Site
Inspection Summary
Contract No. |
HY/2008/09 (Between Island House
Interchange and Ma Wo) |
Date: |
4 May 2011 |
Time: |
09:00 |
Inspection No.: |
125 |
|
Nil |
|
Follow
Up Observation |
|
|
|
Nil. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
New
Observation |
1. |
Dark
smoke was emitted from an excavator at S14. The Contractor was reminded to
properly service the excavator to avoid dark smoke emission. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Nil |
Site
Inspection Summary
Contract No. |
HY/2009/08 (Between Ma Wo and Tai Hang) |
Date: |
5 May 2011 |
Time: |
14:00 |
Inspection No.: |
126 |
|
Nil |
|
Follow
Up Observation |
|
|
|
Nil. |
|
|
|
|
|
|
|
|
|
|
|
New
Observation |
|
Nil. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Nil |
Site
Inspection Summary
Contract No. |
HY/2009/08 (Between Ma Wo and Tai Hang) |
Date: |
11 May 2011 |
Time: |
14:00 |
Inspection No.: |
127 |
|
Nil |
|
Follow
Up Observation |
|
|
|
Nil. |
|
|
|
|
|
|
|
|
|
|
|
New
Observation |
1. |
Stagnant
water was observed inside the waste skip at Gate 7. The Contractor was
reminded to clear the stagnant was and take mitigation measures to prevent
mosquito breeding. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Nil |
Site
Inspection Summary
Contract No. |
HY/2008/09 (Between Island House
Interchange and Ma Wo) |
Date: |
12 May 2011 |
Time: |
09:00 |
Inspection No.: |
128 |
|
Nil |
|
Follow
Up Observation |
|
|
1. |
The site inspection did not cover the area
at S14. The status of emission from the plants at S14 is to be inspected.
(Follow-up) |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
New
Observations |
2. |
The
haul road at Wall 4-7 was dry. The Contractor was reminded to take dust
suppression measures more frequently to minimize fugitive dust generation. |
|
|
3. |
Stagnant
water was observed inside a waste skip at Wall 4-7. The Contractor was
reminded to clear the stagnant water and take mitigation measures to prevent
mosquito breeding. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Nil |
Site
Inspection Summary
Contract No. |
HY/2009/08 (Between Ma Wo and Tai Hang) |
Date: |
18 May 2011 |
Time: |
09:00 |
Inspection No.: |
129 |
|
Nil |
|
Follow
Up Observation |
|
|
1. |
Stagnant water inside the waste skip at
Gate 7 had been cleared and coverage was provided to prevent rainwater from
accumulating inside the skips. (Closed) |
|
|
|
|
|
|
|
|
|
|
|
New
Observation |
|
Nil. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Nil |
Site
Inspection Summary
Contract No. |
HY/2008/09 (Between Island House
Interchange and Ma Wo) |
Date: |
19 May 2011 |
Time: |
14:00 |
Inspection No.: |
130 |
|
Nil |
|
Follow
Up Observation |
|
|
1. |
No dark smoke emission was observed from
the plants at S14. (Closed) |
|
|
2. |
Water spraying
was provided to the haul road at Wall 4-7 and the entire haul road was
sufficiently dampened. (Closed) |
3. |
The
waste skip at Wall 4-7 was flipped over to prevent accumulation of stagnant
water inside. (Closed) |
|
|
|
|
|
|
|
New
Observation |
|
Nil. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Nil |
Site
Inspection Summary
Contract No. |
HY/2008/09 (Between Island House
Interchange and Ma Wo) |
Date: |
25 May 2011 |
Time: |
09:00 |
Inspection No.: |
131 |
|
Nil |
|
Follow
Up Observation |
|
|
|
Nil. |
|
|
|
|
|
|
|
|
|
|
|
|
|
New
Observation |
|
Nil. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Nil |
Site
Inspection Summary
Contract No. |
HY/2009/08 (Between Ma Wo and Tai Hang) |
Date: |
26 May 2011 |
Time: |
14:00 |
Inspection No.: |
132 |
|
Nil |
|
Follow
Up Observation |
|
|
|
Nil. |
|
|
|
|
|
|
|
|
|
|
|
New
Observations |
1. |
The
level of the concrete layer at NLKP Pier 2 had become higher than the sand
bag bunding next to the u-channel. The Contractor was reminded to improve the
bunding to intercept site runoff from entering the u-channel. |
2. |
Exposed
slope was observed near the u-channel at NLKP Pier 2. The Contractor was
reminded to either cover the slope with tarpaulin or hydro-seed the slope to
prevent surface runoff into the u-channel. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Nil |