TABLE OF CONTENTS
2 Environmental Monitoring and Audit
Requirements
4 Construction Noise MONITORING
5 ENVIRONMENTAL SITE INSPECTION AND AUDIT
6 Summary AND REVIEW of Non-compliance
(Exceedances) of the Environmental Quality
7 Environmental Complaints, Notification of
Summons and Successful Prosecutions
8 REVIEW of THE VALIDITY OF THE EIA/ERR Prediction
9 Review of ENVIRONMENTAL IMPLEMENTATION
STATUS
List of Tables
Table 1.1 Contact
Information of Key Personnel
Table 3.1 Locations of Impact
Air Quality Monitoring Stations
Table 3.2 Summary
of Number of Monitoring Events for 1-hr & 24-hr TSP Concentration
Table 3.3 Summary
of Number of Exceedances for 1-hr & 24-hr TSP Monitoring
Table 4.1 Locations of Impact
Noise Monitoring Stations
Table 4.2 Summary
of Number of Monitoring Events for Construction Noise
Table 4.3 Summary
of Number of Monitoring Exceedances for Construction Noise
Figures
Figure 1.1 General Project Layout Plan
Figure 2.1 Locations of EM&A Monitoring Stations
List of Appendix
Appendix A Project Organization Structure
Appendix B Implementation Schedule of Environmental Mitigation Measures
(EMIS)
Appendix
C Summary of Action and Limit Levels
Appendix D Graphical
Presentation of Air Quality Monitoring Results
Appendix E Graphical
Presentation of Construction Noise Monitoring Results
Appendix F Statistics on complaints, notifications
of summons and successful prosecutions
The
proposed widening of
The
construction works for this Project will be delivered in 2 stages i.e. Stage 1
(between Island House Interchange and Tai Hang) and Stage 2 (between Tai Hang
and Wo Hop Shek Interchange). The construction works of Stage 1 were commenced
on 23 November 2009 and will tentatively be completed in December 2013; while
construction programme of Stage 2 is currently under review. This report
focuses on Stage 1 of the Project only.
The
construction phase of Stage 1 under the EP and the EM&A programme for Stage
1 of the Project commenced on 23 November 2009. The impact environmental
monitoring and audit includes air quality and noise monitoring.
This
report documents the findings of EM&A works conducted in the period between
23 November 2009 and 31 October 2010.
As
informed by the Contract 1 Contractor (China State
Construction Engineering (Hong Kong) Ltd.), construction activities in the
reporting period included:
-
Temporary shoring and sheetpiling;
-
Demolition and re-construction of box culverts;
-
Excavation and backfilling;
-
Pipe pile wall construction;
-
Pile cap construction;
-
Bridge column and pier head construction;
-
Bored piling;
-
Tree felling and transplanting of trees;
-
Installation of soil nails;
-
Construction of retaining wall;
-
Construction of at-grade road;
-
Widening and demolition of central dividers;
-
Formation of slip road;
-
Construction of temporary access;
-
Construction of step channel;
-
Construction of retaining wall;
-
Construction of temporary bridges; and
-
Demolition of bridges.
The construction works carried out by the Contract 2 Contractor (Gammon Construction Ltd.) in the
reporting period included:
-
Construction of haul roads and temporary site
accesses;
-
Tree felling and tree transplant;
-
Piling and pile cap of bridges;
-
Construction of pilecap / spread footing of
noise barrier / semi noise enclosure;
-
Slope works, including installation of soil
nail;
-
Entrusted watermain works;
-
Retaining wall construction; and
-
Modification of existing bridge structure.
Breaches of Action and Limit
Levels for Air Quality
No exceedance of Action and Limit Levels was recorded for 1-hour TSP
monitoring in the reporting period.
However, one (1) Limit Level exceedance was recorded for 24-hour TSP
monitoring at AM2 in the reporting period.
Breaches of Action and Limit Levels for Noise
There were six
noise related complaints followed up by Environmental Team in the reporting
period, hence six (6) Action Level exceedances of noise were recorded.
No Limit Level
exceedance of construction noise monitoring was recorded in the reporting
period.
