Site Inspection Summary

 

Inspection Information

Contract No.

HY/2008/09 (Between Island House Interchange and Ma Wo)

Date:

6 October 2010

Time:

14:00

Inspection No.:

065

 

Non-compliance

 

 

Nil

 

 

Observations

 

Follow Up Observation

 

 

 

Nil.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

New Observation

 

 

Nil.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Remarks

 

 

Nil

 

 


Site Inspection Summary

 

Inspection Information

Contract No.

HY/2009/08 (Between Ma Wo and Tai Hang)

Date:

7 October 2010

Time:

14:00

Inspection No.:

066

 

Non-compliance

 

 

Nil

 

 

Observations

 

Follow Up Observations

 

 

1.

The site inspection did not cover the area at Bridge 12A. The condition of excavated mud and the drip trays are to be inspected.

 

 

2.

The site inspection did not cover the area at Bridge 12A. The condition of noise emission of the air compressor is to be inspected.

 

 

3.

The site inspection did not cover the area at Bridge 12A. The condition of stockpile of mud is to be inspected.

 

 

4.

The site inspection did not cover W73. The condition of vehicle washing at W73 is to be inspected.

 

 

 

 

 

New Observation

 

 

Nil.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Remarks

 

 

Nil

 

 


Site Inspection Summary

 

Inspection Information

Contract No.

HY/2009/08 (Between Ma Wo and Tai Hang)

Date:

13 October 2010

Time:

14:00

Inspection No.:

067

 

Non-compliance

 

 

Nil

 

 

Observations

 

Follow Up Observations

 

 

1.

Excavated mud inside the drip tray underneath the air compressor at Bridge 12A P1 had been removed. (Closed)

 

 

2.

Noise emission label of the air compressor at Bridge 12A P1 had been attached at obvious location on the equipment. (Closed)

 

 

3.

The stockpile of mud at Bridge 12A P1 next to the u-channel had been fully covered. (Closed)

 

 

4.

Vehicle wheel washing with high pressure jet had been provided at W73 site entrance. (Closed)

 

 

 

 

 

New Observation

 

5.

The flap of a crane was opened during operation at Bridge 12A P1. The Contractor was reminded to close the flaps of the mechanical equipments during operation.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Remarks

 

 

Nil

 

 


Site Inspection Summary

 

Inspection Information

Contract No.

HY/2008/09 (Between Island House Interchange and Ma Wo)

Date:

14 October 2010

Time:

14:00

Inspection No.:

068

 

Non-compliance

 

 

Nil

 

 

Observations

 

Follow Up Observation

 

 

 

Nil.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

New Observation

 

1.

An oil drum was observed placed on ground without drip tray at Bridge 10A. The Contractor was reminded to provide drip tray to all chemical containers on site.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Remarks

 

 

Nil

 

 


Site Inspection Summary

 

Inspection Information

Contract No.

HY/2008/09 (Between Island House Interchange and Ma Wo)

Date:

21 October 2010

Time:

09:00

Inspection No.:

069

 

Non-compliance

 

 

Nil

 

 

Observations

 

Follow Up Observation

 

 

1.

The oil drum without drip tray at Bridge 10A had been removed. (Closed)

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

New Observation

 

 

Nil.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Remarks

 

 

Nil

 

 

 

 

Name

Signature

Date

Prepared by

Ryan Wong

 

22 October 2010

Checked by

Edith Ng

 

22 October 2010

 


Site Inspection Summary

 

Inspection Information

Contract No.

HY/2009/08 (Between Ma Wo and Tai Hang)

Date:

21 October 2010

Time:

14:00

Inspection No.:

070

 

Non-compliance

 

 

Nil

 

 

Observations

 

Follow Up Observation

 

 

1.

The piling crane with the flap opened at Bridge 12A P2 had been removed. (Closed)

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

New Observation

 

2.

Oil stain was observed on ground next to the drip tray of a generator at Area 25 near Tai Wo Road. The Contractor was advised to provide a large drip tray to the generator.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Remarks

 

 

Nil

 

 


Site Inspection Summary

 

Inspection Information

Contract No.

HY/2008/09 (Between Island House Interchange and Ma Wo)

Date:

27 October 2010

Time:

09:00

Inspection No.:

071

 

Non-compliance

 

 

Nil

 

 

Observations

 

Follow Up Observation

 

 

 

Nil.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

New Observation

 

 

Nil.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Remarks

 

 

Nil

 

 


Site Inspection Summary

 

Inspection Information

Contract No.

HY/2009/08 (Between Ma Wo and Tai Hang)

Date:

28 October 2010

Time:

14:00

Inspection No.:

072

 

Non-compliance

 

 

Nil

 

 

Observations

 

Follow Up Observation

 

 

1.

The site inspection did not cover the area at Tai Wo Road. The condition of the drip tray of the generator at Area 25 is to be inspected.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

New Observations

 

2.

Cement powder was scattered on the ground at W72B. The Contractor was requested to clean up the cement powder.

3.

Empty cement bags were accumulated next to the grouting station at Lam Kam Flyover Pier 3. The Contractor was advised to dispose of the empty cement bags properly.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Remarks

 

 

Nil