Site
Inspection Summary
Contract No. |
HY/2008/09 (Between Island House
Interchange and Ma Wo) |
Date: |
3 March 2011 |
Time: |
09:00 |
Inspection No.: |
107 |
|
Nil |
|
Follow
Up Observation |
|
|
|
Nil. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
New
Observation |
|
Nil. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Nil |
Site
Inspection Summary
Contract No. |
HY/2009/08 (Between Ma Wo and Tai Hang) |
Date: |
3 March 2011 |
Time: |
14:00 |
Inspection No.: |
108 |
|
Nil |
|
Follow
Up Observations |
|
|
1. |
The leaves inside the u-channel at W38 had
been removed. (Closed) |
|
|
2. |
The
stockpiles of dusty material at Area B had been covered properly. (Closed) |
|
|
3. |
Non-inert
C&D waste, general refuse and metal had been sorted and separated from
one another on site. (Closed) |
|
|
|
New
Observations |
4. |
Dark
smoke was observed emitted from a drill rig at Bridge 13A Pier 2. The
Contractor was reminded to properly maintain the plants on site. |
5. |
Seepage
of muddy water was observed from the gaps of concrete blocks under the piling
area at Bridge 13A Pier2. To prevent muddy water from running off to the
adjacent stream, the Contractor was requested to align a bunding at the foot
of the concrete blocks to divert the seeped water to desilting facility. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Nil |
Site
Inspection Summary
Contract No. |
HY/2008/09 (Between Island House
Interchange and Ma Wo) |
Date: |
9 March 2011 |
Time: |
14:00 |
Inspection No.: |
109 |
|
Nil |
|
Follow
Up Observation |
|
|
|
Nil. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
New
Observations |
1. |
Two
chemical containers were placed on ground without drip tray at Bridge 10A.
The Contractor was reminded to provide drip tray to all chemicals on site. |
|
|
2. |
Ropes
to hang clothes were found tied on retained trees at Bridge 10A. The
Contractor was reminded to untie the ropes and not to hang anything on the
retained trees in the future. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Nil |
Site
Inspection Summary
Contract No. |
HY/2009/08 (Between Ma Wo and Tai Hang) |
Date: |
10 March 2011 |
Time: |
14:00 |
Inspection No.: |
110 |
|
Nil |
|
Follow
Up Observations |
|
|
1. |
No dark smoke was observed emitted from the
drill rig at Bridge 13A Pier 2. (Closed) |
|
|
2. |
Sand
bag bunding had been aligned at the bottom of the concrete blocks at Bridge
13A Pier 2 to divert the seeped water to a desilting pit. (Closed) |
|
|
|
|
|
|
|
New
Observations |
3. |
Dusty
material from soil nailing works was accumulated at Bridge 18 C35. The
Contractor was reminded to clear up the dusty material in a timely manner. |
4. |
Soil
nail installation controller was placed on ground without drip tray at Bridge
18 C35. The Contractor was reminded to provide drip tray to all soil nail
installation controllers on site. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Nil |
Site
Inspection Summary
Contract No. |
HY/2008/09 (Between Island House
Interchange and Ma Wo) |
Date: |
17 March 2011 |
Time: |
09:00 |
Inspection No.: |
111 |
|
Nil |
|
Follow
Up Observations |
|
|
1. |
The chemical containers on ground without
drip tray at Bridge 10A had been removed. (Closed) |
|
|
|
|
2. |
Ropes had been untied from the retained
trees at Bridge 10A. (Closed) |
|
|
|
|
|
|
|
|
|
New
Observation |
|
Nil. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Nil |
Site
Inspection Summary
Contract No. |
HY/2009/08 (Between Ma Wo and Tai Hang) |
Date: |
17 March 2011 |
Time: |
14:00 |
Inspection No.: |
112 |
|
Nil |
|
Follow
Up Observations |
|
|
1. |
The dusty material from soil nailing works
at Bridge 18 C35 had been cleared. (Closed) |
|
|
2. |
The
soil nail installation controller at Bridge 18 C35 had been provided with
drip tray. (Closed) |
|
|
|
|
|
|
|
New
Observation |
3. |
The
flap of an air compressor at NLKP 7 was opened during operation. The
Contractor was reminded to close the flaps of mechanical equipments during
operation. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Nil |
Site
Inspection Summary
Contract No. |
HY/2008/09 (Between Island House
Interchange and Ma Wo) |
Date: |
23 March 2011 |
Time: |
09:00 |
Inspection No.: |
113 |
|
Nil |
|
Follow
Up Observation |
|
|
|
Nil. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
New
Observation |
1. |
Noise
emission label was missing on an air compressor at West abutment of Bridge
10A. The Contractor was reminded to attach the noise emission label on the
body of the air compressor. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Nil |
Site
Inspection Summary
Contract No. |
HY/2009/08 (Between Ma Wo and Tai Hang) |
Date: |
24 March 2011 |
Time: |
14:00 |
Inspection No.: |
114 |
|
Nil |
|
Follow
Up Observation |
|
|
1. |
The flap of an air compressor at NLKP 7 had
been closed during operation. (Closed) |
|
|
|
|
|
|
|
|
|
|
|
New
Observation |
2. |
The
sand bag bunding at the bottom of the concrete blocks at Bridge 13A Pier2 was
covered up by shotcrete layer which rendered the sand bags ineffective to
prevent untreated water from running off to the adjacent stream. The
Contractor was advised to provide an effective bunding to divert the
untreated water to desilting facility. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Nil |
Site
Inspection Summary
Contract No. |
HY/2008/09 (Between Island House
Interchange and Ma Wo) |
Date: |
31 March 2011 |
Time: |
09:00 |
Inspection No.: |
115 |
|
Nil |
|
Follow
Up Observation |
|
|
1. |
Noise emission label had been fitted on the
air compressor at West abutment of Bridge 10A. (Closed) |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
New
Observation |
|
Nil. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Nil |
Site
Inspection Summary
Contract No. |
HY/2009/08 (Between Ma Wo and Tai Hang) |
Date: |
31 March 2011 |
Time: |
14:00 |
Inspection No.: |
116 |
|
Nil |
|
Follow
Up Observation |
|
|
1. |
The site inspection did not cover the area
at Bridge 13A Pier2. The status of the bunding to divert untreated water was
to be inspected. |
|
|
|
|
|
|
|
|
|
|
|
New
Observation |
2. |
Two
bottles of chemical were placed on ground without drip tray at W73. The
Contractor was reminded to provide drip tray to all chemicals on site. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Nil |