Complaint, Notification of
Summons and Successful Prosecution
Nine (9)
environmental complaints were followed up by Environmental Team in the
reporting period.
No notification of
summons and successful prosecution was received in the reporting period.
1.1.
1.2.
The objective of the Project “Widening of Tolo
Highway /
1.3.
The Project is a designated project and is governed
by an Environmental Permit (EP-324/2008)(EP).
1.4.
The scope of the Project comprises mainly:
(i) |
Widening of a
5.7 km section of Tolo Highway and 3.0 km section of Fanling Highway between
Island House Interchange and Wo Hop Shek Interchange from the existing dual
3-lane to dual 4-lane, including construction of new vehicular bridges; |
(ii) |
Widening of
interchange sections at Island House Interchange, Tai Po North Interchange,
and Lam Kam Road Interchange from dual 2-lane to dual 3-lane, except Sha Tin
bound carriageway at Tai Po North Interchange, which is widened from 3-lane
to 4-lane, including realignment of various slip roads; |
(iii) |
Modification
and reconstruction of highways, vehicular bridges, underpasses and
footbridges. |
1.5.
The construction works for this Project will be
delivered in 2 stages i.e. Stage 1 (between Island House Interchange and Tai
Hang) and Stage 2 (between Tai Hang and Wo Hop Shek Interchange). The
construction works of Stage 1 commenced on 23 November 2009 and will
tentatively be completed in December 2013; while construction programme of
Stage 2 is currently under review. This report focuses on Stage 1 of the
Project only.
1.6.
The construction works for Stage 1 of the Project
will be implemented under 2 works contracts (Contract 1 and Contract 2). Contract 1 covers the section of
1.7.
Hyder-Arup-Black and Veatch Joint Venture (HABVJV)
are appointed by Highways Department as the consultants for the design and
construction assignment for the Tolo project under Agreement No. CE 58/2000
Supplementary Agreement No. 3 (SA3) (i.e. the Engineer for the Contracts).
1.8.
China State Construction Engineering (Hong Kong) Ltd.
(CSCE) was commissioned as the Contractor of Contract 1 of Stage 1 of the
Project, while Gammon Construction Limited (GCL) was commissioned as the
Contractor of Contract 2 of Stage 1 of the Project.
1.9.
AECOM Asia Co. Ltd. was employed by Highways Department
as the Environmental Team to undertake the EM&A works for Stage 1 of the
Project and Mott MacDonald Hong Kong Ltd. acts as the Independent Environmental
Checker (IEC) for the Contracts.
1.10.
The construction phase of Stage 1 under the EP
commenced on 23 November 2009.
1.11.
According to the updated EM&A Manual of Stage 1
of the Project, there is a need of an EM&A programme including air quality
and noise monitoring. The EM&A programme for Stage 1 of the Project
commenced on 23 November 2009.
Scope of Report
1.12.
This is the first Annual Environmental Monitoring
and Audit (EM&A) Review Report under the Agreement No. CE 20/2009 (EP) -
Widening of Tolo Highway between Island House Interchange and Tai Hang –
Investigation. This report presents a
summary of the environmental monitoring and audit works, list of activities and
mitigation measures proposed by the ET for Stage 1 of the Project from 23
November 2009 to 31 October 2010.
Project
Organization
1.13.
The project organization is shown in Appendix A.
The key personnel contact names and numbers are summarized in Table 1.1.
