Site
Inspection Summary
Contract No. |
HY/2008/09 |
Date: |
7 April 2010 |
Time: |
14:00 |
Inspection No.: |
020 |
|
Nil |
|
Follow
Up Observation |
|
|
|
Nil |
|
|
|
|
|
|
|
|
|
|
|
New
Observation |
|
|
1. |
Small
amount of oil seepage was observed underneath an idle excavator at Banyan
Bridge. The Contractor was reminded to provide a tarpaulin sheets underneath
the excavator and remove the contaminated soil as chemical waste. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Nil |
Site
Inspection Summary
Contract No. |
HY/2008/09 |
Date: |
14 April 2010 |
Time: |
09:00 |
Inspection No.: |
021 |
|
Nil |
|
Follow
Up Observation |
|
|
1. |
The excavator at Banyan Bridge had been
repaired and the oil stains had been removed. However, oil seepage was
observed underneath a crawler crane at Bridge 10A. The Contractor was
reminded to clear the oil stains and properly maintain the machineries on
site. |
|
|
|
|
|
|
|
|
|
|
|
New
Observations |
|
|
2. |
Two
chemical containers at Wall 10 were observed without chemical label. The
Contractor was reminded to provide chemical labels to all chemicals on site. |
3 |
A
few oil containers were placed on ground without drip tray at Wall 14 and at
Bridge 11A. The Contractor was reminded to provide drip tray to all chemicals
on site. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Nil |
Site
Inspection Summary
Contract No. |
HY/2008/09 |
Date: |
20 April 2010 |
Time: |
09:00 |
Inspection No.: |
022 |
|
Nil |
|
Follow
Up Observations |
|
|
1. |
The crawler crane at Bridge 10A had been
repaired and no oil stain was observed on ground. (Closed) |
|
|
2. |
The
chemical containers at Wall 10 had been removed. (Closed) |
|
|
3 |
The
oil containers at Wall 14 and Bridge 11A had been provided with drip trays.
(Closed) |
|
|
|
|
|
|
|
New
Observations |
4. |
Moderate
noise level was generated during the concrete breaking activity at Bridge
10A. The Contractor was recommended to wrap the breaker tip with sound
insulation material. |
5. |
The
water in Tai Po River outside Wall 10 was muddy. The Contractor was requested
to investigate the cause of the muddy water and suspend the work of the
possible source immediately. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Nil |
Site
Inspection Summary
Contract No. |
HY/2008/09 |
Date: |
28 April 2010 |
Time: |
09:00 |
Inspection No.: |
023 |
|
Nil |
|
Follow
Up Observations |
|
|
1. |
The concrete breaking work at Bridge 10A
had been completed. (Closed) |
|
|
2. |
The
water in Tai Po River was observed clear and an investigation report for the
muddy water incident at the last inspection had been submitted. (Closed) |
|
|
|
|
|
|
|
|
|
|
|
New
Observation |
3. |
One
of the fencings for protecting the retained trees was broken at Banyan
Bridge. The Contractor was reminded to fix the fencing. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Nil |