Site Inspection Summary

 

Inspection Information

Contract No.

HY/2009/08

Date:

7 July 2010

Time:

09:00

Inspection No.:

039

 

Non-compliance

 

 

Nil

 

 

Observations

 

Follow Up Observation

 

 

 

Nil.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

New Observation

 

 

Nil.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Remarks

 

 

Nil

 

 


Site Inspection Summary

 

Inspection Information

Contract No.

HY/2008/09

Date:

8 July 2010

Time:

14:00

Inspection No.:

040

 

Non-compliance

 

 

Nil

 

 

Observations

 

Follow Up Observations

 

 

1.

Silt inside a section of the u-channel at Wall 8 had been cleared. However, silt was still found deposited inside a few sections of the u-channel at Wall 8. The Contractor was reminded to clear the u-channel more frequently, especially during rainy seasons.

 

 

 

 

2.

Sand bag bunding had been provided at the section where perimeter u-channel is missing at Wall 8. (Closed)

 

 

 

 

 

 

 

 

 

New Observation

 

 

Nil.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Remarks

 

 

Nil

 

 


Site Inspection Summary

 

Inspection Information

Contract No.

HY/2008/09

Date:

14 July 2010

Time:

09:00

Inspection No.:

041

 

Non-compliance

 

 

Nil

 

 

Observations

 

Follow Up Observation

 

 

1.

The site audit did not include Wall 8 area. The condition of silt deposition in the u-channel at Wall 8 is to be inspected in the next audit.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

New Observation

 

 

Nil.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Remarks

 

 

Nil

 

 


Site Inspection Summary

 

Inspection Information

Contract No.

HY/2009/08

Date:

15 July 2010

Time:

14:00

Inspection No.:

042

 

Non-compliance

 

 

Nil

 

 

Observations

 

Follow Up Observation

 

 

 

Nil.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

New Observation

 

 

Nil.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Remarks

 

 

Nil

 

 


Site Inspection Summary

 

Inspection Information

Contract No.

HY/2008/09

Date:

21 July 2010

Time:

09:00

Inspection No.:

043

 

Non-compliance

 

 

Nil

 

 

Observations

 

Follow Up Observation

 

 

1.

The silt inside the u-channel at Wall 8 had been cleared. (Closed)

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

New Observation

 

2.

Muddy water from vehicle wheel washing overflowed to the public road at the site entrance of Wall 8. The Contractor was requested to review the methodology of the wheel washing facility at the site entracnce.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Remarks

 

 

Nil

 

 


Site Inspection Summary

 

Inspection Information

Contract No.

HY/2009/08

Date:

22 July 2010

Time:

14:00

Inspection No.:

044

 

Non-compliance

 

 

Nil

 

 

Observations

 

Follow Up Observation

 

 

 

Nil.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

New Observations

 

1.

Noise was generated from the pavement breaking work underneath Bridge 12 at Shek Lin Road. The Contractor was advised to erect additional movable noise barriers for noisy activities to reduce the noise nuisance to the nearby residents.

 

 

 

 

2.

General refuse and felled trees were scattered at the soil nailing area on Slope 41. The Contractor was reminded to maintain waste sorting and proper housekeeping.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Remarks

 

 

Nil

 

 


Site Inspection Summary

 

Inspection Information

Contract No.

HY/2008/09

Date:

28 July 2010

Time:

09:00

Inspection No.:

045

 

Non-compliance

 

 

Nil

 

 

Observations

 

Follow Up Observation

 

 

1.

Rectifying measures to divert the water from vehicle wheel washing to a desilting pit had been taken by the Contractor at the site entrance of Wall 8. No muddy water was found runoff to public road. (Closed)

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

New Observation

 

 

Nil.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Remarks

 

 

Nil

 

 


Site Inspection Summary

 

Inspection Information

Contract No.

HY/2009/08

Date:

29 July 2010

Time:

14:00

Inspection No.:

046

 

Non-compliance

 

 

Nil

 

 

Observations

 

Follow Up Observations

 

 

1.

The pavement breaking work at Bridge 12 had been completed. No noisy activity was observed on site. (Closed)

 

 

2.

Proper housekeeping had been kept at Slope 41. (Closed)

 

 

 

 

 

 

 

 

 

 

 

New Observations

 

3.

Bunding was missing at one of the sides and several holes were observed on the temporary bridge leading to Bridge 12B. The Contractor was advised to provide bunding at both sides and to seal the holes on the temporary bridge to prevent runoff to the stream underneath.

 

 

 

 

4.

The water discharged to the public drain at the site entrance of Bridge 12A was observed muddy. The Contractor was requested to stop the water discharge immediately and check the functioning of the desilting facility before further discharge.

 

 

5.

A drip tray underneath an air compressor at Bridge 12A was overflowed with water. The Contractor was reminded to remove the water in the drip tray.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Remarks

 

 

Nil