Table 1.1 Contact
Information of Key Personnel
Party |
Position |
Name |
Telephone |
Fax |
ER of Stage 1, Contract 1 (Hyder-Arup-Black
& Veatch Joint Venture) |
Chief Resident Engineer /TOLO1 |
James Tsang |
9038 8797 |
26674000 |
ER of Stage 1, Contract 2 (Hyder-Arup-Black
& Veatch Joint Venture) |
Chief Resident Engineer /TOLO2 |
Paul Appleton |
9097 5833 |
2653 2348 |
IEC of Stage 1 (Mott MacDonald Hong Kong Ltd.) |
Independent
Environmental Checker |
Joseph Chan (up to 22 Aug 2010) |
2828 5920 |
2827 1823 |
Terence Kong (with effect from 23 Aug 2010) |
2828 5919 |
2827 1823 |
||
Contractor
of Stage 1, Contract 1 (China State Construction
Engineering (Hong Kong) Ltd.) |
Site Agent |
David Lau |
9499 0818 |
2667 5666 |
Environmental Officer |
Michael Tsang |
9277 4956 |
2667 5666 |
|
Contractor
of Stage 1, Contract 2 (Gammon Construction Ltd.) |
Site Agent |
K F Tam (up to 9 Aug 2010) |
9032 1133 |
2559 3410 |
Edmond Chan (with effect from
10 Aug 2010) |
9483 8885 |
2559 3410 |
||
Environmental
Officer |
Kenneth Chan |
9300 2182 |
2559 3410 |
|
ET of Stage 1 (AECOM Asia Co. Ltd.) |
ET Leader |
Y T Tang |
2893 1551 |
2891 0305 |
1.14. The construction
phase of Stage 1 under the EP commenced on 23 November 2009. Details of the
construction works carried out by the Contract 1 Contractor (CSCE) in this reporting period are listed below:
-
Temporary shoring and sheetpiling;
-
Demolition and re-construction of box culverts;
-
Excavation and backfilling;
-
Pipe pile wall construction;
-
Pile cap construction;
-
Bridge column and pier head construction;
-
Bored piling;
-
Tree felling and transplanting of trees;
-
Installation of soil nails;
-
Construction of retaining wall;
-
Construction of at-grade road;
-
Widening and demolition of central dividers;
-
Formation of slip road;
-
Construction of temporary access;
-
Construction of step channel;
-
Construction of retaining wall;
-
Construction of temporary bridges; and
-
Demolition of bridges.
1.15. The construction
works carried out by the Contract 2 Contractor (GCL) in the reporting period
were:
-
Construction of haul roads and temporary site
accesses;
-
Tree felling and tree transplant;
-
Piling and pile cap of bridges;
-
Construction of pilecap / spread footing of
noise barrier / semi noise enclosure;
-
Slope works, including installation of soil
nail;
-
Entrusted watermain works;
-
Retaining wall construction; and
-
Modification of existing bridge structure.
1.16. The general
layout plan of the Project site showing the contract areas is shown in Figure
1.1.
1.17. The mitigation
measures implementation schedule are presented in Appendix B.
2.1.
The updated EM&A Manual designated 4 air
quality monitoring stations and 7 noise monitoring stations to monitor
environmental impacts on air quality and noise due to Stage 1 of the Project.
2.2.
For air quality, monitoring locations AM2 (Shan
Tong New Village) and AM3 (Riverain Bayside) were set up at the proposed
locations in accordance with updated EM&A Manual. However, for monitoring
locations: Dynasty View and Tai Po Garden, proposed in the updated EM&A
Manual, as approval could not be obtained from the owner’s corporation of the
premises, impact air quality monitoring was conducted at alternative monitoring
locations: AM1 (Ha Wun Yiu) and AM4 (Tai Kwong Secondary School). The monitoring
station at 13 Ha Wun Yiu (AM1) was relocated to Fan Sin Temple, 3 Sheung Wun
Yiu (AM1A) in February 2010.
2.3.
For noise, monitoring stations NM3 (Wong Shiu Chi
Middle School), NM6 (PLK Tin Ka Ping Primary School) and NM7 (Riverain Bayside)
were set up at the proposed locations in accordance with updated EM&A
Manual. However, for monitoring locations: Tai Po Garden, Dynasty View, Hong
Kong Teachers’ Association Lee Heng Kwei Secondary School and Grand Palisades,
proposed in the updated EM&A Manual, as approval of access could not be
obtained from the owner’s corporation of the premises or the principal of the
education institutes, impact noise monitoring was conducted at alternative
monitoring locations: NM1 (Tai Kwong Secondary School), NM2 (Ha Wun Yiu), NM4 (Uptown
Plaza) and NM5 (The Paragon).
2.4.
The monitoring locations are depicted in Figure
2.1.
2.5.
The updated EM&A Manual also required
environmental site inspections for air quality, noise, water quality, chemical,
waste management, ecology and landscape and visual impact.
Environmental Quality Performance Limits
(Action/Limit Levels)
2.6.
