles bodies and wheels were kept clean of deposited silt before leaving the site.

 

Oil stain was found on ground underneath the air compressor and compressed air tank near NLKP 9. The Contractor was reminded to clear the oil stain and check potential leakage from containers and machineries.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Remarks

 

 

Nil

 

 


Site Inspection Summary

 

Inspection Information

Contract No.

HY/2008/09 (Between Island House Interchange and Ma Wo)

Date:

8 December 2011

Time:

14:00

Inspection No.:

188

 

Non-compliance

 

 

Nil

 

 

Observations

 

Follow Up Observation

 

 

 

Nil.

 

 

 

 

 

 

 

 

 

 

 

New Observation

 

 

Nil.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Remarks

 

 

Nil

 

 


Site Inspection Summary

 

Inspection Information

Contract No.

HY/2008/09 (Between Island House Interchange and Ma Wo)

Date:

14 December 2011

Time:

9:00

Inspection No.:

189

 

Non-compliance

 

 

Nil

 

 

Observations

 

Follow Up Observations

 

 

 

Nil.

 

 

 

 

 

 

 

 

 

 

 

New Observations

 

1.

Metal wires were found tied onto the retained tree near NB16. The Contractor was reminded to remove the metal wires and do not use the retained tree as a physical support.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Remarks

 

 

Nil

 


Site Inspection Summary

 

Inspection Information

Contract No.

HY/2009/08 (Between Ma Wo and Tai Hang)

Date:

15 December 2011

Time:

14:00

Inspection No.:

190

 

Non-compliance

 

 

Nil

 

 

Observations

 

Follow Up Observation

 

 

1.

Muddy runoff on ground near NLKP 9 was cleared and sand bags were provided to intercept the surface run-off from works area. (Closed)

 

 

2.

Mud trails at the exit point near NLKP 9 were cleared and tarpaulin sheet coverage was provided at the exit point to avoid silt deposition on vehicles’ bodies and wheels. (Closed)

 

3.

Oil stain on ground underneath the air compressor and compressed air tank near NLKP 9 was cleared. Sand bag and tarpaulin sheet coverage were provided to retain any oil leakage, if there is such case. (Closed)

 

 

 

 

 

 

New Observations

 

4.

Exposed soil surfaces/slopes were found at W66 and works area near Gate no. 29. The Contractor was reminded to provide regular water spraying or tarpaulin sheet coverage to the exposed soil surfaces/slopes to minimize dust impacts.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Remarks

 

 

Nil

 


 

Site Inspection Summary

 

Inspection Information

Contract No.

HY/2008/09 (Between Island House Interchange and Ma Wo)

Date:

21 December 2011

Time:

9:00

Inspection No.:

191

 

Non-compliance

 

 

Nil

 

 

Observations

 

Follow Up Observations

 

 

1.

Metal wire tied onto the retained tree near NB16 was removed. The trunk of tree was wrapped up with protective material. (Closed)

 

 

 

 

 

 

 

 

 

 

 

 

 

New Observations

 

 

Nil.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Remarks

 

 

Nil

 


Site Inspection Summary

 

Inspection Information

Contract No.

HY/2009/08 (Between Ma Wo and Tai Hang)

Date:

21 December 2011

Time:

14:00

Inspection No.:

192

 

Non-compliance

 

 

Nil

 

 

Observations

 

Follow Up Observation

 

 

1.

Exposed soil surfaces/slopes at W66 and works area near Gate no. 29 was sprayed with water. (Closed)

 

 

 

 

 

 

 

 

 

 

 

 

New Observations

 

2.

Cement and C&D waste was found accumulated inside the u-channel and plastic bag was found blocking the entrance of the pipe at Link Bridge 1. The Contractor was reminded to clear the cement and C&D waste and provide traps to intercept the silt and debris before discharge.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Remarks

 

 

Nil

 

 

 

 

 

 

Site Inspection Summary

 

Inspection Information

Contract No.

HY/2008/09 (Between Island House Interchange and Ma Wo)

Date:

28 December 2011

Time:

9:00

Inspection No.:

193

 

Non-compliance

 

 

Nil

 

 

Observations

 

Follow Up Observations

 

 

 

Nil.

 

 

 

 

 

 

 

 

 

 

 

New Observations

 

1.

Two chemical containers were placed on ground without drip tray at Bridge 10A. The Contractor was reminded to provide drip tray to the chemical containers on site.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Remarks

 

 

Nil

 

 

 

 

 

 

 

 

 

Site Inspection Summary

 

Inspection Information

Contract No.

HY/2009/08 (Between Ma Wo and Tai Hang)

Date:

29 December 2011

Time:

14:00

Inspection No.:

194

 

Non-compliance

 

 

Nil

 

 

Observations

 

Follow Up Observations

 

 

1.

The blockages at the u-channel and pipe entrance near Link Bridge 1 were removed. (Closed)

 

 

 

 

 

 

 

 

 

 

 

New Observations

 

 

Nil.

 

 

2.

 

 

3.

 

 

Reminder

 

Construction debris was found accumulated on bridge deck and inside the waste skip at NLKP 3. The Contractor was reminded to clear the construction debris on site.

 

The Contractor was reminded to maintain and review the dust suppression measure regularly at W45-W46.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Remarks

 

 

Nil