The environmental quality performance limits (i.e.
Action/Limit Levels) of air quality monitoring were derived from the baseline air
quality monitoring results at the respective monitoring stations (AM1(A), AM2,
AM3 and AM4), while the environmental quality performance limits of noise
monitoring were defined in the EM&A Manual.
2.7.
The environmental quality performance limits of air
quality and noise monitoring and are given in Appendix C.
Environmental Mitigation Measures
2.8.
Relevant environmental mitigation measures were
stipulated in the Particular Specification and EP (EP-324/2008) for the Contractor to adopt. A list of mitigation
measures and their implementation statuses are given in Appendix B.
3.1.
Air quality monitoring, including 1-hour and
24-hour TSP, was conducted at least 3 times every 6 days and at least once
every 6 days respectively at the 4 monitoring stations, in accordance with the
updated EM&A Manual.
3.2.
Figure 2.1 shows the locations of monitoring
stations. Table 3.1 describes the details of the monitoring stations.
Table 3.1 Locations of Impact Air Quality
Monitoring Stations
Monitoring
Station |
Location |
Description |
AM1* |
13 Ha Wun Yiu |
Ground floor outside the premises |
AM1A |
3 Sheung Wun
Yiu |
Ground floor at
the boundary outside |
AM2 |
12 Shan Tong
New Village |
Ground floor outside
the premises |
AM3 |
Riverain
Bayside |
Roof of the
switch room |
AM4 |
|
Roof of the school |
*
AM1 1-hr TSP monitoring station was relocated to AM1A on 26 February
2010; and
AM1
24-hr TSP monitoring station was relocated to AM1A on 25 February 2010
3.3.
The weather was mostly sunny within the reporting
period, but with several downpours between July 2010 and October 2010. The
major dust source of the construction work area included concrete breaking,
soil nail installation and excavation activities from Stage 1 of the Project,
as well as nearby traffic emissions.
3.4.
The number of monitoring events and exceedances
recorded in each month of the reporting period are presented in Table 3.2 and Table
3.3 respectively.
Table 3.2 Summary of
Number of Monitoring Events for 1-hr & 24-hr TSP Concentration
Monitoring Parameter |
Location |
No. of monitoring events |
Nov 09 – Oct 10 |
||
1-hr TSP |
AM1 |
48* |
AM1A |
129 |
|
AM2 |
177 |
|
AM3 |
177 |
|
AM4 |
177 |
|
24-hr TSP |
AM1 |
13** |
AM1A |
43 |
|
AM2 |
58 |
|
AM3 |
59 |
|
AM4 |
59 |
* AM1 1-hr
TSP monitoring station was relocated to AM1A on 26 February 2010
** AM1
24-hr TSP monitoring station was relocated to AM1A on 25 February 2010
Table 3.3
Summary of Number of
Exceedances for 1-hr & 24-hr TSP Monitoring
Monitoring Parameter |
Location |
Level of Exceedance |
Level of Exceedance |
Nov 09 – Oct 10 |
|||
1-hr TSP |
AM1 |
Action |
0 |
Limit |
0 |
||
AM1A |
Action |
0 |
|
Limit |
0 |
||
AM2 |
Action |
0 |
|
Limit |
0 |
||
AM3 |
Action |
0 |
|
Limit |
0 |
||
AM4 |
Action |
0 |
|
Limit |
0 |
||
|
Total |
0 |
|
24-hr TSP |
AM1 |
Action |
0 |
Limit |
0 |
||
AM1A |
Action |
0 |
|
Limit |
0 |
||
AM2 |
Action |
0 |
|
Limit |
1 |
||
AM3 |
Action |
0 |
|
Limit |
0 |
||
AM4 |
Action |
0 |
|
Limit |
0 |
||
|
Total |
1 |
3.5.
All 1-hour TSP results were below the Action and
Limit Levels at all monitoring locations in the reporting period.
3.6.
However, one (1) Limit Level exceedance was
recorded for 24-hour TSP monitoring at AM2 on 22 March 2010.
Soil nailing works, bored piling and excavation works were carried out
on 22 March 2010. The following dust mitigation measures have been implemented
by the Contract 1 Contractor (CSCE):
However, there was a territory-wide air quality issue on the date due to
the dust storm from Mainland China. From the information of the EPD, the Air
Pollution Index (API) at Tai Po exceeded 300 and even reached 500 at some time
during the same monitoring period. The dust exceedance was therefore considered
not due to the Project works.
3.7.
The graphical plots of the air quality monitoring
results are provided in Appendix D.
4.1.
Construction noise monitoring was conducted at 7
monitoring stations for at least once per week during 07:00 – 19:00 in the
reporting period.
4.2.
Figure 2.1 shows the locations of the monitoring
stations. Table 4.1 describes the details of the monitoring stations.
Table
4.1 Locations of Impact Noise
Monitoring Stations
Monitoring Station |
Location |
Description |
NM1 |
|
|
NM2 |
38 Ha Wun Yiu |
1.2m from the ground floor free-field of the
village house |
NM3 |
|
|
NM4 |
|
1m from the exterior of the roof top façade of
Block 4 |
NM5 |
The Paragon |
|
NM6 |
PLK Tin Ka Ping
Primary School |
1.2m ground floor
free-field near the entrance |
NM7 |
Riverain Bayside |
1m from the exterior of the roof façade of the
switch room |
4.3.
The major noise source during the noise monitoring
included construction activities of Stage 1 of the Project, nearby traffic
noise and general school activities.
4.4.
The number of construction noise monitoring events
and exceedances are summarized in Table 4.2 and Table 4.3 respectively.
Table 4.2 Summary of
Number of Monitoring Events for Construction Noise
Monitoring Parameter |
Location |
No. of monitoring events |
Nov 09 – Oct 10 |
||
Construction Noise |
NM1 |
49 |
NM2 |
49 |
|
NM3 |
49 |
|
NM4 |
49 |
|
NM5 |
49 |
|
NM6 |
49 |
|
NM7 |
49 |
Table 4.3 Summary of
Number of Monitoring Exceedances for Construction Noise
Location |
Level of Exceedance |
Level of Exceedance |
|
Nov 09 – Oct 10 |
|||
Construction Noise |
NM1 |
Limit |
0 |
NM2 |
0 |
||
NM3 |
0 |
||
NM4 |
0 |
||
NM5 |
0 |
||
NM6 |
0 |
||
NM7 |
0 |
||
|
Total |
0 |
4.5.
All measured construction noise levels were below the
Limit level and the graphical plots of the trends of the monitoring results are
provided in Appendix F.
4.6.
There were six (6) noise related complaints
followed up by Environmental Team in the reporting period. Hence, six (6)
Action Level exceedances were recorded.
4.7.
The details of the noise related complaints are
described in Section 7, paragraphs 7.3, 7.5, 7.6, 7.10, 7.11 and 7.12 of this
report.
5.1.
Site Inspections were carried out on a weekly basis
to monitor the implementation of proper environmental pollution control and
mitigation measures for Stage 1 of the Project. In the reporting period, 49 and
23 site inspections were carried out for Contract 1 and
Contract 2 of the Project respectively.
5.2.
Particular
observations during the site inspections for Contract 1 are described below:
Air Quality
Noise
Water Quality
Chemical and Waste Management
Landscape and Visual Impact
Miscellaneous
5.3.
All the
observations during the site inspections had been rectified by the Contract 1 Contractor
(CSCE) in the reporting period.
5.4.
Particular
observations during the site inspections for Contract 2 are described below:
Air Quality
Noise
Water Quality
Chemical and Waste Management
Landscape and Visual Impact
5.5.
All the
observations during the site inspections had been rectified by the Contract 2
Contractor (GCL) in the reporting period.
6.1.
There was no 1-hour TSP and construction noise
monitoring exceedance recorded in the reporting period.
6.2.
One (1) Limit Level exceedance of 24-hour TSP
monitoring was recorded in the reporting period. It was considered not Project
related, as mentioned in Section 3.6 of this report.
6.3.
There were six (6) noise related complaints
followed up by Environmental Team in the reporting period. Hence, six (6)
Action Level exceedances were recorded. The details of the exceedances are
described in Section 7, paragraphs 7.3, 7.5, 7.6, 7.10, 7.11 and 7.12 of this
report.
Summary
of Actions Taken in the event of Non-Compliance
6.4.
In the event of non-compliance, actions were taken
in accordance with the Event-Action Plan in the updated EM&A Manual.
Investigation was carried out within three working days of identification of
non-compliance, checking the implementation status of the mitigation measures,
etc. Assessments showed that
the monitoring exceedance was not due to the Project works and therefore no
further action was required to be taken.
7.1.
No notification of summons and prosecutions was
received in the reporting period.
7.2.
Nine (9) environmental complaints were followed up
by Environmental Team in the reporting period.
7.3.
A public complaint about construction noise at Box
Culverts TP4 and TP5 was received from Contractor’s complaint hotline at
09:15am on 19 December 2009. As informed by the Contractor, concrete breaking
works were carrying out at box culverts TP4 and TP5 at the time. Although,
under the Noise Control Ordinance, construction works are permitted during the
period from 07:00am to 07:00pm on Saturdays, to minimize the noise nuisance to
the public, the Contractor had suspended the concrete breaking works at once,
upon receipt of the complaint, until 01:00pm of the date. The temporary noise
barrier opposite to King Nga Court had been erected in accordance with the EP
requirement. Regular impact noise monitoring record at PLK Tin Ka Ping Primary
School (NM6) on 30 December 2009 at 10:15am was 64.4 dB(A). Follow-up site
visit to Wan Tau Tong Estate was carried out on 30 December 2009 at 9:45am. No
noisy construction work was carried out at the time. The Contractor deferred
the noisy construction activities in the morning.
7.4.
A complaint was lodged by Drainage Services
Department on 23 December 2009 regarding muddy water discharged from
construction site into Tai Po River near Shan Tong Road observed during routine
inspection on 16 December 2009. As advised by the Contractor, muddy water
collected in the sump pit on ground level was found leaked to the drainage
system. The Contractor immediately blocked the u-channel to prevent further
leakage on 24 December 2009 and built a metal tank to replace the original soil
type sump pit on 28 December 2009. Water discharged to Tai Po River near Shan
Tong Road was observed clear during the follow-up site inspection on 30
December 2009.
7.5.
EPD, on 20 January 2010, referred a public
complaint about noise nuisance from the highway opposite to Wan Tau Tong
Estate, Wan Lam House from Monday to Saturday starting in the morning until
04:00am at the midnight in the recent 2 months. The complainant did not know if
the noise came from road works or slope maintenance works. As informed by the
Engineer and the Contractor, the Contractor only carried out night works on 12
and 15 January 2010 before 12:00am for unloading plant and material, with a
valid CNP. The noise in midnights is suspected to be related to pavement
resurfacing (routine maintenance) night work, carried out by others. The noise
nuisance in the midnight is considered not Project related. As for the noise
issue at daytime, breaking of box culvert, sheet piling and soil nail works
were carrying out at Retaining Wall W10 and box culverts TP4 and TP5, as
observed during weekly site inspections in December 2009 and January 2010. While temporary noise barrier opposite to
King Nga Court had been erected in accordance with the EP requirement since
early December 2009 and no noise monitoring exceedance was recorded at the
nearest monitoring station - PLK Tin Ka Ping Primary School (NM6) in December
2009 and January 2010, the Contractor was reminded to ensure mitigation measures
are implemented properly.
7.6.
Another noise complaint, also from Wan Lam House,
was referred by HyD about construction works of the Project near Wan Tau Tong
Estate started at 09:00am affecting the public. On 20 January 2010, the
complainant informed that the condition of noise nuisance became worse and
asked if the noise level between 15 January 2010 and 20 January 2010 exceeded
the allowable standard under the EPD permit and he/she also requested for
supporting data. As informed by the Engineer and the Contractor, as well as our
weekly environmental site inspections on 13 and 20 January 2010, demolition of
box culvert by excavator mounted hydraulic breaker was carrying out at box
culverts TP4 and TP5. Temporary noise barrier required under the EP had already
been erected since early December 2009. Also, the Contractor has deferred the
starting time of concrete breaking up operation to 09:00am and 10:00am on
weekdays and Saturday respectively. Weekly noise monitoring in accordance with
the EM&A Manual was scheduled on 11 and 22 January 2010 and no continuous
noise monitoring was required in the EP and EM&A Manual, hence no noise
monitoring result was obtained between 15 and 20 January 2010. Additional noise
monitoring was arranged on 22 January 2010 upon receipt of the complaint. While
no noise monitoring exceedance was recorded at the nearest monitoring station -
PLK Tin Ka Ping Primary School (NM6) in December 2009 and January 2010, the
Contractor was reminded to ensure mitigation measures are implemented properly.
7.7.
Following up with the noise complaint in December
2009, ad hoc monitoring was conducted on 30 December 2009 at King Nga Court –
King Yuet House G/F 2.5m above ground facing Tolo Highway, at 1:15pm during
rock breaking and sheet piling works being taken place. The noise level was
69.6 dB(A), which complied with the noise Limit Level of 75 dB(A).
7.8.
Following up with the noise complaints in January
2010, another ad hoc monitoring was conducted at King Nga Court – King Yuet
House Rooftop 1m façade facing Tolo Highway, during rock breaking being taken
place at box culverts TP4 and TP5 and soil nailing works at Retaining Wall W10
on 22 January 2010 at 10:30, and the noise level (Leq) was 72.9 dB(A), which
complied with the noise Limit Level of 75 dB(A).
7.9.
An anonymous public complaint regarding muddy water
running out from the construction site of HY/2008/09 to existing public
drainage system at Shan Tong Road was received on 21 July 2010. Site inspection
conducted on the same date found that muddy water from vehicle wheel washing
was overflowing the concrete road hump and running off to the public road at
the site entrance of Wall 8. The Contractor was requested to rectify the muddy
water overflowing and to propose preventive measures for muddy runoff. The Contractor
was also recommended to review the methodology of collecting the wheel washing
water to prevent recurrence in the future. During the follow-up site inspection
conducted on 28 July 2010, another concrete road hump (higher in height) to
divert water to a newly constructed temporary water collection pit for
prevention of water from flowing out from the site area had been constructed
behind the gate of the site entrance of Wall 8. No muddy water running out from
the site was observed.
7.10.
A complainant expressed that noisy construction
activities, including road breaking works, at the section of Tolo Highway near
Wun Yiu towards Kowloon had already been started at 07:20am on 7 August 2010
(Saturday). As informed by the Contractor and the Engineer, the noise was
generated from a breaker for breaking an existing retaining wall at Bridge 10A
East Abutment, which started at 07:20am. It was within the non-restricted hours
for general construction work of the Noise Control Ordinance. Although there
was no noise monitoring exceedance recorded at the nearest noise monitoring
station at PLK Tin Ka Ping Primary School and the construction period was in
compliance with the NCO, the Contractor was recommended to take further
mitigation measures to reduce the disturbance to the nearby residents. Upon
receipt of the complaint, an ad-hoc noise monitoring was conducted on 9 August
2010 at 11:15am – 11:45am on the ground floor at King Nga Court. The Leq
(30mins) was 69.3 dB(A) which was within the standard of 75 dB(A).
7.11.
A complainant expressed that noise was generated
from piling and breaking works, with heavy mechanical plants, still taking
place after 07:00pm on 7 August 2010 (Saturday) at the construction site for
expressway construction facing Tai Po, King Nga Court. According to the site
diary provided by the Engineer, no construction work was carried out after
06:00pm on 7 August 2010 (Saturday). Besides, according to the Contractor’s
record, most of the staffs had got off duty before 07:00pm on 7 August 2010.
Noise from heavy mechanical plants was unlikely to be generated from the
Project after 07:00pm on 7 August 2010.
7.12.
A complainant expressed that noise from piling
works began from 07:00am on general days and noise was still generated from
construction works on Sunday. In accordance with the Noise Control Ordinance,
07:00am-07:00pm of any general days are the non-restricted hours of general
construction work. Therefore, commencement of construction work at 07:00am on
general days is in compliance with the NCO. No noise monitoring exceedance was
recorded at the nearest noise monitoring station at PLK Tin Ka Ping Primary
School. However, according to the site diary provided by the Engineer, only
general site cleaning works, without utilizing any mechanical plant, were
carried out by the Contractor’s staffs on Sunday (8 August 2010). The
construction noise was unlikely to be generated from the Project on 8 August
2010 (Sunday).
7.13.
EPD referred a public complaint regarding generation
of construction dust from road extension construction site at Tolo Highway,
near Pun Chun Yuen, and requested follow-up. As informed by the Contract 2
(HY/2009/08) Contractor (GCL), drilling works of pre-bored H-pile at Bridge 12A
(the site opposite to Pun Chun Yuen) was taking place on 17 September 2010 and
mitigation measures taken included circular dust cover surrounding the drill
rod and casing; u-shape tarpaulin sheet covering the mast and drill rod; and
water spraying to suppress the dust. However, there was a period on the date
when water pressure for water spraying was low due to water hose being twisted
and the dust from the drilling works could not be suppressed efficiently.
Although the 24-hour TSP monitoring at Tai Kwong Secondary School Roof/F – AM4
on 17 September 2010 was below the Action Level, the Contractor was advised to
ensure the mitigation measures on dust suppression were implemented properly
throughout their construction activities.
7.14.
Statistics on complaints, notifications of summons
and successful prosecutions are summarized in Appendix F.
8.1.
Only one (1) 24-hour TSP monitoring exceedance was
recorded in the reporting period and it was considered not related to the
Project works. All the rest of the air quality monitoring results in the
reporting period were below the Action Levels established in the baseline air
quality monitoring carried out in October and November 2009. The result was in
line with the Environmental Impact Assessment (EIA) and Environmental Review
Report (ERR) prediction that dust generation would be controlled and would not
exceed the acceptable criteria, with proper implementation of the recommended
dust mitigation measures.
8.2.
No construction noise monitoring exceedance was
recorded in the reporting period. This is generally in line with the EIA and
ERR prediction that with the implementation of noise mitigation measures, the
construction noise from the Project works will meet the stipulated criterion at
the residential NSRs and at a majority of the education institutions, except
that elevated construction noise level at Wong Shiu Chi Middle School (NM3) was
predicted by the EIA and ERR.
9.1.
The environmental monitoring results indicated that
the construction activities in general were in compliance with the relevant
environmental requirements and were environmentally acceptable. Despite the minor deficiencies found during
site audits, the relevant contractor had taken appropriate actions to rectify
deficiencies within reasonable timeframe. Therefore, the effectiveness and
efficiency of the mitigation measures were considered high in most of the time.
9.2.
For all the parameters under monitoring as
mentioned in Section 8, the measured levels were in line with the EIA and ERR
predictions generally. This indicates that the mitigation measures were
effectively implemented.
10.1. The environmental
monitoring methodology was considered well established as the monitoring
results were found in line with the EIA predictions.
10.2. As effective
follow up actions were promptly taken once exceedances were recorded, no
further exceedance occurred for each case. The EM&A programme was
considered successfully and adequately conducted during the course of the
reporting period.
11.1.
The construction phase and EM&A programme of
Stage 1 of the Project commenced on 23 November 2009.
11.2.
Air quality and noise monitoring, and weekly site
inspections were carried out in the reporting period, in accordance with the
updated EM&A manual.
11.3.
All 1-hour TSP monitoring results complied with the
Action / Limit Level in the reporting period. However, one (1) Limit Level
exceedance of 24-hour TSP was recorded, but it was considered not related to
the Project works.
11.4.
There were six (6) noise related complaints
followed up by Environmental Team in the reporting period. Hence, six (6)
Action Level exceedances were recorded. No Limit Level exceedance for
construction noise was recorded at all monitoring stations in the reporting
period.
11.5.
Nine (9) environmental complaints were followed up
by Environmental Team in the reporting period.
11.6.
No notification of summons and prosecution was
received in the reporting period.
11.7.
Mitigation measures had been implemented by the
Contractors to minimize the environmental impacts due to construction
activities. Site inspections carried out by ET and IEC showed that the
Contractors rectified the problems observed promptly and no major environmental
deficiency was induced. The EM&A programme was considered successfully and adequately
conducted during the course of the reporting period.